HomeMy WebLinkAbout20150600 Ver 1_Stormwater Info_20150615Stormwater Impact Analysis Site Plan Submittal For the proposed Crystal Lake Subdivision at Croasdaile Farm Durham, North Carolina Prepared By Stewart Inc. e STEWART March 3, 2015 Table of Contents 1. Table of Contents & Narrative 2. Site Information a. QUAD Map b. FEMA Map c. Soils Map 3. Quantity Calculations a. 1 -Year Peak Flow Analysis b. 2 and 10 Year Peak Flow Analysis c. Detention Basin Sizing 4. Nutrient Loading Calculations a. Jordan Lake Accounting Tool b. City of Durham Nutrient Reporting Form c. TSS Summary 5. Plan Sheets a. SW1.0 - Existing Impervious Areas b. SW2.0 - Proposed Impervious Areas c. SW3.0 - 1 Year Pre - Development Drainage Area Map d. SW4.0 - 2/10 Year Pre Development Drainage Area Map e. SW5.0 - Post Development Drainage Area Map 6. Miscellaneous Information a. Wetlands Study b. City of Durham Site Plan Checklist STORMWATER IMPACT ANALYSIS CRYSTAL LAKE SUBDIVISION AT CROASDAILE FARM DURHAM, NORTH CAROLINA Site Description: Project Location: Garden View Realty is planning to construct a residential subdivision containing single family homes and townhomes on 2 existing contiguous lots totaling approximately 150 -acres of land located north of the intersection of Croasdaile Farm Parkway and Hillandale Road. See Figure 1.0 below. Figure 1.0 - Vicinity Map for Crystal Lake Subdivision Site Characteristics: The site is currently vacant and mostly wooded. There is an existing house and associated driveway directly north of Crystal Lake. There are regulated streams in the southwest portion of the site but will not be impacted by this development. Drainage Area A: There is a ridge that runs the divides the area west of Hillendale into two areas. The northern portion drains to an existing stream that drains in to the Crystal Lake. The southern portion also drains to the existing stream that runs south, and drains in to the Crystal Lake. There is an third drainage area, bordered by Trail Wood Dr, Croasdaile Farm Pkwy and Hillendale Rd, that drains directly in to the Crystal Lake. There is approximately 150 feet of fall across the site with slopes ranging from 10 -20 percent. The western side of the site drains to the stream buffer to the south and will not be affected by this development. Soil Type: ApB, ApC, CfE, CrB, GrB, IrB, IrC, MfB, MfC, PfE, WmD, WxE - Mostly Hydraulic Soil Group B, with some Hydraulic Soil Group D and Hydraulic Soil Group C. See attached Soils Map from Durham County Soils Survey (USDA, SCS - 1971) sheets 16 -17. River Basin: Neuse Watershed: Falls Lake Water Quantity Analysis (Q1 /Q2 /Q10 /Q100): No new development can increase the peak runoff rate from the 1 -yr storm events where it leaves the property. The 1 -yr analysis point and drainage area can be found on sheet SW3.0. There is an existing culvert that runs underneath Ashburn Lane that will be affected by this project. This point was chosen as the 2 and 10 -yr analysis point. The pre and post development drainage areas can be found on sheets SW4.0 and SW5.0 within this report. The SCS method and TR -55 segmental Time of Concentration was used to calculate peak flows for all storm events. For the proposed conditions, a Time of Concentration of 5 minutes was assumed. Composite curve numbers (CN) were calculated using curve numbers for open space, wooded and impervious surfaces. Within the SCS stormwater impact analysis model, Durham County precipitation data and a Type II rainfall distribution were used. Once the pre - development and post - development flow rates were calculated it was determined that a detention basin is necessary to attenuate the post development 1 -year storms back to pre - development conditions at the 1 -year storm analysis point. Additionally, 2 and 10 -year detention will be provided to attenuate the post development peak flow to pre - development conditions at the existing culvert. Summary of Water Quantity Results: The following tables summarize the results from the pre and post development, 1 -year, 2 -year, 10- year pre & post development peak flow rates. Additionally, each table summarizes if detention is required. Wetland A: Table 1.0 — Pre and )ost Peak Flow Rates: 2 Year Storm Event Post - Pre- Development: Detention Post - Development No Detention Required Development: Increase /Decreas Sub -Basin # (cfs) (cfs) (Y/ N) Detention (cfs) e after Detention At Analysis Point 33.34 60.68 Y 22.33 -33% Table 2.0 — Pre and Post Peak Flow Rates: 10 Year Storm Event Wetland B: Post - Pre- Development: Detention Post - Development No Detention Required Development: Increase /Decrease Sub -Basin # (cfs) (cfs) (Y /N) Detention (cfs) after Detention At Analysis Point 63.79 108.12 Y 67.34 5.3% Wetland B: Table 3.0 — Pre and Post Peak Flow Rates: 1 Year 4naiysis Post - Pre- Development: Detention Post - Development No Detention Required Development: Increase /Decreas Sub -Basin # (cfs) (cfs) (Y /N) Detention (cfs) e after Detention 1 -Year Analysis Point 27.83 101.63 Y 25.64 -7.9% Table 4.0 — Pre and Post Peak Flow Rates: 2 Year Storm Event Post - Post - Post Peak Flow Rates: 2 Year Pre- Development: Pre- Development: Detention Post - No Detention Development No Detention Required Development: Increase /Decreas Sub -Basin # (cfs) (cfs) (Y/ N) Detention (cfs) e after Detention At Analysis Point 116.85 128.16 Y 84.56 -27.6% Table 5.0 — Pre and Post Peak Flow Rates: 10 Year Storm Event Post - Table 6.0 — Pre and Post Peak Flow Rates: 2 Year Pre- Development: Detention Post - Development No Detention Required Development: Increase /Decrease Sub -Basin # (cfs) (cfs) (Y /N) Detention (cfs) after Detention At Analysis Point 221.69 216.53 Y 141.44 -36.2% Wetland C: Post - Table 6.0 — Pre and Post Peak Flow Rates: 2 Year Storm Event Development: Detention Post - Development No Detention Pre- Development: Detention Post - (cfs) Development No Detention Required Development: Increase /Decreas Sub -Basin # (cfs) (cfs) (Y /N) Detention (cfs) e after Detention At Analysis Point 114.04 111.36 Y 76.62 -32.8% Table 3.0 — Pre and Post Peak Flow Rates: 10 Year Storm Event Post - Pre- Development: Detention Post - Development No Detention Required Development: Increase /Decrease Sub -Basin # (cfs) (cfs) (Y /N) Detention (cfs) after Detention At Analysis Point 207.04 203.08 Y 179.53 -13.3% Water Quality Analysis (TSS & Nutrient Removal): The site meets the requirement to be classified as a low density project (below 16% in the Falls basin) therefore the project is not required to construct SCMs except for all piped conveyed areas. The site is located within the Upper Falls Basin of the Falls of the Neuse watershed. Per the City of Durham Stormwater Performance Standards the total post development nitrogen export must be limited to 2.2 Ibs /ac /yr and the post development phosphorus export must be limited to 0.33 Ibs /ac /yr. This can be achieved through a combination of onsite removal and purchasing offsite credits. Also, 85% of all TSS from new impervious surface must be removed. In order to meet the onsite removal requirements as well as the TSS requirement, a water quality stormwater control measures has been proposed. Three constructed wetlands are proposed to capture all of the runoff within proposed drainage area as shown on sheet SW5.0. The wetlands have been sized to remove 90 %. Engineer's Conclusion: Because of the increase in the peak flows from the new development three Stormwater Control Measures are needed to attenuate the flows to the pre - development levels at the 1 -yr and 2 /10 -yr analysis points. Three constructed wetlands will capture and treat the site runoff. The proposed SCMs will be designed per NCDENR requirements in order to receive the nutrient and TSS reduction requirements. All peak flow and nutrient calculations have been included within this report. Attachments Miscellaneous Maps • USGS 7.5 Minute Map • Durham County Soils Map • FEMA Floodway ]-Series Maps Support Documents — Pre - Development • SCS Pre Development Flow rates • Composite CN Values • TR -55 Time of Concentration Support Documents — Post Development • SCS Post Development Flow rates • Composite CN Values • TR -55 Time of Concentration Support Documents — Nitrogen Loading • City of Durham Nitrogen Worksheet • Jordan Lake Tool Plan Sheets • Pre - Development Conditions • Post - Development Conditions Submitted 3`d day of March 2015 by STEWART tl`et'tltiu�lrrr►►4 s Li /I v AW - AL 6 Aaron Hutchens = ; Ariel Gamboa, PIE L GA f �rirrrrr�i�<< tt�tt�,, Appendix 2 2. Site Information a. QUAD Map b. FEMA Map C. Soils Map `���� U.S. DEPARTMENT S. GEOLOGIC ERIOR ALSURVEY science for a changing world 79 °00' 36 °07'? 39990[ 5' 10a 820 F 36 °00' 7u -uu, - Produced by the United States Geological Survey North American Datum of 1983 (NAD83) World Geodetic System of 1984 (WGS84). Projection and 1 000 -meter grid: Universal Transverse Mercator, Zone 17S 10 000 -foot ticks: North Carolina Coordinate System of 1983 The National Map USTopo 57'30" 55' NORTHWEST DURHAM QUADRANGLE NORTH CAROLINA 7.5- MINUTE SERIES 78 °52'30" 36 °07'30" Imagery ......................... ..........................NAIP, May 2012 Roads ......................... .....................02006 -2012 TomTom Names ........................... ............................... GNIS, 2012 Hydrography ....................National Hydrography Dataset, 2012 Contours ..... .......................National Elevation Dataset, 2008 Boundaries ....................Census, IBWC, IBC, USGS, 1972 - 2012 8° 57' 159 MILS (N 1° 13' 22 MILS UTM GRID AND 201 = MAGNETIC NORTH DECLINATION AT CENTER OF SHEET U.S. National Grid 100,000 -ra Square ID PV Grid Zone Designation 17S - SCALE 1:24 000 1 0.5 0 KILOMETERS 1 2 1000 500 0 METERS 1000 2000 1 0.5 0 1 MILES 1000 0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 ~ FEET CONTOUR INTERVAL 10 FEET NORTH AMERICAN VERTICAL DATUM OF 1988 This map was produced to conform with the National Geospatial Program US Topic, Product Standard, 2011. A metadata file associated with this product is draft version 0.6.11 55' N-RTH ■ ,fCANA QUADRANGLE LOCATION Caldwell Rougemont Lake Michie Hillsborough Northwest Northeast Durham Durham Chapel Southwest Southeast Hill Durham Durham ADJOINING 7.5' QUADRANGLES 99 60 000 =ET 98 97 96 5' 95 94 93 92 191 2'30" 190 189 188 187000"N 36 °00' is °5x30" ROAD CLASSIFICATION Expressway Local Connector Secondary Hwy Local Road Ramp 4WD • Interstate Route 0 US Route O State Route NORTHWEST DURHAM, NC 2013 850000 FEET 840000 FEET 2010000 FEET Ki:3ilRil]IW 101MlB71101 KI:i�lYli17Y►1 78 °57'30 "W 78 °57'0 "W 78 °56'30 "W 2020000 FEET 78 °56'0 "W 2010000 FEET FLOOD HAZARD INFORMATION SEE FIS REPORT FOR ZONE DESCRIPTIONS AND INDEX MAP THE INFORMATION DEPICTED ON THIS MAP AND SUPPORTING DOCUMENTATION ARE ALSO AVAILABLE IN DIGITAL FORMATAT HTTP: / /FRIS.NC.GOV /FRIS Hydrographic Feature OTHER Limit of Study FEATURES Jurisdiction Boundary 78 °57'30 "W NOTES TO USERS 78 °57'0 "W For information and questions about this map, available products associated with this FIRM including historic versions of this FIRM, how to order products or the National Flood Insurance Program in general, please call the FEMA Map Information eXchange at 1- 877 -FEMA -MAP (1- 877 - 336 -2627) or visit the FEMA Map Service Center website at http: / /msc.fema.gov. An accompanying Flood Insurance Study report, Letter of Map Revision (LOMR) or Letter of Map Amendment (LOMA) revising portions of this panel, and digital versions of this FIRM may be available. Visit the North Carolina Floodplain Mapping Program website at http: / /www.ncf[oodmaps.com or contact the FEMA Map Service Center. Communities annexing land on adjacent FIRM panels must obtain a current copy of the adjacent panel as well as the current FIRM Index. These may be ordered directly from the Map Service Center at the number listed above. For community and countywide map dates refer to the Flood Insurance Study report for this jurisdiction. To determine if flood insurance is available in the community, contact your Insurance agent or call the National Flood Insurance Program at 1- 800 - 638 -6620. Base map information shown on this FIRM was provided in digital format by the North Carolina Floodplain Mapping Program (NCFMP). The source of this information can be determined from the metadata available in the digital FLOOD database and in the Technical Support Data Notebook (TSDN). ACCREDITED LEVEE NOTES TO USERS: If an accredited levee note appears on this panel check with your local community to obtain more information, such as the estimated level of protection provided (which may exceed the 1- percent - annual- chance level) and Emergency Action Plan, on the levee system(s) shown as providing protection. To mitigate flood risk in residual risk areas, property owners and residents are encouraged to consider flood insurance and floodproofing or other protective measures. For more information on flood insurance, interested parties should visit the FEMA Website at http: / /www.fema.gov /business /nfip /index.shtm. PROVISIONALLY ACCREDITED LEVEE NOTES TO USERS: If a Provisionally Accredited Levee (PAL) note appears on this panel, check with your local community to obtain more information, such as the estimated level of protection provided (which may exceed the 1- percent - annual- chance level) and Emergency Action Plan, on the levee system(s) shown as providing protection. To maintain accreditation, the levee owner or community is required to submit the data and documentation necessary to comply with Section 65.10 of the NFIP regulations. If the community or owner does not provide the necessary data and documentation or if the data and documentation provided indicates the levee system does not comply with Section 65.10 requirements, FEMA will revise the flood hazard and risk information for this area to reflect de- accreditation of the levee system. To mitigate flood risk in residual risk areas, property owners and residents are encouraged to consider flood insurance and floodproofing or other protective measures. For more information on flood insurance, interested parties should visit the FEMA Website at http: / /www.fema.gov /business /nfip /index.shtm. LIMIT OF MODERATE WAVE ACTION NOTES TO USERS: For some coastal flooding zones the AE Zone category has been divided by a Limit of Moderate Wave Action (LiMWA). The LiMWA represents the approximate landward limit of the 1.5 -foot breaking wave. The effects of wave hazards between the VE Zone and the LiMWA (or between the shoreline and the LiMWA for areas where VE Zones are not identified) will be similar to, but less severe than those in the VE Zone. Limit of Moderate Wave Action (LiMWA) COASTAL BARRIER RESOURCES SYSTEM (CBRS) NOTE This map may include approximate boundaries of the CBRS for informational purposes only. Flood insurance is not available within CBRS areas for structures that are newly built or substantially improved on or after the date(s) indicated on the map. For more information see http:// www. fws. gov/ habitatconservation /coastal_barrier.htmi, the FIS Report, or call the U.S. Fish and Wildlife Service Customer Service Center at 1- 800 - 344 -WILD. CBRS Area r,\ � \ ; ,\r Otherwise Protected Area 78 °56'30 "W SCALE Map Projection: North Carolina State Plane Projection Feet (Zone 3200) Datum: NAD 1983 (Horizontal), NAVD 1988 (Vertical) 1 inch = 500 feet 1:6,000 0 250 500 1,000 Feet Meters 0 75 150 300 PANEL LOCATOR PERSON COUNTY 0940 0910 i��'�i�i� I G73. 1 0819 !- 0828 0848 1b818 st 0807 J 0817 0827 0837 0847 085+ GRANVILLE COUNTY 08061 0816 0826 0836 0846 085: --i 0805 0815 0825 0835 0845 085, 0865 ORANGE COUNTY �N 0804 U8d4 0824 0834 0844 0854 0864 -0 &74 -� 0903 0813 0823 0833 0843 0853 0863 0873 0883 0812 0822 0832 0842 0852 0862 0811 0821 0831 0841 0851 0861 0871 989010800 0810 0820 0830 0840 0850 0860 0870 979911I0709 Without Base Flood Elevation (BFE) 0729 0739 Zone A, V, A99 9798 0708 With BFE or Depth zone AE, A0, AH, VE, AR SPECIAL FLOOD Regulatory Floodway HAZARD AREAS 0.2% Annual Chance Flood Hazard, Areas 9797 0707 of 1% Annual Chance Flood with Average 0727 0737 Depth Less Than One Foot or With Drainage Areas of Less Than One Square Mile zone x 0716 Future Conditions 1% Annual Chance Flood Hazard zone x OTHER AREAS OF �_ Area with Reduced Flood Risk due to Levee FLOOD HAZARD See Notes zone x OTHER Areas Determined to be Outside the AREAS 0.2% Annual Chance Floodplain zone x ------- - - - - -- Channel, Culvert, or Storm Sewer ' ' ' ' ' ' ' ' ' • 1 Accredited or Provisionally Accredited GENERAL Levee, Dike, or Floodwall STRUCTURES Non - accredited Levee, Dike, or Floodwall BM5510 X North Carolina Geodetic Survey bench mark BM5510 ® National Geodetic Survey bench mark BM5510� Contractor Est. NCFMP Survey bench mark Cross Sections with 1% Annual Chance Water Surface Elevation (BFE) sa - - - - - Coastal Transect - -- - -- Coastal Transect Baseline Profile Baseline Hydrographic Feature OTHER Limit of Study FEATURES Jurisdiction Boundary 78 °57'30 "W NOTES TO USERS 78 °57'0 "W For information and questions about this map, available products associated with this FIRM including historic versions of this FIRM, how to order products or the National Flood Insurance Program in general, please call the FEMA Map Information eXchange at 1- 877 -FEMA -MAP (1- 877 - 336 -2627) or visit the FEMA Map Service Center website at http: / /msc.fema.gov. An accompanying Flood Insurance Study report, Letter of Map Revision (LOMR) or Letter of Map Amendment (LOMA) revising portions of this panel, and digital versions of this FIRM may be available. Visit the North Carolina Floodplain Mapping Program website at http: / /www.ncf[oodmaps.com or contact the FEMA Map Service Center. Communities annexing land on adjacent FIRM panels must obtain a current copy of the adjacent panel as well as the current FIRM Index. These may be ordered directly from the Map Service Center at the number listed above. For community and countywide map dates refer to the Flood Insurance Study report for this jurisdiction. To determine if flood insurance is available in the community, contact your Insurance agent or call the National Flood Insurance Program at 1- 800 - 638 -6620. Base map information shown on this FIRM was provided in digital format by the North Carolina Floodplain Mapping Program (NCFMP). The source of this information can be determined from the metadata available in the digital FLOOD database and in the Technical Support Data Notebook (TSDN). ACCREDITED LEVEE NOTES TO USERS: If an accredited levee note appears on this panel check with your local community to obtain more information, such as the estimated level of protection provided (which may exceed the 1- percent - annual- chance level) and Emergency Action Plan, on the levee system(s) shown as providing protection. To mitigate flood risk in residual risk areas, property owners and residents are encouraged to consider flood insurance and floodproofing or other protective measures. For more information on flood insurance, interested parties should visit the FEMA Website at http: / /www.fema.gov /business /nfip /index.shtm. PROVISIONALLY ACCREDITED LEVEE NOTES TO USERS: If a Provisionally Accredited Levee (PAL) note appears on this panel, check with your local community to obtain more information, such as the estimated level of protection provided (which may exceed the 1- percent - annual- chance level) and Emergency Action Plan, on the levee system(s) shown as providing protection. To maintain accreditation, the levee owner or community is required to submit the data and documentation necessary to comply with Section 65.10 of the NFIP regulations. If the community or owner does not provide the necessary data and documentation or if the data and documentation provided indicates the levee system does not comply with Section 65.10 requirements, FEMA will revise the flood hazard and risk information for this area to reflect de- accreditation of the levee system. To mitigate flood risk in residual risk areas, property owners and residents are encouraged to consider flood insurance and floodproofing or other protective measures. For more information on flood insurance, interested parties should visit the FEMA Website at http: / /www.fema.gov /business /nfip /index.shtm. LIMIT OF MODERATE WAVE ACTION NOTES TO USERS: For some coastal flooding zones the AE Zone category has been divided by a Limit of Moderate Wave Action (LiMWA). The LiMWA represents the approximate landward limit of the 1.5 -foot breaking wave. The effects of wave hazards between the VE Zone and the LiMWA (or between the shoreline and the LiMWA for areas where VE Zones are not identified) will be similar to, but less severe than those in the VE Zone. Limit of Moderate Wave Action (LiMWA) COASTAL BARRIER RESOURCES SYSTEM (CBRS) NOTE This map may include approximate boundaries of the CBRS for informational purposes only. Flood insurance is not available within CBRS areas for structures that are newly built or substantially improved on or after the date(s) indicated on the map. For more information see http:// www. fws. gov/ habitatconservation /coastal_barrier.htmi, the FIS Report, or call the U.S. Fish and Wildlife Service Customer Service Center at 1- 800 - 344 -WILD. CBRS Area r,\ � \ ; ,\r Otherwise Protected Area 78 °56'30 "W SCALE Map Projection: North Carolina State Plane Projection Feet (Zone 3200) Datum: NAD 1983 (Horizontal), NAVD 1988 (Vertical) 1 inch = 500 feet 1:6,000 0 250 500 1,000 Feet Meters 0 75 150 300 PANEL LOCATOR PERSON COUNTY 0940 0910 i��'�i�i� I G73. 1 0819 !- 0828 0848 1b818 st 0807 J 0817 0827 0837 0847 085+ GRANVILLE COUNTY 08061 0816 0826 0836 0846 085: --i 0805 0815 0825 0835 0845 085, 0865 ORANGE COUNTY �N 0804 U8d4 0824 0834 0844 0854 0864 -0 &74 -� 0903 0813 0823 0833 0843 0853 0863 0873 0883 0812 0822 0832 0842 0852 0862 0811 0821 0831 0841 0851 0861 0871 989010800 0810 0820 0830 0840 0850 0860 0870 979911I0709 0719 0729 0739 0749 0759 0769 0,779 0789 9798 0708 0718 0728 0738 0748 07j58 0768 0778 / 9797 0707 0717 0727 0737 0747 ,0757 WAKE COUNTY 9796 0706 0716 I CHATHAM COUNTY i i W 1< w 0• w . « A My3 ,ter KZ:3�.'YIlY►1 36 °4'30 "N 36 °4'0 "N 36 °3'30 "N 78 °56'0 "W 2020000 FEET OR7 11CAROt.I\ l ' Cooperatin "f'ee�linical Stake 850000 FEET 840000 FEET This digital Flood Insurance Rate Map (FIRM) was produced through a unique cooperative partnership between the State of North Carolina and the Federal Emergency Management Agency (FEMA). The State of North Carolina has implemented a long term approach to floodplain management to decrease the costs associated with flooding. This is demonstrated by the State's commitment to map flood hazard areas at the local level. As a part of this effort, the State of North Carolina has joined in a Cooperating Technical State agreement with FEMA to produce and maintain this digital FIRM. E cc S� �rW 0 S� Q. V cc V 0 0 cc a 0 ._ Z NORTH CAROLINA FLOODPLAIN MAPPING PROGRAM NATIONAL FLOOD INSURANCE PROGRAM FLOOD INSURANCE RATE MAP NORTH CAROLINA ep� PANEL 0814 o �Ft -IND SV,C,'��. Panel Contains: COMMUNITY DURHAM COUNTY DURHAM, CITY OF CID PANEL SUFFIX 370085 0814 J 370086 0814 J MAP NUMBER 3720081400J MAP REVISED 05/02/06 840000 FEET 830000 FEET 2010000 FEET 1011- SY1}Y►1 KI:3i�aBi�lY►1 Ki:Vxljii► 78 °57'30 "W 78 °57'0 "W 78 °56'30 "W 2020000 FEET 78 °56'0 "W 2010000 FEET FLOOD HAZARD INFORMATION 78 °57'30 "W NOTES TO USERS 78 °57'0 "W SCALE 78 °56'30 "W SEE FIS REPORT FOR ZONE DESCRIPTIONS AND INDEX MAP For information and questions about this map, available products associated with this FIRM including historic versions of this FIRM, how to order products or the National Flood Insurance Program in general, Map Projection: THE INFORMATION DEPICTED ON THIS MAP AND SUPPORTING please call the FEMA Map Information eXchange at 1- 877 -FEMA -MAP (1- 877 - 336 -2627) or visit the FEMA Map North Carolina State Plane Projection Feet (Zone 3200) DOCUMENTATION ARE ALSO AVAILABLE IN DIGITAL FORMATAT Service Center website at http: / /msc.fema.gov. An accompanying Flood Insurance Study report, Letter of Map Datum: NAD 1983 (Horizontal), NAVD 1988 (Vertical) Revision (LOMR) or Letter of Map Amendment (LOMA) revising portions of this panel, and digital versions of this H 1 T 1 T P: / /FRIS.NC.GOV /FRIS FIRM may be available. Visit the North Carolina Floodplain Mapping Program website at http: / /www.ncf[oodmaps.com 1 inch = 500 feet 1'6 000 or contact the FEMA Map Service Center. , Without Base Flood Elevation (BFE) Communities annexing land on adjacent FIRM panels must obtain a current copy of the adjacent panel as well as 250 500 1 ,000 Zone A, V, A99 the current FIRM Index. These may be ordered directly from the Map Service Center at the number listed above. With BFE or Depth zone AE, AO, AH, VE, AF? Feet For community and countywide map dates refer to the Flood Insurance Study report for this jurisdiction. Meters FLOOD Regulatory Floodway To determine if flood insurance is available in the community, contact your Insurance agent or call the National 0 75 150 300 HAZARD AREAS Flood Insurance Program at 1 -800- 638 -6620. 0.2% Annual Chance Flood Hazard, Areas Base map information shown on this FIRM was provided in digital format by the North Carolina Floodplain Mapping Program (NCFMP). The source of this information can be determined from the metadata available in the PANEL LOCATOR of 1% Annual Chance Flood with Average digital FLOOD database and in the Technical Support Data Notebook (TSDN). Depth Less Than One Foot or With Drainage ACCREDITED LEVEE NOTES TO USERS: If an accredited levee note appears on this panel check with your local Areas of Less Than One Square Mile zone X community to obtain more information, such as the estimated level of protection provided (which may exceed the 1- percent - annual- chance level) and Emergency Action Plan, on the levee system(s) shown as providing protection. PERSON COUNTY o To mitigate flood risk in residual risk areas, property owners and residents are encouraged to consider flood Future Conditions 1 /o Annual insurance and floodproofing or other protective measures. For more information on flood insurance, interested U' OTHER AREAS OF y�� ���.� Chance Flood Hazard zone X parties should visit the FEMA Website at http: / /www.fema.gov /business /nfip / index.shtm. oy :.tr 1 0940 �',. ' I Area with Reduced Flood Risk due to Levee PROVISIONALLY ACCREDITED LEVEE NOTES TO USERS: If a Provisionally Accredited Levee (PAL) note FLOOD HAZARD appears on this panel, check with your local community to obtain more information, such as the estimated level of See Notes Zone X protection provided (which may exceed the 1- percent - annual- chance level) and Emergency Action Plan, on the 0819 OTHER levee system(s) shown as providing protection. To maintain accreditation, the levee owner or community is -r— 0828 0848 Areas Determined to be Outside the required to submit the data and documentation necessary to comply with Section 65.10 of the NFIP regulations. 19818 AREAS o If the community or owner does not provide the necessary data and documentation or if the data and documentation 0.2 /o Annual Chance Floodplain zone X provided indicates the levee system does not comply with Section 65.10 requirements, FEMA will revise the flood GRANVILLE COUNTY hazard and risk information for this area to reflect de- accreditation of the levee system. To mitigate flood risk in 10807,"0817 0827 0837 0847 085 Channel Culvert or Storm Sewer s s residual risk areas, property owners and residents are encouraged to consider flood insurance and floodproofing ' ' ' ' ' ' ' ' ' ' ' ' Accredited or Provisionally Accredited or other protective measures. For more information on flood insurance, interested parties should visit the FEMA 08061 0816 0826 0836 0846 085 Website at http: / /www.fema.gov /business /nfip /index.shtm. —j GENERAL Levee, Dike, or Floodwall 0805 0815 0825 0835 0845 085 0865 LIMIT OF MODERATE WAVE ACTION NOTES TO USERS: For some coastal flooding zones the AE Zone STRUCTURES Non- accredited Levee, Dike, or Floodwall category has been divided by a Limit of Moderate Wave Action (LiMWA). The LiMWA represents the approximate ORANGE COUNTY 1 �N ___ —_` landward limit of the 1.5 -foot breaking wave. The effects of wave hazards between the VE Zone and the LiMWA 0804 0814 0824 0834 0844 0854 0864, -0 8&-74 BM5510 X North Carolina Geodetic Survey bench mark (or between the shoreline and the LiMWA for areas where VE Zones are not identified) will be similar to, but less 1 severe than those in the VE Zone. 0903 @81 0823 0833 0843 0853 0863 0873 0883 BM5510 ® National Geodetic Survey bench mark f Limit of Moderate Wave Action (LiMWA) BM5510 Contractor Est. NCFMP Survey bench mark 802 0812 0822 0832 0842 0852 0862 0872 08821 � 1 012 1.8.2— Cross Sections with 1% Annual Chance COASTAL BARRIER RESOURCES SYSTEM (CBRS) NOTE 6801 0811 0821 0831 0841 0851 0861 0871 08s1 This map may include approximate boundaries of the CBRS for informational purposes only. Flood insurance is not Water Surface Elevation (BFE) available within CBRS areas for structures that are newly built or substantially improved on or after the date(s) 9890 0800 0810 0820 0830 0840 0850 0860 0870 0880 indicated on the map. For more information see http:// www. fws. gov/ habitatconservation /coastal_barrier.html, the sa - - - - - Coastal Transeet FIS Report, or call the U.S. Fish and Wildlife Service Customer Service Center at 1- 800 - 344 -WILD. j \ \ 9799 0709 0719 0729 0739 0749 0759 0769 0,779 0789 - -- - -- Coastal Transect Baseline ������� CBRS Area �r Otherwise Protected Area I 9798 0708 0718 0728 0738 0748 07j58 0768 0778 Profile Baseline 1 1 9797 0707 0717 0727 0737 0747 ,0757 WAKE COUNTY Hydrographic Feature 1 9796 0706 0716 j OTHER Limit of Study CHATHAM COUNTY I j / FEATURES Jurisdiction Boundary 1< W w 0* AA, 7 36 °3'0 "N 36 °2'30 "N 36 °2'0 "N 78 °56'0 "W 2020000 FEET ,jam V 1RHiC:tROf-D l I` Cooperating "Fedinical State 840000 FEET 830000 FEET This digital Flood Insurance Rate Map (FIRM) was produced through a unique cooperative partnership between the State of North Carolina and the Federal Emergency Management Agency (FEMA). The State of North Carolina has implemented a long term approach to floodplain management to decrease the costs associated with flooding. This is demonstrated by the State's commitment to map flood hazard areas at the local level. As a part of this effort, the State of North Carolina has joined in a Cooperating Technical State agreement with FEMA to produce and maintain this digital FIRM. r-- r'� M �W 0 CL V 0 0 0 ■� Z NORTH CAROLINA FLOODPLAIN MAPPING PROGRAM NATIONAL FLOOD INSURANCE PROGRAM FLOOD INSURANCE RATE MAP NORTH CAROLINA ep� PANEL 0813' �Ft-IND Skc'��. EEN1.A Panel Contains: COMMUNITY DURHAM COUNTY DURHAM, CITY OF CID PANEL SUFFIX 370085 0813 1 370086 0813 1 MAP NUMBER 3720081300J MAP REVISED 05/02/06 i DURHAM COUNTY, NORTH CAROLINA — SHEET NUMBER 16 (Joins sheet 12) _ i _. TaE W . a TaE I - 0 /'l /1' - -... � APf. N 7 W, iii ' - � � 7' _ a 4� GeB � _V.- -- � t TaE GeC%`` �r {;%' ,�t -i•L •.7.., _� APB k y MfB • -.�. II RlVi �i iaE - Ge8 .�F. 1 --' - GeB �'''`! �� _ A :t ��� ! fir, } � G ; - °i ,Gx. .ref: _ l - - - _ +�nG I f7 is`/ m 4. U 1 t Y �, _ �. - u-r �:y ;+ :yz� ;"1 i TaE ;i: -fJ GIB _ # f HrB r 1 CfE - G'rB 4_a �1 " -MfB § +f I r f- �� / Q� fI I � >• .: d � � � ? < .. ' Gel -- .. cfc F GeE3 t f3 q � Hr6. 7-c f" . f All .`fief. j ff ✓ jc ' GeC r MfB e_ f` f r i TaE ; G 3 _ /( f , GeC 1 # ' GeB <�r1:� "- A�' ��.°`_' -,; y `"ti • ,�� ��: i'�'- ---- r' ty� O = gut dsti: t _ -_ Mf � � To .� � t I. I � C {. � �. -'� ,w1 Q H F FfrC HrC [.;;E, i 1 Mfc J %1 Gog ,I'� / lti ! c, O GeC ;rte aif� 3 r w; j 4MfFx i1 'y - � .( - -- .i• �j'�- G1E SS - G ®C S Ge#].I p� 1 GeC - 1 t s .•'`� 1 TaE Hr8 GeC GeC..3 J n 00 27- in 1 - - O D� �' �f BC. IYC GIF _ �1'iL4T+s£ i tlrk il: WsH Z - P u 1 • _ ,: cn • { `¢ = �i�'1 - - � i � y � s I GeB GeD � % MfC '• GeCI �,t..:i,.. Apf=' -� 3eE GeC CL (. S U°o t � GeC Q \ APO Huckleberry Spnng r 3 * He8 f..� f _ a r mu �r�:, •. �. _ �:',� F .i'�+' .r� 1` ,r I Ap qpB = _ ✓ � -..III _ C +r � � GIB o —' - GeC GrB N APC -- k {rC` �� Hr6 � ,f C FTaE ki, i k l Ws6 o f_ GeC j_ MrE GeC- a t APB ;keC ! GeL° f �� Cr43 GrB z' �� ~� • APB P Ar W A C - 0A. A'�B�'• Btlf5 v-, APB � o 1 1 I WSB f' H e B - l� a '- fr. App W5L` "'�Y1f5C r t �� r sasr ti� ypA GIB i CrB S C v `A i w 2 OW 000 FEET (Joins slmef ?d) q`pg - �. - -- ]BYP� Val DURHAM COUNTY, NORTH CAROLINA — SHEET NUMBER 17 02 13 rii l: -r l'�t1 Hxr C,� ._ P+1f[a _Mtt -- - W4B I (Joins sheet 13l �] WsC C 10 Ir HrB Hr .. s - .. wmE r C I MfC j_ - I(� � c � r �w APB IB: . ;r ''.,�; NdsB ' k r` �'-°�, .�G U T I r: � v Ch I Ir L B J Mf8 hfi8 ( tkii; �MfC h9fR a'C ' f f fj' _ �* "GV i lffi"• N bp -- 1 UB Rtl f D-, \, hl r 6 r M f C LL t 3MuB Mf .p I� ifc B Ws8 (, u Mfp y Ir8 rB l } _ 1ti1�J1 i U r-' S$ r� '�'F r` MfB, y�`' �''� �' Ur 'j Ir T� Ws6= - MfB,i sB jtt i Ch WxE WsB „tr� o ` f 1 } t Ire I y o IrB -.I IyiE.6 a,r MfB• ie +- - -'" T1 W E �. r 4 MfB ^,,.`• 1 trC 1 - _ .04 C '1* w5 _ ° ii WsC i a r \} cr, MfC - � }- MfC -, WY MfB 'c - 1� \ r i Rr mfc Cho r5 . r i Ws6 J ti WsB \ Q -, � � Mf r `• 'i ( I1 r WsB a,;, L WIC M f C kil } CrC Mf _•� •r` :�' , ---�: ti r� - _ F Cr6 6 � z rovc : — t ,3 f Mill G � � _ Mr .� j � Y f` �� _- WxE wsui r' 11. B '1 (rut h1}Cj'4 tR'±cBY IuB Ira 4 1� NsB fi 11 Weaver : ,. Or MfC f r MfB 1 Mf6 its 9C _ '{ f- C, Cr6 CG Ws6 He F1 0 s �- v WsB .. I, / 19 1 ftr �. o,MC� -- .�.r -- •-, WYE Wn,r F. �, %./' : x,..... � Jj� 1 [r ii JW..0 Ir€� r ! �1YwC f �I� k.F" Mf6 /l on H i V f err ' k f y '_�� , y 7 f I l v, y �. „p I .'` Y 1 .+ .'.* b ivf —: \, ✓ �f~ Y i... /"'. r Ws6 r .: ✓ %' - IuB r i ``..,.. �1 IuB �;.. . r. J4, <.,,•,fC fMffft. I'•1,. W.: I .t::' iti . ., +' 4 .. •f L.r � -"r-_. •r ' I 4uB - -• 1; n o. Ea f, y � 'h [' _. � i � ':Vra � CrB /'-J i k t �_ ' ' � _ r •3 ,,ri. 'I � l 1',� lhairy _ +< _ �. - f , r, `, Ir $ , ,,' , • J ..; _- .. r , t r :. '` ` M atri ��f y� V'rll'� - FB J�qI t^ E 1. WwC Y CrB hS`[ A4fC_ �!R T 1 1 Vv•,P= ! CrB m' Iss { ,• 5 Ira MuC IliFS wsB J o C I ✓ / by s e U. ° y �`�' l ; t' 00 CrB -` I e ri1rF ` i ^tr'r�' Jl ¢ = Ws B tm,, 3 cv F wn I� .., �:3/ I ," '' , ,.`�: ..- r-•� -� ` �, �'�s.rh';4' Braggto �. Ch -_ I - •�, :: - _, .: a ,, �. ",,.� srEi • - - �. � r �` IrC `' � `a ) �� -f; r•- } " II F� xUr r wy VISB 4 i O r , i • +J� _ -- Cr8 i' [rCtll (y PfE Ws6 1�! ., '. , 0 Cr6 R `" .` WwC Ct r Wy zE WsB �.` - iy .,; w r$ r a 0 Mfc / t, _ tw M 9 F W s B "VAC f w_ w C MfB Ur f �. F"`r�— WsB \ ♦ e�� ✓'" � I .. MfC / r '� ?' WsC r ci r i 4 vlry(( III y �. yI -r w Ur AIA MrC _ --yy I' "fr� '•,-,/ y�r ^s 6' wwc 1 lam! j - ` wwc -- BYP i 501 a•O BJ �-- . M (€] - ._.:.Y, - _ C.ho `s\�/7r+ ' -' l W SC` C �i I 11e6 _= URHAM Cr ,^ ✓f (county seat) ;,.W:vC trSEE �'II V�wC I (Jo ins sheet 2 1) 5 Ra Appendix 3 3. Quantity Calculations a. 1 -Year Peak Flow Analysis b. 2 and 10 Year Peak Flow Analysis c. BMP Sizing for peak flow and water quality. Year Peak Flow Analysis Hydrograph Summary Report 2 726 279,788 - - - - -- Hydraflow Hydrographs Extension for AutoCAD®Civil 3D@2015 by Autodesk, Inc. v10.4 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 86.83 2 726 279,788 - - - - -- - - - - -- - - - - -- Pre Development DA'B' 2 SCS Runoff 27.83 2 728 99,307 - - - - -- - - - - -- - - - - -- Pre Dev DA'B' 1 -YR 4 SCS Runoff 73.49 2 716 153,094 - - - - -- - - - - -- - - - - -- Post Development DA'B' 5 SCS Runoff 41.97 2 726 135,223 - - - - -- - - - - -- - - - - -- POST DEV AREA —B BYPASS 7 Reservoir 25.64 2 724 149,876 4 357.98 52,858 Constructed Wetland 8 Combine 67.48 2 724 285,098 5,7 - - - - -- - - - - -- COMBINE 10 Combine 101.63 2 718 288,317 4, 5, - - - - -- - - - - -- POST DEV NO DETENTION PrePost B Site Plan.gpw Return Period: 1 Year ` Tuesday, 03 / 3 / 2015 STFWART Project: Crystal Lake Date: 03.03.15 Project No: C 13098 By: ACH Composite CN Values - Drainage Area 'B' 1 -YR Pre Development Analysis lPre- Development 1 -Year Analysis Surface SCS CN Impervious 98 Open Space 80 lWooded 77 _> Total Area 11 => Composite SCS CN Value Area (ac) Comments 0.96 assume good condition 0.10 assume good condition 22.75 assume good condition 23.81 ac 78 i+ ,"�il S T E'WA R T TR 55 Time of Concentration Worksheet Project Crystal Lake Calculated By AH Date 03.03.15 Location Area B Culvert Checked By AG Revised - Flow length, L in ft Pre - development Condition 1 Year Storm Analysis Sheet Flow 0.036 Segment ID 1 Subtotal 1 Surface Description Open Space 2 Mannings Roughness, n 0.23 3 Flow Length, L in ft (max 300') 75 4 Two -year 24 -hr rainfall, P2 in inches 3.5 5 Land Slope, s in ft/ft 0.040 6 Tt = 0.007x(nL) ^0.8 /(P2A0.5xsA0.4) in hr 0.132 0.132 Shallow Concentrated Flow 7 8 9 10 11 Segment ID 2 Surface description (paved or unpaved) Unpaved Flow length, L in ft 2662 Watercourse slope, s in ft/ft 0.036 Average velocity, V in ft/s (figure 3 -1) 3 Tt= L /3600V in hr 0.246 0.246 Channel Flow Segment ID 12 Cross Sectional flow area, a in ftA2 13 Wetted perimeter, pw in ft 14 Hydraulic radius, r =a /pw in ft 15 Channel slope, s in ft/ft 16 Manning's roughness, n 17 V= 1.49xrA0.667xsA0.5/n in ft/s 18 Flow length, L in ft 19 Tt= L/3600V, in hr 0.000 20 Watershed total Tc in hours 0.379 21 Watershed total Tc in minuets 22.7 See page 30 of TR -55 Manual. 2662 Pre Area B 1 -YR J: \C13098 - Croasdaile Farm SF \CALCS AND DATA \Stormwater \Spreadsheets \C13098_Tc.xls Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Hyd. No. 2 Pre Dev DA 'B' 1 -YR Hydrograph type = SCS Runoff Peak discharge Storm frequency = 1 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 23.810 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 3.00 in Distribution Storm duration = 24 hrs Shape factor Pre Dev DA W 1 -YR Q (cfs) Hyd. No. 2 -- 1 Year 28.00 24.00 20.00 16.00 12.00 11 4.00 Monday, 03 / 2 / 2015 = 27.83 cfs = 728 min = 99,307 cuft = 78 = Oft = 22.70 min = Type II = 484 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 Hyd No. 2 Q (cfs) 28.00 24.00 20.00 16.00 12.00 F-WIT11 4.00 ,%- 0.00 1440 1560 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Monday, 03 / 2 / 2015 Hyd. No. 4 Post Development DA 'B' Hydrograph type = SCS Runoff Peak discharge = 73.49 cfs Storm frequency = 1 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 153,094 cuft Drainage area = 21.720 ac Curve number = 91 * Basin Slope = 0.0% Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.00 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 " Composite (Area /CN) = [(10.510 x 98) + (9.230 x 80) + (0.770 x 77)] / 21.720 Post Development DA W Q (cfs) Hyd. No. 4 -- 1 Year Q (cfs) 80.00 80.00 70.00 70.00 60.00 60.00 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 ii 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 Hyd No. 4 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Monday, 03 / 2 / 2015 Hyd. No. 7 Constructed Wetland Hydrograph type = Reservoir Peak discharge = 25.64 cfs Storm frequency = 1 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 149,876 cuft Inflow hyd. No. = 4 - Post Development DA'B' Max. Elevation = 357.98 ft Reservoir name = POND B Max. Storage = 52,858 cuft Storage Indication method used Constructed Wetland Q (cfs) Hyd. No. 7 -- 1 Year Q (cfs) 80.00 80.00 1 70.00 70.00 60.00 60.00 50.00 50.00 40.00 40.00 30.00 i 30.00 20.00 20.00 10.00 i i 10.00 S 0.00 i - - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) Hyd No. 7 111111-1 Hyd No. 4 1����� Total storage used = 52,858 Cuft 21 10 Year Peak Flow Analysis 1 SCS Runoff 33.34 1 Hydrograph Summary Report - - - - -- - - - - -- Pre Development DA W 3 SCS Runoff Hydraflow Hydrographs Extension for AutoCAD®Civil 3D@2015 by Autodesk, Inc. v10.4 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 33.34 2 722 87,393 - - - - -- - - - - -- - - - - -- Pre Development DA W 3 SCS Runoff 46.24 2 716 93,423 - - - - -- - - - - -- - - - - -- Post Development DA W 4 SCS Runoff 16.22 2 722 42,519 - - - - -- - - - - -- - - - - -- POST DEV AREA —A BYPASS 6 Reservoir 6.695 2 728 93,402 3 398.51 40,505 Constructed Wetland 7 Combine 22.33 2 722 135,921 4,6 - - - - -- - - - - -- COMBINE 9 Combine 60.68 2 718 135,942 3, 4, - - - - -- - - - - -- POST DEV NO DETENTION PrePost A Site Plan.gpw Return Period: 2 Year ` Tuesday, 03 / 3 / 2015 STEWART Project: Crystal Lake Date: 03.03.15 Project No: C13098 By: ACH Development Composite CN Values - Drainage Area'A'Pre Pre- Development Area A Surface SCS CN Area (ac) Comments Impervious 98 0 assume good condition Open Space 80 0.00 assume good condition l Wooded 77 16.32 assume good condition _> Total Area 16.32 ac 11 => Composite SCS CN Value 77 J STFWART Project: Crystal Lake Date: 03.03.15 Project No: C 13098 By: ACH Composite CN Values - Drainage Area 'A' Post Development Bypass Analysis Post Development Bypass Analysis Surface SCS CN Area (ac) Comments Impervious 98 3.75 assume good condition Open Space 80 12.50 assume good condition l Wooded 77 28.14 assume good condition _> Total Area 44.39 ac 11 => Composite SCS CN Value 80 1 rou"'Aw STEWART Proj:cl: Crystal Lake Date: 03.03.15 Proj C, No: C13098 By: ACH Composite CN Values - Drainage Area to POND A Post Development Analysis Post Development Analysis POND Surface SCS CN Area lac) Comments Impervious 98 2.42 assume good condition Open Space 80 7.94 assume good condition l Wooded 77 5.04 assume good condition => Total Area 15.40 ac 11 => Composite SCS CN Value 82 ,"�il S T E'WA R T TR 55 Time of Concentration Worksheet Project Crystal Lake Calculated By AH Date 03.03.15 Location Area A Checked By AG Revised - Flow length, L in ft Pre - development Condition -2 and 10 Year Storm Analysis Sheet Flow 0.054 Segment ID 1 Subtotal 1 Surface Description Open Space 2 Mannings Roughness, n 0.23 3 Flow Length, L in ft (max 300') 75 4 Two -year 24 -hr rainfall, P2 in inches 3.5 5 Land Slope, s in ft/ft 0.080 6 Tt = 0.007x(nL) ^0.8 /(P2A0.5xsA0.4) in hr 0.100 0.100 Shallow Concentrated Flow 7 8 9 10 11 Segment ID 2 Surface description (paved or unpaved) Unpaved Flow length, L in ft 1347 Watercourse slope, s in ft/ft 0.054 Average velocity, V in ft/s (figure 3 -1) 3.8 Tt= L /3600V in hr 0.098 0.098 Channel Flow Segment ID 12 Cross Sectional flow area, a in ftA2 13 Wetted perimeter, pw in ft 14 Hydraulic radius, r =a /pw in ft 15 Channel slope, s in ft/ft 16 Manning's roughness, n 17 V= 1.49xrA0.667xsA0.5/n in ft/s 18 Flow length, L in ft 19 Tt= L/3600V, in hr 0.000 20 Watershed total Tc in hours 0.199 21 Watershed total Tc in minuets 11.9 See page 30 of TR -55 Manual. Pre Area A J: \C13098 - Croasdaile Farm SF \CALCS AND DATA \Stormwater \Spreadsheets \C13098_Tc.xls ,"�il S T E'WA R T TR 55 Time of Concentration Worksheet Project Crystal Lake Calculated By AH Date 03.03.15 Location Area A Checked By AG Revised - Flow length, L in ft Post development Condition -2 and 10 Year Storm Analysis - Bypass Sheet Flow 0.054 Segment ID 1 Subtotal 1 Surface Description Open Space 2 Mannings Roughness, n 0.23 3 Flow Length, L in ft (max 300') 75 4 Two -year 24 -hr rainfall, P2 in inches 3.5 5 Land Slope, s in ft/ft 0.080 6 Tt = 0.007x(nL) ^0.8 /(P2A0.5xsA0.4) in hr 0.100 0.100 Shallow Concentrated Flow 7 8 9 10 11 Segment ID 2 Surface description (paved or unpaved) Unpaved Flow length, L in ft 2091 Watercourse slope, s in ft/ft 0.054 Average velocity, V in ft/s (figure 3 -1) 3.8 Tt= L /3600V in hr 0.153 0.153 Channel Flow Segment ID 12 Cross Sectional flow area, a in ftA2 13 Wetted perimeter, pw in ft 14 Hydraulic radius, r =a /pw in ft 15 Channel slope, s in ft/ft 16 Manning's roughness, n 17 V= 1.49xrA0.667xsA0.5/n in ft/s 18 Flow length, L in ft 19 Tt= L/3600V, in hr 0.000 20 Watershed total Tc in hours 0.253 21 Watershed total Tc in minuets 15.2 See page 30 of TR -55 Manual. POST Area A J: \C13098 - Croasdaile Farm SF \CALCS AND DATA \Stormwater \Spreadsheets \C13098_Tc.xls Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Hyd. No. 1 Pre Development DA W Hydrograph type = SCS Runoff Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 16.320 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 3.50 in Distribution Storm duration = 24 hrs Shape factor " Composite (Area /CN) = [(4.670 x 77) + (6.820 x 80) + (0.410 x 98)] / 16.320 Q (cfs) 35.00 30.00 25.00 15.00 10.00 5.00 0.00 0 120 240 Hyd No. 1 Pre Development DA W Hyd. No. 1 -- 2 Year Monday, 03 / 2 / 2015 = 33.34 cfs = 722 min = 87,393 cuft = 77* = Oft 11.90 min = Type II = 484 Q (cfs) 35.00 30.00 25.00 ' 20.00 15.00 10.00 5.00 0.00 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Hyd. No. 3 Post Development DA W Hydrograph type = SCS Runoff Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 15.400 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 3.50 in Distribution Storm duration = 24 hrs Shape factor " Composite (Area /CN) = [(10.510 x 98) + (9.230 x 80) + (0.770 x 77)] / 15.400 Post Development DA W Q (cfs) Hyd. No. 3 -- 2 Year 50.00 40.00 30.00 20.00 10.00 0.00 0 120 240 360 480 600 720 840 960 Hyd No. 3 Monday, 03 / 2 / 2015 = 46.24 cfs = 716 min = 93,423 cuft = 82* = Oft = 5.00 min = Type II = 484 Q (cfs) 50.00 40.00 30.00 20.00 10.00 U.UU 1080 1200 1320 1440 1560 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Hyd. No. 4 POST DEV AREA A BYPASS Hydrograph type = SCS Runoff Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 7.940 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 3.50 in Distribution Storm duration = 24 hrs Shape factor POST DEV AREA_A BYPASS Q (cfs) Hyd. No. 4 -- 2 Year 18.00 15.00 Monday, 03 / 2 / 2015 = 16.22 cfs = 722 min = 42,519 cuft = 77 = Oft 11.90 min = Type II = 484 Q (cfs) 18.00 15.00 12.00 12.00 9.00 9.00 6.00 6.00 3.00 3.00 0.00 ' 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 4 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Hyd. No. 6 Constructed Wetland Hydrograph type = Reservoir Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyd. No. = 3 - Post Development DA W Max. Elevation Reservoir name = POND A Max. Storage Storage Indication method used. Q (cfs) 50.00 40.00 30.00 20.00 10.00 0.00 0 240 Hyd No. 6 Constructed Wetland Hyd. No. 6 -- 2 Year Monday, 03 / 2 / 2015 = 6.695 cfs = 728 min = 93,402 cuft = 398.51 ft = 40,505 cuft 480 720 960 1200 1440 1680 Hyd No. 3 111111-1 Total storage used = 40,505 cuft Q (cfs) 50.00 40.00 30.00 20.00 10.00 - 0.00 1920 Time (min) 1 SCS Runoff 63.79 2 Hydrograph Summary Report - - - - -- Pre Development DA W 3 SCS Runoff 81.05 Hydraflow Hydrographs Extension for AutoCAD®Civil 3D@2015 by Autodesk, Inc. v10.4 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 63.79 2 720 165,370 - - - - -- - - - - -- - - - - -- Pre Development DA W 3 SCS Runoff 81.05 2 716 166,064 - - - - -- - - - - -- - - - - -- Post Development DA W 4 SCS Runoff 31.04 2 720 80,456 - - - - -- - - - - -- - - - - -- POST DEV AREA —A BYPASS 6 Reservoir 36.64 2 722 166,043 3 399.31 63,444 Constructed Wetland 7 Combine 67.34 2 722 246,499 4,6 - - - - -- - - - - -- COMBINE 9 Combine 108.12 2 718 246,520 3, 4, - - - - -- - - - - -- POST DEV NO DETENTION PrePost A Site Plan.gpw Return Period: 10 Year ` Tuesday, 03 / 3 / 2015 Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Hyd. No. 1 Pre Development DA W Hydrograph type = SCS Runoff Peak discharge Storm frequency = 10 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 16.320 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 5.10 in Distribution Storm duration = 24 hrs Shape factor " Composite (Area /CN) = [(4.670 x 77) + (6.820 x 80) + (0.410 x 98)] / 16.320 Q (cfs) 70.00 .1 11 50.00 F 1 11 30.00 20.00 10.00 0.00 0 120 240 Hyd No. 1 Pre Development DA W Hyd. No. 1 -- 10 Year Monday, 03 / 2 / 2015 = 63.79 cfs = 720 min = 165,370 cuft = 77* = Oft 11.90 min = Type II = 484 Q (cfs) 70.00 .1 11 50.00 F4, 11 30.00 20.00 10.00 0.00 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Monday, 03 / 2 / 2015 Hyd. No. 3 Post Development DA W Hydrograph type = SCS Runoff Peak discharge = 81.05 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 166,064 cuft Drainage area = 15.400 ac Curve number = 82* Basin Slope = 0.0% Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.10 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 " Composite (Area /CN) = [(10.510 x 98) + (9.230 x 80) + (0.770 x 77)] / 15.400 Post Development DA W Q (cfs) Hyd. No. 3 -- 10 Year Q (cfs) 90.00 1 90.00 80.00 80.00 70.00 70.00 60.00 60.00 50.00 50.00 40.00 40.00 30.00 — � 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 Hyd No. 3 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Hyd. No. 4 POST DEV AREA A BYPASS Hydrograph type = SCS Runoff Peak discharge Storm frequency = 10 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 7.940 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 5.10 in Distribution Storm duration = 24 hrs Shape factor Q (cfs) 35.00 30.00 25.00 20.00 15.00 10.00 POST DEV AREA_A BYPASS Hyd. No. 4 -- 10 Year Monday, 03 / 2 / 2015 = 31.04 cfs = 720 min = 80,456 cuft = 77 = Oft 11.90 min = Type II = 484 Q (cfs) 35.00 30.00 25.00 20.00 15.00 10.00 5.00 5.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 4 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Monday, 03 / 2 / 2015 Hyd. No. 6 Constructed Wetland Hydrograph type = Reservoir Peak discharge = 36.64 cfs Storm frequency = 10 yrs Time to peak = 722 min Time interval = 2 min Hyd. volume = 166,043 cuft Inflow hyd. No. = 3 - Post Development DA W Max. Elevation = 399.31 ft Reservoir name = POND A Max. Storage = 63,444 cuft Storage Indication method used Constructed Wetland Q (cfs) Hyd. No. 6 -- 10 Year Q (cfs) 90.00 90.00 I 80.00 80.00 70.00 70.00 50.00 40.00 30.00 20.00 10.00 50.00 40.00 30.00 20.00 10.00 0.00 - 1 ' - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) Hyd No. 6 111111-1 Hyd No. 3 1����� Total storage used = 63,444 Cuft Hydrograph Summary Report 2 724 371,134 - - - - -- Hydraflow Hydrographs Extension for AutoCAD®Civil 3D@2015 by Autodesk, Inc. v10.4 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 116.85 2 724 371,134 - - - - -- - - - - -- - - - - -- Pre Development DA'B' 2 SCS Runoff 37.45 2 728 131,730 - - - - -- - - - - -- - - - - -- Pre Dev DA'B' 1 -YR 4 SCS Runoff 89.18 2 716 187,830 - - - - -- - - - - -- - - - - -- Post Development DA'B' 5 SCS Runoff 56.47 2 724 179,370 - - - - -- - - - - -- - - - - -- POST DEV AREA —B BYPASS 7 Reservoir 28.09 2 724 184,609 4 358.19 64,852 Constructed Wetland 8 Combine 84.56 2 724 363,979 5,7 - - - - -- - - - - -- COMBINE 10 Combine 128.16 2 718 367,200 4, 5, - - - - -- - - - - -- POST DEV NO DETENTION PrePost B Site Plan.gpw Return Period: 2 Year ` Tuesday, 03 / 3 / 2015 STEWART Project: Crystal Lake Date: 03.03.15 Project No: C13098 By: ACH Development Composite CN Values - Drainage Area'B' Pre lPre- Development 1 -Year Analysis Surface SCS, CN Area (ac) Comments Impervious 98 2.93 assume good condition Open Space 80 7.71 assume good condition l Wooded 77 57.64 assume good condition _> Total Area 68.28 ac 11 => Composite SCS CN Value 78 1+ STFWART Project: Crystal Lake Date: 03.03.15 Project No: C 13098 By: ACH Composite CN Values - Drainage Area 'B' Post Development Bypass Analysis Post Development Bypass Analysis Surface SCS CN Area (ac) Comments Impervious 98 1.25 assume good condition Open Space 80 4.81 assume good condition l Wooded 77 26.94 assume good condition _> Total Area 33.00 ac 11 => Composite SCS CN Value 78 1 rou"'Aw STEWART Proj:ct: Crystal Lake Date: 03.03.15 Composite CN Values - Drainage Area to POND B Post Development Analysis Post Development Analysis POND Surface SCS CN Area (ac) Comments Impervious 98 14.22 assume good condition Open Space 80 2.72 assume good condition l Wooded 77 4.78 assume good condition => Total Area 21.72 ac 11 => Composite SCS CN Value 91 ,"�il S T E'WA R T TR 55 Time of Concentration Worksheet Project Crystal Lake Calculated By AH Date 03.03.15 Location Area B Checked By AG Revised - Cross Sectional flow area, a in ftA2 Pre - development Condition -2 and 10 Year Storm Analysis Sheet Flow 14 Segment ID 1 Subtotal 1 Surface Description Open Space 2 Mannings Roughness, n 0.23 3 Flow Length, L in ft (max 300') 75 4 Two -year 24 -hr rainfall, P2 in inches 3.5 5 Land Slope, s in ft/ft 0.080 6 Tt = 0.007x(nL) ^0.8 /(P2A0.5xsA0.4) in hr 0.100 0.100 Shallow Concentrated Flow Segment ID 7 Surface description (paved or unpaved) 8 Flow length, L in ft 9 Watercourse slope, s in ft/ft 10 Average velocitv, V in ft/s (figure 3 -1) 11 Tt= L /3600V in hr Channel Flow Paved Segment ID 12 Cross Sectional flow area, a in ftA2 13 Wetted perimeter, pw in ft 14 Hydraulic radius, r =a /pw in ft 15 Channel slope, s in ft/ft 16 Manning's roughness, n 17 V= 1.49xrA0.667xsA0.5/n in ft/s 18 Flow length, L in ft 19 Tt= U3600V, in hr 20 Watershed total Tc in hours 21 Watershed total Tc in minuets See page 30 of TR -55 Manual. Unpaved Paved Unpaved Unpaved 327 38 203 2349 0.035 0.061 0.084 0.032 3 5 4.7 3.9 0.030 0.002 0.012 0.167 1.77 2.36 0.75 0.0313 0.013 11.04 57 0.212 0.313 18.8 Pre Area B J: \C13098 - Croasdaile Farm SF \CALCS AND DATA \Stormwater \Spreadsheets \C13098_Tc.xls ,"�il S T E'WA R T TR 55 Time of Concentration Worksheet Project Crystal Lake Calculated By AH Date 03.03.15 Location Area B Checked By AG Revised - Cross Sectional flow area, a in ftA2 Pre - development Condition -2 and 10 Year Storm Analysis - Bypass Sheet Flow 14 Segment ID 1 Subtotal 1 Surface Description Open Space 2 Mannings Roughness, n 0.23 3 Flow Length, L in ft (max 300') 75 4 Two -year 24 -hr rainfall, P2 in inches 3.5 5 Land Slope, s in ft/ft 0.080 6 Tt = 0.007x(nL) ^0.8 /(P2A0.5xsA0.4) in hr 0.100 0.100 Shallow Concentrated Flow Segment ID 7 Surface description (paved or unpaved) 8 Flow length, L in ft 9 Watercourse slope, s in ft/ft 10 Average velocitv, V in ft/s (figure 3 -1) 11 Tt= L /3600V in hr Channel Flow Paved Segment ID 12 Cross Sectional flow area, a in ftA2 13 Wetted perimeter, pw in ft 14 Hydraulic radius, r =a /pw in ft 15 Channel slope, s in ft/ft 16 Manning's roughness, n 17 V= 1.49xrA0.667xsA0.5/n in ft/s 18 Flow length, L in ft 19 Tt= U3600V, in hr 20 Watershed total Tc in hours 21 Watershed total Tc in minuets See page 30 of TR -55 Manual. Unpaved Paved Unpaved Unpaved 327 38 203 2349 0.035 0.061 0.084 0.032 3 5 4.7 3.9 0.030 0.002 0.012 0.167 1.77 2.36 0.75 0.0313 0.013 11.04 57 0.212 0.313 18.8 POST Area B J: \C13098 - Croasdaile Farm SF \CALCS AND DATA \Stormwater \Spreadsheets \C13098_Tc.xls Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Hyd. No. 1 Pre Development DA 'B' Hydrograph type = SCS Runoff Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 68.280 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 3.50 in Distribution Storm duration = 24 hrs Shape factor " Composite (Area /CN) = [(4.670 x 77) + (6.820 x 80) + (0.410 x 98)] / 68.280 Pre Development DA 'B' Q (cfs) Hyd. No. 1 -- 2 Year 120.00 I 1 100.00 80.00 60.00 40.00 20.00 Monday, 03 / 2 / 2015 = 116.85 cfs = 724 min = 371,134 cuft = 78* = Oft 18.80 min = Type II = 484 Q (cfs) 120.00 100.00 •1 11 FA� 20.00 0.00 L 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 1 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Hyd. No. 2 Pre Dev DA 'B' 1 -YR Hydrograph type = SCS Runoff Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 23.810 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 3.50 in Distribution Storm duration = 24 hrs Shape factor Q (cfs) 40.00 30.00 20.00 10.00 0.00 0 120 240 Hyd No. 2 Pre Dev DA W 1 -YR Hyd. No. 2 -- 2 Year I Monday, 03 / 2 / 2015 = 37.45 cfs = 728 min = 131,730 cuft = 78 = Oft = 22.70 min = Type II = 484 Q (cfs) 40.00 30.00 20.00 10.00 0.00 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Monday, 03 / 2 / 2015 Hyd. No. 4 Post Development DA 'B' Hydrograph type = SCS Runoff Peak discharge = 89.18 cfs Storm frequency = 2 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 187,830 cuft Drainage area = 21.720 ac Curve number = 91 * Basin Slope = 0.0% Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.50 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 " Composite (Area /CN) = [(10.510 x 98) + (9.230 x 80) + (0.770 x 77)] / 21.720 Post Development DA W Q (cfs) Hyd. No. 4 -- 2 Year Q (cfs) 90.00 90.00 80.00 80.00 70.00 70.00 60.00 60.00 50.00 50.00 40.00 40.00 30.00 30.00 i 20.00 20.00 10.00 10.00 i 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 Hyd No. 4 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Monday, 03 / 2 / 2015 Hyd. No. 5 POST DEV AREA —B BYPASS Hydrograph type = SCS Runoff Peak discharge = 56.47 cfs Storm frequency = 2 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 179,370 cuft Drainage area = 33.000 ac Curve number = 78 Basin Slope = 0.0% Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 18.80 min Total precip. = 3.50 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 POST DEV AREA_B BYPASS Q (cfs) Hyd. No. 5 -- 2 Year Q (cfs) 60.00 60.00 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 5 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Hyd. No. 7 Constructed Wetland Hydrograph type = Reservoir Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyd. No. = 4 - Post Development DA'B' Max. Elevation Reservoir name = POND B Max. Storage Storage Indication method used Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 Constructed Wetland Hyd. No. 7 -- 2 Year Monday, 03 / 2 / 2015 = 28.09 cfs = 724 min = 184,609 cuft = 358.19 ft = 64,852 cuft Q (cfs) 90.00 80.00 70.00 60.00 50.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 — - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) Hyd No. 7 111111-1 Hyd No. 4 1����� Total storage used = 64,852 Cuft Hydrograph Summary Report 2 724 693,203 - - - - -- Hydraflow Hydrographs Extension for AutoCAD®Civil 3D@2015 by Autodesk, Inc. v10.4 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 221.69 2 724 693,203 - - - - -- - - - - -- - - - - -- Pre Development DA'B' 2 SCS Runoff 71.21 2 726 246,044 - - - - -- - - - - -- - - - - -- Pre Dev DA'B' 1 -YR 4 SCS Runoff 139.04 2 716 301,519 - - - - -- - - - - -- - - - - -- Post Development DA'B' 5 SCS Runoff 107.15 2 724 335,028 - - - - -- - - - - -- - - - - -- POST DEV AREA B BYPASS 7 Reservoir 34.30 2 724 298,291 4 358.90 105,622 Constructed Wetland 8 Combine 141.44 2 724 633,318 5,7 - - - - -- - - - - -- COMBINE 10 Combine 216.53 2 718 636,547 4, 5, - - - - -- - - - - -- POST DEV NO DETENTION PrePost B Site Plan.gpw Return Period: 10 Year ` Tuesday, 03 / 3 / 2015 Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Monday, 03 / 2 / 2015 Hyd. No. 1 Pre Development DA 'B' Hydrograph type = SCS Runoff Peak discharge = 221.69 cfs Storm frequency = 10 yrs Time to peak = 724 min Time interval = 2 min Hyd. volume = 693,203 cuft Drainage area = 68.280 ac Curve number = 78* Basin Slope = 0.0% Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 18.80 min Total precip. = 5.10 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 " Composite (Area /CN) = [(4.670 x 77) + (6.820 x 80) + (0.410 x 98)] / 68.280 Pre Development DA 'B' Q (cfs) Hyd. No. 1 -- 10 Year Q (cfs) 240.00 240.00 i 210.00 210.00 180.00 180.00 150.00 150.00 120.00 120.00 90.00 90.00 60.00 60.00 30.00 30.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 1 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Hyd. No. 2 Pre Dev DA 'B' 1 -YR Hydrograph type = SCS Runoff Peak discharge Storm frequency = 10 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 23.810 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 5.10 in Distribution Storm duration = 24 hrs Shape factor Pre Dev DA W 1 -YR Monday, 03 / 2 / 2015 = 71.21 cfs = 726 min = 246,044 cuft = 78 = Oft = 22.70 min = Type II = 484 Q (cfs) Hyd. No. 2 -- 10 Year Q (cfs) 80.00 80.00 70.00 70.00 60.00 i 60.00 50.00 50.00 40.00 40.00 30.00 i 30.00 20.00 20.00 10.00 i 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 2 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Hyd. No. 4 Post Development DA 'B' Hydrograph type = SCS Runoff Peak discharge Storm frequency = 10 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 21.720 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 5.10 in Distribution Storm duration = 24 hrs Shape factor " Composite (Area /CN) = [(10.510 x 98) + (9.230 x 80) + (0.770 x 77)] / 21.720 Q (cfs) 140.00 120.00 100.00 80.00 60.00 40.00 20.00 I 0.00 0 Post Development DA W Hyd. No. 4 -- 10 Year Monday, 03 / 2 / 2015 = 139.04 cfs = 716 min = 301,519 cuft = 91* = Oft = 5.00 min = Type II = 484 Q (cfs) 140.00 120.00 100.00 80.00 60.00 40.00 20.00 0.00 120 240 360 480 600 720 840 960 1080 1200 Hyd No. 4 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Hyd. No. 5 POST DEV AREA —B BYPASS Hydrograph type Storm frequency Time interval Drainage area Basin Slope Tc method Total precip. Storm duration Q (cfs) 120.00 100.00 :1 11 .1 11 i 1 11 20.00 1 11 0 120 240 Hyd No. 5 = SCS Runoff Peak discharge = 10 yrs Time to peak = 2 min Hyd. volume = 33.000 ac Curve number = 0.0% Hydraulic length = User Time of conc. (Tc) = 5.10 in Distribution = 24 hrs Shape factor POST DEV AREA_B BYPASS Hyd. No. 5 -- 10 Year 360 480 600 720 840 960 1080 1200 Monday, 03 / 2 / 2015 = 107.15 cfs = 724 min = 335,028 cuft = 78 = Oft 18.80 min = Type II = 484 Q (cfs) 120.00 100.00 :1 11 •1 11 i 1 11 20.00 %� 0.00 1320 1440 1560 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Hyd. No. 7 Constructed Wetland Hydrograph type = Reservoir Peak discharge Storm frequency = 10 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyd. No. = 4 - Post Development DA'B' Max. Elevation Reservoir name = POND B Max. Storage Storage Indication method used Q (cfs) 140.00 120.00 100.00 80.00 60.00 40.00 20.00 Constructed Wetland Hyd. No. 7 -- 10 Year Monday, 03 / 2 / 2015 = 34.30 cfs = 724 min = 298,291 cuft = 358.90 ft = 105,622 cuft Q (cfs) 140.00 120.00 100.00 .1 11 40.00 20.00 0.00 - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) Hyd No. 7 111111-1 Hyd No. 4 1����� Total storage used = 105,622 cuft Hydrograph Summary Report 2 718 261,182 - - - - -- Hydraflow Hydrographs Extension for AutoCAD®Civil 3D@2015 by Autodesk, Inc. v10.4 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 114.04 2 718 261,182 - - - - -- - - - - -- - - - - -- Pre Development DA'C' 3 SCS Runoff 41.93 2 716 85,012 - - - - -- - - - - -- - - - - -- Post Development DA'C' 4 SCS Runoff 70.48 2 720 161,337 - - - - -- - - - - -- - - - - -- POST DEV AREA C BYPASS 6 Reservoir 6.870 2 726 84,984 3 367.06 37,395 Constructed Wetland 7 Combine 76.62 2 720 246,321 4,6 - - - - -- - - - - -- COMBINE 9 Combine 111.36 2 718 246,349 3, 4, - - - - -- - - - - -- POST DEV NO DETENTION PrePost C Site Plan.gpw Return Period: 2 Year I Monday, 03 / 2 / 2015 STEWART Project: Crystal Lake Date: 03.03.15 Project No: C13098 By: ACH Development Composite CN Values - Drainage Area'C' Pre lPre- Development 1 -Year Analysis Surface SCS CN Impervious 98 Open Space 80 lWooded 77 _> Total Area 11 => Composite SCS CN Value 80 1 Area (ac) Comments 4.17 assume good condition 13.00 assume good condition 26.80 assume good condition 43.97 ac 80 1 rou"'Aw STEWART Proj:ct: Crystal Lake Date: 03.03.15 Composite CN Values - Drainage Area 'C' Post Development Bypass Analysis Post Development Bypass Analysis Surface SCS CN Area (ac) Comments Impervious 98 assume good condition Open Space 80 assume good condition l Wooded 77 31.07 assume good condition _> Total Area 31.07 ac 11 => Composite SCS CN Value 77 ,"�A STEWART r Composite CN Values - Drainage Area to POND C Post Development Analysis Post Development Analysis POND Surface SCS CN Area Jac) Comments Impervious 98 4. 9 assume pood condition �O an $ace D p 80 2.18 assume good and n J/ Wooded 77 6.53 assume pood on 't, _> Total Area 12.90 ac IF-=> Composite SCS CN Value 84 iI ,"�il S T E'WA R T TR 55 Time of Concentration Worksheet Project Crystal Lake Calculated By AH Date 03.03.15 Location Area C Checked By AG Revised - Surface description (paved or unpaved) Pre - development Condition -2 and 10 Year Storm Analysis Sheet Flow Unpaved Segment ID 1 Subtotal 1 Surface Description Open Space 2 Mannings Roughness, n 0.23 3 Flow Length, L in ft (max 300') 75 4 Two -year 24 -hr rainfall, P2 in inches 3.5 5 Land Slope, s in ft/ft 0.080 6 Tt = 0.007x(nL) ^0.8 /(P2A0.5xsA0.4) in hr 0.100 0.100 Shallow Concentrated Flow 7 8 9 10 11 Segment ID 2 3 4 Surface description (paved or unpaved) Unpaved Paved Unpaved Flow length, L in ft 219 42 603 Watercourse slope, s in ft/ft 0.055 0.039 0.093 Average velocitv. V in ft/s (figure 3 -1) 3.8 4 4.8 Tt= L /3600V in hr 0.016 0.003 0.035 0.054 Channel Flow Segment ID 12 Cross Sectional flow area, a in ftA2 13 Wetted perimeter, pw in ft 14 Hydraulic radius, r =a /pw in ft 15 Channel slope, s in ft/ft 16 Manning's roughness, n 17 V= 1.49xrA0.667xsA0.5/n in ft/s 18 Flow length, L in ft 19 Tt= L/3600V, in hr 0.000 20 Watershed total Tc in hours 0.154 21 Watershed total Tc in minuets 9.2 See page 30 of TR -55 Manual. Pre Area C J: \C13098 - Croasdaile Farm SF \CALCS AND DATA \Stormwater \Spreadsheets \C13098_Tc.xls ,"�il S T E'WA R T TR 55 Time of Concentration Worksheet Project Crystal Lake Calculated By AH Date 03.03.15 Location Area C Checked By AG Revised - Surface description (paved or unpaved) Pre - development Condition -2 and 10 Year Storm Analysis - Bypass Sheet Flow Unpaved Segment ID 1 Subtotal 1 Surface Description Open Space 2 Mannings Roughness, n 0.23 3 Flow Length, L in ft (max 300') 75 4 Two -year 24 -hr rainfall, P2 in inches 3.5 5 Land Slope, s in ft/ft 0.080 6 Tt = 0.007x(nL) ^0.8 /(P2A0.5xsA0.4) in hr 0.100 0.100 Shallow Concentrated Flow 7 8 9 10 11 Segment ID 2 3 4 Surface description (paved or unpaved) Unpaved Paved Unpaved Flow length, L in ft 219 42 603 Watercourse slope, s in ft/ft 0.055 0.039 0.093 Average velocitv. V in ft/s (figure 3 -1) 3.8 4 4.8 Tt= L /3600V in hr 0.016 0.003 0.035 0.054 Channel Flow Segment ID 12 Cross Sectional flow area, a in ftA2 13 Wetted perimeter, pw in ft 14 Hydraulic radius, r =a /pw in ft 15 Channel slope, s in ft/ft 16 Manning's roughness, n 17 V= 1.49xrA0.667xsA0.5/n in ft/s 18 Flow length, L in ft 19 Tt= L/3600V, in hr 0.000 20 Watershed total Tc in hours 0.154 21 Watershed total Tc in minuets 9.2 See page 30 of TR -55 Manual. POST Area C J: \C13098 - Croasdaile Farm SF \CALCS AND DATA \Stormwater \Spreadsheets \C13098_Tc.xls Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Hyd. No. 1 Pre Development DA 'C' Hydrograph type = SCS Runoff Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 43.970 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 3.50 in Distribution Storm duration = 24 hrs Shape factor " Composite (Area /CN) = [(4.670 x 77) + (6.820 x 80) + (0.410 x 98)] / 43.970 Pre Development DA V Q (cfs) Hyd. No. 1 -- 2 Year 120.00 J 100.00 :1 11 .1 11 i 1 11 20.00 0.00 0 120 240 Hyd No. 1 Monday, 03 / 2 / 2015 = 114.04 cfs = 718 min = 261,182 cuft = 80* = Oft = 9.20 min = Type II = 484 Q (cfs) 120.00 100.00 :1 11 •1 11 i 1 11 20.00 0.00 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Monday, 03 / 2 / 2015 Hyd. No. 3 Post Development DA 'C' Hydrograph type = SCS Runoff Peak discharge = 41.93 cfs Storm frequency = 2 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 85,012 cuft Drainage area = 12.900 ac Curve number = 84* Basin Slope = 0.0% Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 3.50 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 " Composite (Area /CN) = [(10.510 x 98) + (9.230 x 80) + (0.770 x 77)] / 12.900 Post Development DA V Q (cfs) Hyd. No. 3 -- 2 Year Q (cfs) 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 Hyd No. 3 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Hyd. No. 4 POST DEV AREA C BYPASS Hydrograph type = SCS Runoff Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 31.070 ac Curve number Basin Slope = 0.0% Hydraulic length Tc method = User Time of conc. (Tc) Total precip. = 3.50 in Distribution Storm duration = 24 hrs Shape factor Q (cfs) 80.00 70.00 .1 11 50.00 rd� 30.00 20.00 10.00 0.00 0 120 240 360 480 Hyd No. 4 POST DEV AREA_C BYPASS Hyd. No. 4 -- 2 Year Monday, 03 / 2 / 2015 = 70.48 cfs = 720 min = 161,337 cuft = 77 = Oft = 9.20 min = Type II = 484 Q (cfs) 80.00 70.00 I 60.00 50.00 40.00 30.00 20.00 10.00 0.00 600 720 840 960 1080 1200 1320 1440 1560 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Hyd. No. 6 Constructed Wetland Hydrograph type = Reservoir Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyd. No. = 3 - Post Development DA'C' Max. Elevation Reservoir name = POND C Max. Storage Storage Indication method used Q (cfs) 50.00 40.00 30.00 20.00 10.00 0.00 0 240 Hyd No. 6 Constructed Wetland Hyd. No. 6 -- 2 Year 480 720 - Hyd No. 3 Monday, 03 / 2 / 2015 = 6.870 cfs = 726 min = 84,984 cuft = 367.06 ft = 37,395 cuft Q (cfs) 50.00 1 11 30.00 20.00 10.00 - 0.00 960 1200 1440 1680 1920 Time (min) II T T T— l ll Total storage used = 37,395 cuft Hydrograph Summary Report 2 718 475,686 - - - - -- Hydraflow Hydrographs Extension for AutoCAD®Civil 3D@2015 by Autodesk, Inc. v10.4 Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) (min) (min) (cuft) (ft) (cuft) 1 SCS Runoff 207.04 2 718 475,686 - - - - -- - - - - -- - - - - -- Pre Development DA'C' 3 SCS Runoff 71.44 2 716 147,594 - - - - -- - - - - -- - - - - -- Post Development DA'C' 4 SCS Runoff 133.40 2 718 305,292 - - - - -- - - - - -- - - - - -- POST DEV AREA C BYPASS 6 Reservoir 47.29 2 720 147,566 3 367.82 52,504 Constructed Wetland 7 Combine 179.53 2 720 452,858 4,6 - - - - -- - - - - -- COMBINE 9 Combine 203.08 2 718 452,886 3, 4, - - - - -- - - - - -- POST DEV NO DETENTION PrePost C Site Plan.gpw Return Period: 10 Year ` Monday, 03 / 2 / 2015 Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Monday, 03 / 2 / 2015 Hyd. No. 1 Pre Development DA 'C' Hydrograph type = SCS Runoff Peak discharge = 207.04 cfs Storm frequency = 10 yrs Time to peak = 718 min Time interval = 2 min Hyd. volume = 475,686 cuft Drainage area = 43.970 ac Curve number = 80* Basin Slope = 0.0% Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 9.20 min Total precip. = 5.10 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 " Composite (Area /CN) = [(4.670 x 77) + (6.820 x 80) + (0.410 x 98)] / 43.970 Pre Development DA V Q (cfs) Hyd. No. 1 -- 10 Year Q (cfs) 210.00 210.00 180.00 150.00 120.00 •1 11 •1 11 �I 180.00 150.00 120.00 •1 11 •1 11 30.00 30.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 1 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. 00.4 Monday, 03 / 2 / 2015 Hyd. No. 3 Post Development DA 'C' Hydrograph type = SCS Runoff Peak discharge = 71.44 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 147,594 cuft Drainage area = 12.900 ac Curve number = 84* Basin Slope = 0.0% Hydraulic length = 0 ft Tc method = User Time of conc. (Tc) = 5.00 min Total precip. = 5.10 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 " Composite (Area /CN) = [(10.510 x 98) + (9.230 x 80) + (0.770 x 77)] / 12.900 Post Development DA V Q (cfs) Hyd. No. 3 -- 10 Year Q (cfs) 80.00 80.00 70.00 70.00 60.00 60.00 50.00 50.00 40.00 40.00 30.00 30.00 20.00 20.00 10.00 i 10.00 0.00 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 Hyd No. 3 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Hyd. No. 4 POST DEV AREA —C BYPASS Hydrograph type Storm frequency Time interval Drainage area Basin Slope Tc method Total precip. Storm duration Q (cfs) 140.00 120.00 100.00 80.00 60.00 40.00 20.00 0.00 = SCS Runoff Peak discharge = 10 yrs Time to peak = 2 min Hyd. volume = 31.070 ac Curve number = 0.0% Hydraulic length = User Time of conc. (Tc) = 5.10 in Distribution = 24 hrs Shape factor POST DEV AREA_C BYPASS Hyd. No. 4 -- 10 Year Monday, 03 / 2 / 2015 = 133.40 cfs = 718 min = 305,292 cuft = 77 = Oft = 9.20 min = Type II = 484 0 120 240 360 480 600 720 840 960 1080 1200 1320 Hyd No. 4 Q (cfs) 140.00 120.00 100.00 80.00 60.00 40.00 20.00 0.00 1440 1560 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Hyd. No. 6 Constructed Wetland Hydrograph type = Reservoir Peak discharge Storm frequency = 10 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyd. No. = 3 - Post Development DA'C' Max. Elevation Reservoir name = POND C Max. Storage Storage Indication method used Constructed Wetland Q (cfs) Hyd. No. 6 -- 10 Year 80.00 70.00 .1 11 50.00 i 1 11 30.00 20.00 10.00 Monday, 03 / 2 / 2015 = 47.29 cfs = 720 min = 147,566 cuft = 367.82 ft = 52,504 cuft Q (cfs) 80.00 70.00 •1 11 50.00 i 1 11 30.00 20.00 10.00 0.00 __.1.. , - 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) Hyd No. 6 111111-1 Hyd No. 3 1����� Total storage used = 52,504 Cuft BMP Sizing for Peak Flow and Water Quality rmqw;j STEWART Project: Crystal Lake Date: 03.03.15 Revision - Project No: C13098 By: ACH Constructed . . Calcukifions Input values in red Drainage Area: A Drainage JTotal Drainage Area (sf) 720,787 IOn-site Drainage Area �sf) 597,845 Off -site Drainage Area s) 97,806 Impervious Surface Area 6.59 ac On -site Buildings /Lots (sf) 120,000 JOn -site Streets (sf) 86,625 On -site Parking (sf) 0 On -site Sidewalks (sf) 80,150 Other On -site (sf) 76 Future (sf) 0 Off -site sf 0 Existing A* (sf) 0 JTotal Impervious Area (sf) 286,851 Total Drainage Area = 16.55 ac Total Impervious Area = 6.59 ac Percent Impervious = 39.80% Design Rainfall Depth = 1 in Allowed Ponding Depth = 12 in Required Surface Area = 24517 sf Required Storage Area = Provided Surface Area = Wetland Zone Type Deep Water (Forebay) Shallow Water Shallow Land Deep Water (non - Forebay) 24517 SF 25136 SF Managed Pervious Area (sf) JUnmanged Pervious Area (pasture) (sf) Forest (sf) JTotal Pervious Area (sf) 228,202 0 180,598 408,800 * = Report only amount of existing BUA that will remain after development. Do not report any existing BUA that is to be removed and which will be replaced by new BUA Simple Method Rv = 0.05 + 0.009(I) I = % impervious = 40% Rv = 0.41 in Required Volume = 24517 cf % of Total Surface Surface Wetland Area Area Surface Required Zone Provided Area (sf) Depth (sf) % of Total 10% 2,514 18 -36" 5,323 21.2% 40% 10,054 3 -6" 21,291 84.7% 40% 10,054 12" 21,291 84.7% 10% 2,514 18 -36" 5,323 21.2% STEWART Project: Crystal Lake Proiect No: C13098 Input values in red Drainage Area: A Date: 03.03.15 Bv: ACH Storage Volume Required (Simple Method) Basin Characteristics Revision - Total Drainage Area = 16.55 ac Wetland Invert = 395.50 ft Total Impervious Area = 6.59 ac Normal Pool Elevation = 397.00 ft Percent Impervious = 40% Next available Outlet = 398.00 ft Storage Depth = 1.00 ft Rv = 0.05 + 0.009(I) Driving Head (H /3)= 0.33 ft I = % impervious = 40% Rv = 0.41 in Runoff Vol. Req'= 24517 cf Temporary Storage Volume = 25136 cf Temporary Storage Surface Area = 25136 sf Find orifice size for 2 -day drawdown time Flow Rate = Volume (cf) / Time (sec) 0.1455 cfs Q= CD *A *(2 *g *h) ^(1/2) (Orifice Equation - solve for A (area)) A= 0.05233 ft2 7.53497 in Orifice Size (2 day) = 3.10 in (dia) Find orifice size for 5 -day drawdown time Flow Rate = Volume (cf) / Time (sec) 0.0568 cfs Q= CD *A *(2 *g *h) ^(1/2) (Orifice Equation - solve for A (area)) A= 0.02042 ft2 2.93978 in Orifice Size (5 day) = 1.93 in (dia) Select orifice size between 2 and 5 day size Actual Drawdown Time Volume = 25136 cf Pipe Size = 2.5 "dia Area = 0.03409 ft2 Flow Rate = 0.09476 cfs STRONGER BY DESIGN 421 FAYETTEVILLE ST. SUITE 400 RALEIGH, NC 27603 T 919.380.8750 F 919.380.8752 Pond Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Monday, 03 / 2 / 2015 Pond No. 1 - POND A [C] [PrfRsr] Pond Data [B] [C] [D] Contours - User - defined contour areas. Average end area method used for volume calculation. Begining Elevation = 397.00 ft Stage / Storage Table 0.00 Crest Len (ft) = 20.00 Stage (ft) Elevation (ft) Contour area (sqft) Incr. Storage (cuft) Total storage (cuft) 0.00 397.00 25,136 0 0 1.00 398.00 27,141 26,139 26,139 2.00 399.00 29,204 28,173 54,311 3.00 400.00 31,322 30,263 84,574 4.00 401.00 33,498 32,410 116,984 Culvert / Orifice Structures Weir Structures Stage (ft) 4.00 3.00 f 1117 1.00 0.00 0.00 7.00 Total Q Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet (oc) control. Weir risers checked for orifice conditions (ic) and submergence (s) Stage / Discharge 14.00 21.00 28.00 35.00 42.00 49.00 56.00 63.00 Elev (ft) 401.00 400.00 16DR- [1111 398.00 397.00 70.00 Discharge (cfs) [A] [B] [C] [PrfRsr] [A] [B] [C] [D] Rise (in) = 36.00 6.00 6.00 0.00 Crest Len (ft) = 20.00 40.00 0.00 0.00 Span (in) = 36.00 6.00 24.00 0.00 Crest El. (ft) = 398.60 399.40 0.00 0.00 No. Barrels = 1 4 1 0 Weir Coeff. = 3.33 3.33 3.33 3.33 Invert El. (ft) = 395.50 397.00 398.00 0.00 Weir Type = 1 Ciplti - -- - -- Length (ft) = 68.00 0.00 0.00 0.00 Multi -Stage = Yes Yes No No Slope ( %) = 0.50 0.00 0.00 n/a N -Value = .013 .013 .013 n/a Orifice Coeff. = 0.60 0.60 0.60 0.60 Exfil.(in /hr) = 0.000 (by Contour) Multi -Stage = n/a Yes Yes No TW Elev. (ft) = 0.00 Stage (ft) 4.00 3.00 f 1117 1.00 0.00 0.00 7.00 Total Q Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet (oc) control. Weir risers checked for orifice conditions (ic) and submergence (s) Stage / Discharge 14.00 21.00 28.00 35.00 42.00 49.00 56.00 63.00 Elev (ft) 401.00 400.00 16DR- [1111 398.00 397.00 70.00 Discharge (cfs) rmqw;j STEWART Project: Crystal Lake Date: 03.03.15 Revision - Project No: C13098 By: ACH Constructed Wetland . Calculations Input values in red Drainage Area: B Drainage Area Pervious Surface Area JTotal Drainage Area (sf) 998,529 1Managed Pervious Area (sf) 118,314 JOn -site Drainage Area �sf) 945,817 JUnmanged Pervious Area (pasture) (sf) 0 lOff -site Drainage Area s) 0 1 Forest (sf) 208,231 JTotal Pervious Area (sf) 326,545 Impervious Surface Area 14.22 ac On -site Buildings /Lots (sf) 272,500 JOn -site Streets (sf) 134,508 JOn -site Parking (sf) 25,640 lOn -site Sidewalks (sf) 159,813 10ther On -site (sf) 26,811 Future (sf) 0 JOff -site (sf) 0 lExisting BUA* (sf) 0 JTotal Impervious Area (sf) 619,272 Total Drainage Area = 22.92 ac Total Impervious Area = 14.22 ac Percent Impervious = 62.02% Design Rainfall Depth = 1 in Allowed Ponding Depth = 12 in Required Surface Area = 50606 sf Required Storage Area = Provided Surface Area = Wetland Zone Type Deep Water (Forebay) Shallow Water Shallow Land Deep Water (non - Forebay) 50606 SF 52712 SF * = Report only amount of existing BUA that will remain after development. Do not report any existing BUA that is to be removed and which will be replaced by new BUA Simple Method Rv = 0.05 + 0.009(I) I = % impervious = 62% Rv = 0.61 in Required Volume = 50606 cf % of Total Surface Surface Wetland Area Area Surface Required Zone Provided Area (sf) Depth (sf) % of Total 10% 5,271 18 -36" 5,323 10.1% 40% 21,085 3 -6" 21,291 40.4% 40% 21,085 12" 21,291 40.4% 10% 5,271 18 -36" 5,323 10.1% -A STEWART Project: Crystal Lake Proiect No: C13098 Input values in red Drainage Area: B Storage Volume Required (Simple Method) Date: 03.03.15 Bv: ACH Basin Characteristics Revision - Total Drainage Area = 22.92 ac Wetland Invert = 355.50 ft Total Impervious Area = 14.22 ac Normal Pool Elevation = 357.00 ft Percent Impervious = 62% Next available Outlet = 358.00 ft Storage Depth = 1.00 ft Rv = 0.05 + 0.009(I) Driving Head (H /3)= 0.33 ft I = % impervious = 62% Rv = 0.61 in Runoff Vol. Req'= 50606 cf Temporary Storage Volume = 52712 cf Temporary Storage Surface Area = 52712 sf Find orifice size for 2 -day drawdown time Flow Rate = Volume (cf) / Time (sec) 0.3050 cfs Q= CD *A *(2 *g *h) ^(1/2) (Orifice Equation - solve for A (area)) A= 0.10973 ft2 15.80137 in Orifice Size (2 day) = 4.49 in (dia) Find orifice size for 5 -day drawdown time Flow Rate = Volume (cf) / Time (sec) 0.1171 cfs Q= CD *A *(2 *g *h) ^(1/2) (Orifice Equation - solve for A (area)) A= 0.04214 ft2 6.06802 in Orifice Size (5 day) = 2.78 in (dia) Select orifice size between 2 and 5 day size Actual Drawdown Time Volume = 52712 cf Pipe Size = 3.5 "dia Area = 0.066813 ft2 Flow Rate = 0.185736 cfs STRONGER BY DESIGN 421 FAYETTEVILLE ST. SUITE 400 RALEIGH, NC 27603 T 919.380.8750 F 919.380.8752 Pond Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Monday, 03 / 2 / 2015 Pond No. 1 - POND B [C] [PrfRsr] Pond Data [B] [C] [D] Contours - User - defined contour areas. Average end area method used for volume calculation. Begining Elevation = 357.00 ft Stage / Storage Table 0.00 Crest Len (ft) = 20.00 Stage (ft) Elevation (ft) Contour area (sqft) Incr. Storage (cuft) Total storage (cuft) 0.00 357.00 52,712 0 0 1.00 358.00 55,594 54,153 54,153 2.00 359.00 58,534 57,064 111,217 3.00 360.00 61,529 60,032 171,249 4.00 361.00 64,582 63,056 234,304 Culvert / Orifice Structures Weir Structures Stage (ft) 4.00 3.00 f 1111 Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet (oc) control. Weir risers checked for orifice conditions (ic) and submergence (s) Stage / Discharge 1.00 r Elev (ft) 361.00 360.00 [CM111I11 358.00 0.00 357.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 45.00 50.00 Total Q Discharge (cfs) [A] [B] [C] [PrfRsr] [A] [B] [C] [D] Rise (in) = 30.00 1.50 6.00 0.00 Crest Len (ft) = 20.00 40.00 0.00 0.00 Span (in) = 30.00 1.50 24.00 0.00 Crest El. (ft) = 357.10 357.90 0.00 0.00 No. Barrels = 1 1 3 0 Weir Coeff. = 3.33 3.33 3.33 3.33 Invert El. (ft) = 355.50 357.00 358.00 0.00 Weir Type = 1 Ciplti - -- - -- Length (ft) = 103.00 0.00 0.00 0.00 Multi -Stage = Yes Yes No No Slope ( %) = 2.72 0.00 0.00 n/a N -Value = .013 .013 .013 n/a Orifice Coeff. = 0.60 0.60 0.60 0.60 Exfil.(in /hr) = 0.000 (by Contour) Multi -Stage = n/a Yes Yes No TW Elev. (ft) = 0.00 Stage (ft) 4.00 3.00 f 1111 Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet (oc) control. Weir risers checked for orifice conditions (ic) and submergence (s) Stage / Discharge 1.00 r Elev (ft) 361.00 360.00 [CM111I11 358.00 0.00 357.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 45.00 50.00 Total Q Discharge (cfs) _ I STEWART Project: Crystal Lake Date: 03.03.15 Revision - Project No: C13098 By: ACH Constructed Wetland . Calculations Input values in red Drainage Area: C - _, . JTotal Drainage Area (sf) 578,329 IOn-site Drainage Area �sf) 321,093 Off -site Drainage Area s) 240,728 Impervious Surface Area 4.19 ac On -site Buildings /Lots (sf) 21,314 JOn -site Streets (sf) 52,657 On -site Parking (sf) 0 On -site Sidewalks (sf) 24,357 Other On -site (sf) 200 Future (sf) 0 Off -site sf 84,054 Existing A* (sf) 0 JTotal Impervious Area (sf) 182,582 Total Drainage Area = 13.28 ac Total Impervious Area = 4.19 ac Percent Impervious = 31.57% Design Rainfall Depth = 1 in Allowed Ponding Depth = 12 in Required Surface Area = 16103 sf 1. Managed Pervious Area (sf) 94,810 JUnmanged Pervious Area (pasture) (sf) 0 1 Forest (sf) 284,429 JTotal Pervious Area (sf) 379,239 * = Report only amount of existing BUA that will remain after development. Do not report any existing BUA that is to be removed and which will be replaced by new BUA Simple Method Rv = 0.05 + 0.009(I) I = % impervious = 32% Rv = 0.33 in Required Volume = 16103 cf Required Surface Area .. Required Storage Area = 16103 SF Provided Surface Area = 16508 SF % of Total Surface Surface Wetland Area Area Surface Required Zone Provided Wetland Zone Type Area (sf) Depth (sf) % of Total Deep Water (Forebay) 10% 1,651 18 -36" 5,323 32.2% Shallow Water 40% 6,603 3 -6" 21,291 129.0% Shallow Land 40% 6,603 12" 21,291 129.0% Deep Water (non - Forebay) 10% 1,651 18 -36" 5,323 32.2% -A STEWART Project: Crystal Lake Proiect No: C13098 Input values in red Drainage Area: C Storage Volume Required (Simple Method) Date: 03.03.15 Bv: ACH Basin Characteristics Revision - Total Drainage Area = 13.28 ac Wetland Invert = 363.50 ft Total Impervious Area = 4.19 ac Normal Pool Elevation = 365.00 ft Percent Impervious = 32% Next available Outlet = 366.00 ft Storage Depth = 1.00 ft Rv = 0.05 + 0.009(I) Driving Head (H /3)= 0.33 ft I = % impervious = 32% Rv = 0.33 in Runoff Vol. Req'= 16103 cf Temporary Storage Volume = 16508 cf Temporary Storage Surface Area = 16508 sf Find orifice size for 2 -day drawdown time Flow Rate = Volume (cf) / Time (sec) 0.0955 cfs Q= CD *A *(2 *g *h) ^(1/2) (Orifice Equation - solve for A (area)) A= 0.03437 ft2 4.94857 in Orifice Size (2 day) = 2.51 in (dia) Find orifice size for 5 -day drawdown time Flow Rate = Volume (cf) / Time (sec) 0.0373 cfs Q= CD *A *(2 *g *h) ^(1/2) (Orifice Equation - solve for A (area)) A= 0.01341 ft2 1.93091 in Orifice Size (5 day) = 1.57 in (dia) Select orifice size between 2 and 5 day size Actual Drawdown Time Volume = 16508 cf Pipe Size = 2 "dia Area = 0.021817 ft2 Flow Rate = 0.060649 cfs STRONGER BY DESIGN 421 FAYETTEVILLE ST. SUITE 400 RALEIGH, NC 27603 T 919.380.8750 F 919.380.8752 Pond Report Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2015 by Autodesk, Inc. v10.4 Monday, 03 / 2 / 2015 Pond No. 1 - POND C Pond Data Contours - User - defined contour areas. Average end area method used for volume calculation. Begining Elevation = 365.00 ft Stage / Storage Table Stage (ft) Elevation (ft) Contour area (sqft) Incr. Storage (cuft) Total storage (cuft) 0.00 365.00 16,508 0 0 1.00 366.00 18,081 17,295 17,295 2.00 367.00 19,711 18,896 36,191 3.00 368.00 21,397 20,554 56,745 4.00 369.00 23,140 22,269 79,013 Culvert / Orifice Structures Weir Structures [A] [B] [C] [PrfRsr] [A] [B] [C] [D] Rise (in) = 48.00 6.00 6.00 0.00 Crest Len (ft) = 20.00 40.00 0.00 0.00 Span (in) = 48.00 6.00 24.00 0.00 Crest El. (ft) = 367.10 367.90 0.00 0.00 No. Barrels = 1 2 1 0 Weir Coeff. = 3.33 3.33 3.33 3.33 Invert El. (ft) = 363.00 365.00 366.00 0.00 Weir Type = 1 Ciplti - -- - -- Length (ft) = 86.00 0.00 0.00 0.00 Multi -Stage = Yes Yes No No Slope ( %) = 6.98 0.00 0.00 n/a N -Value = .013 .013 .013 n/a Orifice Coeff. = 0.60 0.60 0.60 0.60 Exfil.(in /hr) = 0.000 (by Contour) Multi -Stage = n/a Yes Yes No TW Elev. (ft) = 0.00 Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet (oc) control. Weir risers checked for orifice conditions (ic) and submergence (s). Stage (ft) 4.00 3.00 41111 1.00 Stage / Discharge Elev (ft) 369.00 368.00 1911*I[1I11 366.00 0.00 365.00 0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0 120.0 Total Q Discharge (cfs) Appendix 4 4. Nutrient Loading Calculations a. Jordan Lake Accounting Tool b. City of Durham Nutrient Reporting Form c. TSS Summary 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 A I B I C I D E F I G I11IIII K L I M I N 1 O 1 P I O I R I S I T I U Watershed Characteristics Ver2.0 Clear All Values _j IReturn to Instructions J Proceed to BMP Characteristics L Skip to Development Summary Instructions 1. Select your physiographic /geologic region. (see map on 'instructions' page) 2. Enter the area of the entire development in square feet (ft). 3. Select the location that is most representative of the site's precipitation characteristics. (see map on 'instructions' page) 4. For each applicable land use, enter the total area of that land use that lies within the development under pre - development conditions. 5. For each applicable land use, enter the total area of that land use that lies within the development under post - development conditions, before BMP implementation. 6. Ensure that the sum of pre- and post - development areas entered equal the orginal development area. 7. Continue to "BMP Characteristics" tab. Additional Guidelines - For non - residential watersheds, indicate acreages of each land use type in Column 1 for both pre- and post - development conditions. - For residential watersheds, complete the required information in Column 2 for both pre- and post - development conditions. - If a given land use is not present in the given watershed, leave the cell blank or enter a zero. - Ensure that land use areas entered for both pre- and post - development conditions match the total development area entered in cell 021. - Residential areas may be entered by average lot size (column, part A), or may be separated into individual land uses (column 2, part B) -- do NOT list out individual land uses within an area already described by lot size. - Unless runoff flowing onto the development from offsite is routed separately around or through the site, the offsite catchment area draining in must be included in the acreage values of the appropriate land use(s) and treated. Physiographic /Geologic Region: Piedmont Soil Hydrologic Group B Precipitation location: Carrboro Total Development Area (ft`): 6,510,557 Development Name: Crystal Lake I Model Prepared By: A. Hutchens COLUMN 1 -- NON- RESIDENTIAL LAND USES COLUMN 2 -- RESIDENTIAL LAND USES Pre- Post- Custom Pre- Post - TN EMC TP EMC Development Development Age TN EMC Lot Size TP EMC Development Development (mg/L) (mg/L) (ftz) (ftz) (ac) (yrs) (mg/L) (mg/L) (ftz) Ihzl COMM ERCIAL I PART A Parking lot 1.44 0.16 M -ac lots -- - - Roof 1.08 0.15 I Y -ac lots -- -- -- I�4 Open/Landscaped 2.24 0.44 INDUSTRIAL 1 -ac lots - Parking lot 1.44 0.39 2 -ac lots -- - - Roof 1.08 0.15 Multi - family -- -- -- Open /Landscaped 2.24 0.44 Townhomes -- -- -- �TRANSPORTATION Custom Lot Size -- -- Higli Density (interstate, main) 3.67 0.43 PART B Low Density (secondary, feeder) 1.4 0.52 Roadway -- 1.4 0.52 286,702 Rural 1.14 0.47 Driveway 1.0 1.44 _ 0.39 20,000 75,856 Sidewalk 1.4 1.16 Parking lot - 1.44 0.39 276 PERVIOUS Roof -- 1.08 0.15 4,430 402,304 Managed pervious 3.06 0.59 Sidewalk /Patio -- 1.4 1.16 268,742 Unmanaged (Pasture) 3.61 1.56 I Lawn -- 2.24 0.44 Forest 1.47 0.25 I Managed pervious -- 3.06 0.59 395,463 441,301 JURISDICTIONAL LANDS* I Forest -- 1.47 _ 0.25 4,325,364 3,175,720 Natural wetland. - -- I Natural wetland* -- -- _ -- Riparian buffer -- -- Riparian buffer* - - _ - 1,271,195 1,271,195 Open water - Open water* - -- -- 494,105 494,105 LAND TAKEN UP BY BMPs 1.08 0.15 ILAND TAKEN UP BY BMPs -- 1.08 0.15 I 94,356 *Jurisdictional land uses are not included in nutrient /flow calculations. LAND USE AREA CHECK Total Development Area Entered (ftz): 6,510,557 Total Pre - Development Calculated Area (ft): 6,510,557 Total Post - Development Calculated Area (ftz): 6,510,557 BMP Characteristics Ver2.0 I Remmto water shed Frppeed ep Deyelplwmentl: Clear All Values I Return to Instructions Characteristics Summary Instructions '� I\ 1. Select the type of BMP for each catchment. z Enter the area of each land use type in the contributing drainage area for each BMP. 3. Continue to "Development Summary" tab. Additional Guidelines -This spreadsheet allows the development to be divided into as many as 6 smaller catchments. - BMPs 1, 2, and 3 for a given catchment are assumed to operate in series, with the outflow from I serving as the inflow to 2, etc. - If the outflow from an entire catchment (including outflow from selected BMPs) drains to another BMP, indicate this in the drop down menu below the BMP type and leave all cells for individual land uses blank - Nat all BMP or catchments must be utilized. Simply leave fields blank in the columns not needed. - Leave cells blank or insert zeroes if a land use is not present in the area draining to the BMP. - For water harvesting BMPs, be sure to enter the percent volume reduction that will be achieved by your system. Volume detention (catch- and - release mechanisms) will not be considered -only proven volume reductions are valid inputs. The BMP undersizing option should only be used for existing development or retrofit sites. - Volume reduction efficiencies for undersized BMPs are calculated based on a 1:1 ratio (a BMP that is 60 % smaller than the required design size is assigned a removal efficiency equal to 60% of the standard efficiency value). Effluent concentrations remain the same as full -sized BMPS. - IMPORTANT: for the land area calculation checks to occur, you MUST press enter after entering a value for area to be treated by a BMP )not just click on the next cell). -See User's Manual far instructions on modeling oversized BMPs. Type of BMP: If BMP is undersized, Indicate the BMP's: relative to the designs I,, required to capture the designated water quality del (i.e. 0.75 = BMP is 75% of required cash size): 'For water harvesting BMP, enter pert e volume reduction In decimal form. Catchment 1: Catchment 2: Catchment 3: Catchment 4: Catchment s: 2 Drainage Area Land Use {COMMERCIAL Parking lot Roof Open /Landscaped )INDUSTRIAL Parking lot Roof Open / Landscaped (TRANSPORTATION High DenyIinterstate, main` Low Density secondary, feeder) Rural Sidewalk MISC. PERVIOUS Managed pervious Unmanaged (pasture) Forest RESIDENTIAL 2 -ac lots (New) I 2 -ac lots ( Built after 1995) 2 -ac lots (Built before 1995) 1-ac lots (New) 1 -ac lots (Built after 1995) 1 -ac lots (Built before 1995) Y2 Y -ac lots lNew) Y -ac lots l Built after 1995) Y -ac lots +Built before 1995) Y. -ac lots (New) % -ac lots (Built after 1995) Y. -ac lots Built before 1995) Y -ac lotsSNew) lots (Built after 1995) Y -ac lots (Built before 1995) Townhomes(New) Townhomes (Built after 1995) Townhomes Built before 1995) Multi - family New) Mufti - family (Built after 1995) Multi- family (Built before 1995) Custom LOt Size INIW I Custom Lot Size Built after 1995) Custom Lot Size (Built before 1995) Roadway Driveway Parking of Roof Sidewalk Lawn Man cl pervious Forest LAND TAKEN UP BY BMP BMP DETAILS BMP Volume Reduction ( %) TN Effluent Concert. TP Effluent Concert. (mg/L) (mg/L) Green Roof 50% 1.08 0.15 Level Spreader, Filter Strip 40% 1.20 0.15 Permeable Pavements 0% 1.44 0.39 Sand Filter 5% g1 g1 or N2 0.92 0.14 Water Harvesting u ser defined 1.08 0.15 We Mention Pond 30% 1 1.01 0.11 Wetland 20% 1 1.08 0.12 •if treating commercial parking lot, TP effluent concentration = 0.16 mg/L ----- - - - - -- CATCHMENT1 CATCHMENT2 CATCHMENTS ----- - - - --- CATCHMPNT4 . CATCHMENTS Does BMP accept the outflow f no no no no no no -- -- no no no I no no no no no no I no no no no no no I no no no no no no no no no Area treated Area treated Area treated Area treated Area Treated by BMP p2 that is by BMP 43 that is Area Treated by BMP #2 that is by BMP e3 that is by BMP not treated by BMP not treated by BMPS by BMP nottreated by BMP nottreated by BMP, (ft') #1 al or g2 (W) g1 #1 or e2 w lft'1 Ift'1 � Ift'1 (ft'1 I w I TOTAL AREA TREATED BY BMP (ft): 720,787 998,529 578,329 0 0 TOTAL AREA TREATED BY SERIES (ft 2): 11 2,297,645 0 om another Catchment? Use, indicate which one(s).(Land use a no no no no no no no no no no no no no Area treated Area treated Area Treated by BMP g2 that is by BMP e3 that is by BMP not treated by BMP not treated by BMPs (ft2) g1 #1 or a2 (ft') (ft) I I -eas entered below are in addition to the watershed areas treated by contributing catchments).) no no no no no 1 no no no II no no no no no II no no -- -- -- I no no no no no I -- -- no no no II no no Area treated Area treated Area treated Area Treated by BMP p2 that is by BMP p3 that is Area Treated by BMP 42 that by BMP "or treated by BMP nottreated by BMPS by BMP not treated by BI (H') #1 41 or p2 (k') #1 (ft ') (k') (ft') I II I 0 CATCHMENT6 no no no no no Area treated I no I no I no I no no I — no no no no no no no no no no Area treated Area treated Total Land Use BMP 43 that is Area Treated by BMP p2 that is by BMP p3 that is Area Treated By treated by BMP s by BMP nottreated by BMP nottreated by SNIPS pg BMPs ff1 or 42 (ft') g1 g1 or N2 Ik ) (ft') (ft') (ft') .I p II II II I� II �I i II �I II �I II II II II II II ) II II II II II II II „ II 9 IIuII 0 7 8' I C Allowable Total Land Use Area to be Treated Based on Post -Dev. Areas (W) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 286,702 75,856 276 402,304 268,742 0 441,301 3 175,720 C;, 75 3. Development Summary BMP3 Development: Crystal Lake Prepared By: A. Hutchens Date: March 3, 2015 WATERSHED SUMMARY Ver2.0 BMP VOLUME REDUCTIONS /EFFLUENT CONCENTRATIONS REGION: Piedmont TOTAL DEVELOPMENT AREA (ft`): 6,510,557 Volume Reduction TN Effluent Concen. TP Effluent Concen. Pre - Development Conditions Post - Development Conditions Post - Development w /BMPs ( %) (mg /L) (mg /L) Percent Impervious Bioretention with ( %) 0.5% 23.8% 23.8% IWS 50% 0.95 0.12 Return to Instructions Annual Runoff Volume Bioretention (c.f.) 1,001,785 4,840,546 3,183,061 without IWS 35% 1.00 0.12 Return to Watershed Characteristics Total Nitrogen EMC (mg /L) 1.58 1.32 1.13 Dry Detention Pond 0% 1.20 0.20 Total Nitrogen Loading L Return to BMP Characteristics (lb /ac /yr) 0.91 3.66 2.06 Grassed Swale 0% 1.21 0.26 Total Phosphorus EMC 0.28 0.47 0.11 Green Roof 50% 1.08 0.15 Print Summary (mg /L) Total Phosphorus Loading Level Spdr, Filter (lb /ac /yr) 0.16 1.31 0.21 Strip 40% 1.20 0.15 Permeable Percent Difference Between: Pavement* 0% 1.44 0.39 Pre -Dev. & Pre - Development & Post -Dev without BMPs & Post -Dev. without BMPs Post - Development with BMPs Post -Dev with BMPs Sand Filter 5% 0.92 0.14 Percent Impervious (%) 23% 23% 0% Water Harvesting user defined 1.08 0.15 Annual Runoff Volume (c.f.) 383% 218% -34% Total Nitrogen EMC (mg /L) -17% -28% -14% Wet Detention Pond 10% 1.01 0.11 Total Nitrogen Loading (Ib /ac /yr) 303% 127% -44% Total Phosphorus EMC (mg /L) 65% -60% -76% Total Phosphorus Loading (Ib /ac /yr) 699% 27% -84% Wetland 20% 1.08 0.12 *Negative percent difference values indicate a decrease in runoff volume, pollutant concentration or pollutant loading. Positive values indicate an increase. *if treating commercial parking lot, TP effluent concentration = 0.16 mg /L BMP SUMMARY Ver2.0 CATCHMENT 1 CATCHMENT 2 CATCHMENT 3 CATCHMENT 4 CATCHMENT 5 CATCHMENT 6 BMP1 BMP2 BMP3 BMP1 BMP2 BMP3 BMP1 BMP2 BMP3 BMP1 BMP2 BMP3 BMP1 BMP2 BMP3 BMP1 BMP2 Wetland Wetland Wetland -- -- -- -- -- -- -- -- -- -- -- -- -- -- Total Area Treated 16.55 39.47 5175 -- -- -- -- -- -- -- -- -- -- Total Inflow Volume 1,229,131 3,523,406 3,626,037 - - - - - - - - - - - - - - Percent Volume Reduced 20% 20% 20% Inflow Nitrogen EMC (mg /L) 1.32 1.22 1.15 -- -- -- -- -- -- -- -- -- -- - -- -- -- Total Inflow Nitrogen (Ib /ac /yr) 6.13 6.82 4.98 - - - - - - - - Inflow Phosphorus EMC (mg /L) 0.506 0.380 0.220 - - - - - - - - Total Inflow Phosphorus (lb /ac /yr) 2.35 2.18 1.04 -- -- -- -- -- -- -- -- -- -- BMP Outflow Nitrogen (Ibs /ac /yr) . ' BMP Outflow Phosphorus (Ibs /ac /yr) . ' Catchment Outflow Nitrogen EMC (mg /L) 1.09 - - - - - Catchment Outflow Total Nitrogen (lb /ac /yr) 3.73 - - - - - Percent Reduction in Nitrogen Load ( %) 36% - - - - - Catchment Outflow Phosphorus EMC (mg /L) 0.130 Catchment Outflow Total Phosphorus (lb/ac/yr) 0.445 -- -- -- -- -- Percent Reduction in Phosphorus Load ( %) 73% -- -- -- -- -- BMP3 DURHAM CITY OF DURHAM Neuse, Falls Lake and Jordan Lake Developer Nutrient Reporting Form Please complete and submit the following information to the City of Durham Stormwater Services to 1869 characterize your project and assess the need to purchase nutrient offsets. See the CM OF NT:DKWE Citv Stormwater Performance Standards. For nutrient offset information, see nutrient offset intro PROJECT INFORMATION Applicant Name: Prepared by Garden View Realty, INC Aaron Hutchens Project Name (& Previous name, if applicable): (Site Plan #: Crystal Lake Subdivision at Croasdaile Farm Project Address (if available): Street: City /Town: County: Hillandale Rd Durham Durham Date: (mo/d/yr) Project (dec. degrees) IN: Long: (dec. degrees) PIN /PID #s: 3/3/2015 Locat'n: ILat: 36.0544746 (For the Jordan, Falls, and Neuse /Outside of Falls Watershed areas) - 78.939669 173133 Is this Redevelopment? I ❑ Yes ❑ No Development Type (Please check all that apply) Impervious Cover ( %) Pre - Construction: ❑ Commercial ❑ Duplex Residential 0.5 ❑ Industrial F�] Single - Family Residential Impervious Cover ( %) Post - Construction: ❑ Institutional ❑ Multi - Family Residential 15.9 (E) Mixed Use WATERSHED INFORMATION (See online map or alternative source for 12 -digit and 6 -digit IDS) ❑ Upper Falls Basin, 12 -digit Watershed ID: Applicable) 030202010304 I Jordan Lake Delivery Factors ( %) ❑ Lower Falls Basin, 12 -digit Watershed ID: Reduction Needed Nitrogen Phosphorus ❑ Neuse /Outside of Falls Basin, 03020201 State Buy Down Additional Site: Bank: Site: Bank: ❑ Jordan Lake (Upper New Hope) 6 -digit Small Offset Amount Delivered 5% if bank Total Delivered Watershed ID: Rate Target Name of Bank Name of Bank Neuse /Falls Lake Delivery Factors: There are no delivery factors, so the Delivery Factor = 1. DURHAM STORMWATER PERFORMANCE STANDARDS FOR DEVELOPMENT COMPLIANCE ALTERNATIVE Nutrient loading limits and on -site treatment minimum (Sections 70- 740(a) and Sections 70- 741(a)) Off -site treatment threshold ( %): IN: I 50 IP: 150 (Required on -site reduction achieved? IN: IYESIP: IYEE NUTRIENT OFFSET REQUEST (Must meet the offsite thresholds — see above) Loading Loading Nitrogen Loading / Offset Needs (For the Jordan, Falls, and Neuse /Outside of Falls Watershed areas) Rate Target 0.00 0.00 0.00 PE #: Phone #: 41363 stew rt i n c. c (1) (Where (A) (B) (C) (D) (E) (F) (G) (H) Applicable) 0) Untreated Treated Reduction Needed State Buy Down Additional Loading Loading Load Rate (Ibs /ac /yr) Offset Amount Delivered 5% if bank Total Delivered Rate Rate Target (from Compl. Project Size Duration Site Delivery (Ibs) not in City (Ibs) (Ibs /ac /yr) (Ibs /ac /yr) (Ibs /ac /yr) worksheet) (square feet) (yrs) Factor D * E * F * G limits (Ibs) H + 1 3.66 2.06 2.20 0.00 I 6,510,557 I 30 1.00 0.00 0.00 0.00 Phosphorus Loading / Offset Needs (For the Jordan and Falls Watershed areas) (A) (B) (C) Untreated Treated Factor Loading Loading Load Rate Rate Rate Target (Ibs /ac /yr) (Ibs /ac /yr) (Ibs /ac /yr) 1.31 0.21 1 0.33 Responsible Professional En (D) (E) Reduction Needed (Ibs /ac /yr) (from Compl. Project Size Worksheet) (square feet) 0.00 6,510,557 gineer's Name: 1A (F) (G) I (H) Offset Additional Duration Site Deliv (yrs) Factor 30 1.00 I Gamboa D * E * F * G Staff Name: (Aaron Hutchens (Staff e-mail: ahutcilens@ July 30, 2014 Version (1) (Where Applicable) 0) State Buy Down Additional Amount Delivered 5% if bank Total Delivered .ry (Ibs) not in City (Ibs) D * E * F * G limits(lbs) H + I 0.00 0.00 0.00 PE #: Phone #: 41363 stew rt i n c. c 919- 866 -4793 COMPLIANCE WORKSHEET Watershed (Select from Menu) Falls Lake Basin Note that if a nutrient bank is used to buy offset credits Jordan Lake Basin in order to achieve compliance with the alternative selected below, the bank must be located in the same Lower Neuse Basin watershed as the project site. Compliance Alternative (Pick one alternative, see descriptions and calculations below) 1 Nutrient loading limits and on -site treatment minimum (Sections 70- 740(a) and Sections 70- 741(a)) O Alternative percentage reduction option for Redevelopment that increases impervious area (Section 70- 0 740(b)) O Alternative percentage reduction option for Redevelopment that does not increase impervious area 0 (Section 70- 740(c)) O 0 Alternative for low impact development in Falls Basin. O Exempt from Stormwater Pollutant standards (Section 70 -739) Project Area Disturbance (Fill in yellow cell below) 1,488,829 square feet 34.179 acres TABLE 1 THRESHOLDS FOR APPLICATION OF STORMWATER POLLUTANT REQUIREMENTS Project Location Land Disturbance Limited Residential Multifamily & Other Jordan Basin 1 acre 0.5 acres Falls Basin 0.5 acres 12,000 square feet Lower Neuse Basin 1 acre 0.5 acres Note: Thresholds are based upon land disturbance since the applicable basin Baseline date. The Project is Located Outside the Downtown Area (select from menu list) Per Section 70 -736, Downtown Area means the Downtown Tier, Compact Neighborhoods, and Suburban Transit Zones as shown on the Durham Comprehensive Land Use Plan most recently approved by the Durham City Council. The Project Type is Limited Residential (select from menu list) Per Section 70 -736, Limited Residential means single family and duplex residential and recreational development. Multifamily and Other Development means development not included in Limited Resdiential, and includes but is not limited to multifamily and townhomes, and office, industrial, institutional (including local government institutional), and commercial development. Other key definitions from Section 70 -736: Development means Land Disturbance which increases impervious surface on a property, or alters its location, or results in an increase in runoff from a property or a decrease in infiltration of precipitation into the soil. It includes both existing development and new development. It does not include agriculture, mining, or forestry activities. Redevelopment means Development on a site where structures or impervious surface already exists. It is a category of new development. Version 2 DRAFT, April 5,2013 Nutrient Loading Limits and On -Site Treatment Minimum ORDINANCE REQUIREMENTS Sec. 70 -740. (a) Nutrient Loading Rate Limits. Development not exempt under subsection 70 -739 shall construct and implement SCMs so as to limit the post construction loading rate of nitrogen and phosphorus from the project area to the limits set forth in Table 2 below, or shall comply with an allowed alternative as set forth in (b) through (d) below. A portion of the reduction requirements for nitrogen and phosphorus may be met through off site measures or payments as set forth in 70 -741. TABLE 2 NUTRIENT EXPORT LOADING RATE LIMITS Project Location Export Limit Ibs /acre /year Nitrogen Phosphorus Jordan Basin 2.2 0.82 Falls Basin 2.2 0.33 Lower Neuse Basin 3.6 not required Sec. 70 -741 (a) On site nutrient treatment requirements. Nitrogen and phosphorus reduction requirements may be met, in part, through offsite management measures or the purchase of nutrient credits. At a minimum, however, in the Jordan and Falls Basins a percentage of the required nitrogen and phosphorus reductions must be achieved through onsite treatment, in the amount shown in Table 4 below. In addition to meeting the percentage reductions below, in the Jordan and Lower Neuse Basins, nitrogen export load from the site must not exceed 6 Ibs. per acre per year for Limited Residential, and and 10 Ibs per acre per year for Multifamily and Other. (Note: offsite credit purchases do not meet TSS removal requirements, which must be met onsite.) TABLE 4 ONSITE NUTRIENT TREATMENT REQUIREMENTS Project Jordan - General Falls - General Falls and Jordan within Downtown Area Minimum Onsite Nutrient Treatment Nitrogen Phosphorus *40% of required *40% of required reduction reduction *50% of required reduction *30% of required reduction *50% of required reduction *30% of required reduction Version 2 DRAFT, April 5,2013 Falls and Jordan exceeding thresholds but with less than 1 *30% of required *30% of required acre land disturbance reduction reduction Lower Neuse No percentage reductions apply, but the 6/10 nitrogen export limit described in paragraph (a) above must be met No percentage reductions apply, but the 6/10 nitrogen export limit described in paragraph (a) above must be met *The "required reduction" is the difference between the post development loading in pounds per acre per year multiplied by the site area in acres before treatment minus the loading target, in pounds per acre per year multiplied by the acres. The percentage shown in the chart above is applied to that difference and the resulting number is the amount in pounds /year of nutrient reduction that must be achieved onsite. CALCULATIONS - ENTER VALUES IN YELLOW CELLS Nitrogen Post Loading Rate Untreated (Ibs /ac /yr) 3.66 Post Loading Rate Untreated (Ibs /ac /yr) 1.31 Post Loading Rate Load Rate Target Treated (Ibs /ac /yr) (Ibs /ac /yr) 2.06 2.2 Phosphorus Post Loading Rate Load Rate Target Treated (Ibs /ac /yr) (Ibs /ac /yr) 0.21 0.33 Reduction Needed (Ibs /ac /yr) 0.00 Reduction Needed (Ibs /ac /yr) 0.00 ONSITE CALCULATIONS - ENTER VALUE IN YELLOW CELLS BASED ON TABLE 4 Onsite Reduction Required Onsite Reduction Achieved? Required ( %) Nitrogen Phosphorus 50 YES I YES In the Jordan and Lower Neuse Basins, the nitrogen export loading rate from the site does not exceed 6 Ib /ac /yr for Limited Residential, or 10 Ib /ac /yr for Multifamily and Other. Version 2 DRAFT, April 5,2013 N/A Alternative percentage reduction option for Redevelopment that increases impervious area ORDINANCE REQUIREMENTS Sec. 70 -740. (b) Alternative percentage reduction option for Redevelopment that increases impervious area. As an alternative to meeting the loading rate reductions described in (a) above, Redevelopment not exempt under 70 -739 that increases impervious area may reduce the pre - development nutrient loading rate from the entire project site for nitrogen and phosphorus by the percentage loading rate reduction shown in Table 3 below. The pre - development nutrient loading rate is calculated as of the Applicable Baseline Date. Load reductions already achieved shall be credited. TABLE 3 PERCENTAGE REDUCTION OPTION FOR REDEVELOPMENT. Project Location Percent Loading Rate Reduction from Pre -Dev Loading Rate Nitrogen Phosphorus Jordan 35% 5% Falls 40% 77% Lower Neuse 30% Not applicable CALCULATIONS - ENTER VALUES IN YELLOW CELLS Nitrogen Pre -Dev Loading Post Loading Rate Load Rate Target Reduction Needed Rate* (Ibs /ac /yr) Treated (Ibs /ac /yr) (Ibs /ac /yr) (Ibs /ac /yr) 0.00 NONE Phosphorus Pre -Dev Loading Post Loading Rate Load Rate Target Reduction Needed Rate* (Ibs /ac /yr) Treated (Ibs /ac /yr) (Ibs /ac /yr) (Ibs /ac /yr) 0.00 NONE * As of the Applicable Baseline Date. ONSITE CALCULATIONS - ENTER VALUE IN YELLOW CELLS BASED ON TABLE 4, above Onsite N Reduction Onsite P Reduction Required Onsite Reduction Achieved? Required ( %) Required ( %) Nitrogen Phosphorus li YES YES In Jordan and Lower Neuse Basins, the nitrogen export loading rate from the site does not exceed 6 Ib /ac /yr for Limited Residential, or 10 Ib /ac /yr for Multifamily and Other. Version 2 DRAFT, April 5,2013 [Hill Alternative Percentage Reduction Option for Redevelopment that does not Increase Impervious Area ORDINANCE REQUIREMENTS Sec. 70 -740. (c) Alternative percentage reduction option for Redevelopment that does not increase impervious area. Redevelopment not exempt under 70 -739 that is outside the Downtown Area and that does not increase impervious area shall reduce the pre - development nutrient loading rate, calculated as of the Applicable Baseline Date, by 10% if reductions are achieved entirely onsite, and by 15% if reductions cannot be entirely achieved onsite. Table 4 is not applicable to this alternative. CALCULATIONS - ENTER VALUES IN YELLOW CELLS Nitrogen Pre -Dev Loading Post Loading Rate Load Rate Target Rate* (Ibs /ac /yr) Treated (Ibs /ac /yr) (Ibs /ac /yr) 0.00 Phosphorus Pre -Dev Loading Post Loading Rate Load Rate Target Rate* (Ibs /ac /yr) Treated (Ibs /ac /yr) (Ibs /ac /yr) 0.00 * As of the Applicable Baseline Date. Draft Reduction Needed ( %) Nitrogen Phosphorus 10 1 10 Draft Reduction Needed (Ibs /ac /yr) none Draft Reduction Needed (Ibs /ac /yr) none Is N reduced by at least 10 %? YES Is P reduced by at least 10 %? YES If either N or P is not reduced by at least 10% on site, a 15% reduction is required for both. Final Reduction Required Nitrogen Phosphorus /o Ibs /ac /yr /o Ibs /ac /yr 10 1 NONE 10 1 NONE Alternative for Low Impact Development in Falls Basin ORDINANCE REQUIREMENTS Sec. 70 -740. (d) Alternative for low impact development in Falls basin. Development in the Falls Basin will be considered compliant with the nutrient reduction obligations of this Section 70 -740 if it demonstrates that it meets the post development hydrologic criteria set forth in Chapter 2 of the North Carolina Low Impact Development Guidebook dated June of 2009, as it may be amended from time to time. ❑ This development meets the post - development hydrologic criteria in Chapter 2 of the North Carolina Low Impact Development Guidebook dated June 2009, as amended. NO NUTRIENT OFFSET REPORT IS NEEDED WITH THIS ALTERNATIVE. Version 2 DRAFT, April 5,2013 Exempt from Stormwater Pollutant standards (Section 70 -739) ORDINANCE REQUIREMENTS Sec. 70 -739. (a) Exemptions for limited disturbances. Development in which Land Disturbance, calculated cumulatively as of the Applicable Baseline Date, is less than the thresholds in Table 1 below is exempt from the standards in subsections 70 -740 and 70 -741, subject to paragraphs (1) and (2) below. TABLE 1 THRESHOLD FOR APPLICATION OF STORMWATER POLLUTANT REQUIREMENTS Project Location Land Disturbance Limited Residential Multifamily & Other Jordan Basin 1 acre 0.5 acre Falls Basin 0.5 acre 12,000 sq. ft Lower Neuse Basin 1 acre 0.5 acre (1) Common Plan of Development. Development that is part of a Common Plan of Development shall be included in the calculation. If the applicable threshold set forth in Table 1 is exceeded, all other portions of the Common Plan are subject to the requirements of this Article; (2) Redevelopment and Existing Development, maintenance of treatment. Redevelopment and Existing Development that are exempt under these thresholds must continue to maintain and reconstruct all SCMs in compliance with approved plans, prior ordinance requirements, and City Standards. (b) Other exemptions. Additionally, Development is exempt if: A. it qualifies in its entirety as Existing Development; or B. it is located in the Downtown Area and does not increase impervious area over the Applicable Baseline Date; or C. it is undertaken by a state or federal entity. (Note: Review and approval by the state must be demonstrated); or D. it is a City transportation project in the Jordan basin. ❑ This project is exempt because it is below the applicable land disturbance threshold. ❑ This project is exempt because it qualifies entirely as Existing Development. ❑ This project is exempt because • It is located in the Downtown Area and • It does not increase impervious area over the Applicable Baseline Date. ❑ This project exempt because • It is undertaken by a state or federal entity, and • A demonstration of review and approval by the state has been provided. ❑ This project is exempt because it is a City transportation project in the Jordan Basin. Version 2 DRAFT, April 5,2013 STEWART Project: Crystal Lake Subdivision Date: 03.03.15 Project No: C13098 By: ACH Total New Impervious Area Type of Land Cover Area (ac) New Impervious (current project) 23.73 Required treatment area 20.17 FDA to SCM Treatment Device Device #1 -Level Spreader and EFS 90% Impervious Surface to SCM (ac) 24.99 Provided treatment (ac) 22.49 Total Treatment Provided 22.49 Weighted TSS Runoff Calculation 95% J: \C13098 - Croasdaile Farm SF \CALCS AND DATA \Stormwater \Spreadsheets \Cl3098_TSS Calculations.xlsx TSS Appendix 5 5. Plan Sheets a. SW1.0 - Existing Impervious Areas b. SW2.0 - Proposed Impervious Areas c. SW3.0 - 1 Year Pre - Development Drainage Area Map d. SW4.0 - 2/10 Year Pre Development Drainage Area Map e. SW5.0 - Post Development Drainage Area Map E ca 0 0 0 CV cl C) C) 0 / \ b / / / \ 0 \ O / I \ I � '1 I I I I II I II \ / / / / / / II / II / I / I I II � I II \ i / / i I I I \ / \o / / �1 f - - - - -- 11 \ I, it II I I l LEGEND ROADWAY DRIVEWAY OPEN /LANDSCAPED FOREST ROOF / 1 I 1 I I - 1 I / \ CROASDAILE FARM PKWY 1 / / / 1 1 1 \ / 1 1 � i 1 / ,P/* STEWART 101 WEST MAIN STREET DURHAM, NC 27701 T 919.380.8750 Client: FIRM LICENSE #: C -1051 www.stewartinc.com PROJECT #: C13098 GARDEN VIEW REALTY, INC 2451 CROASDAILE FARM PARKWAY, SUITE 101 DURHAM, NC 27705 ATTN: MR. DAVID BEISCHER PHONE (919) 383 - 5575 dbeischer @gardenviewrealty.com Project: CRYSTAL LAKE SUBDIVISION AT CROASDAILE FARM Vicinity map: Seal: Issued for: N CARP''% ,........ ! , ,,.•oFFSSioti.,N )RTON RD Of`S'um lot S PRELIMINARY - DO NOT USE FOR CONSTRUCTION No. Date SITE PLAN SUBMITTAL Description 0 100 200 400 Scale: 1 " = 200' Title: EXISTING IMPERVIOUS AREAS 0 Cn U) W AN Project number: C13098 Sheet: Date: 03/03/2015 Drawn by: AH SW1.0 Approved by: AG E 0. N N O N cl O (0 / r - - -t � III I / \ I / \ J / \ / i II / / / / i 1 \ I I I I I I / \ \ / 7 J h� / / / / / , II / / ROADWAY _ h I / / / / i 1 \ I I I I I I / \ \ / 7 J h� / / / / / , II / / ROADWAY _ h SIDEWALK /PATIOS MANAGED PERVIOUS _ FOREST _ ROOF / LAND TAKEN BY BMP O \ I \ \ 1 \ 1� 4� LEGEND 0 ROADWAY _ DRIVEWAY SIDEWALK /PATIOS MANAGED PERVIOUS _ FOREST _ ROOF _ LAND TAKEN BY BMP ,P/* STEWART 101 WEST MAIN STREET DURHAM, NC 27701 T 919.380.8750 Client: FIRM LICENSE #: C -1051 www.stewartinc.com PROJECT #: C13098 GARDEN VIEW REALTY, INC 2451 CROASDAILE FARM PARKWAY, SUITE 101 DURHAM, NC 27705 ATTN: MR. DAVID BEISCHER PHONE (919) 383 - 5575 dbeischer @gardenviewrealty.com Project: CRYSTAL LAKE SUBDIVISION AT CROASDAILE FARM Vicinity map: Seal: I I � Issued for: N CARP% ••'•p0- ss /oti'••, Ly -!MG t...•- Q, 1P ...••�O AN` )RTON RD dt,44m gal S PRELIMINARY - DO NOT USE FOR CONSTRUCTION 1 1 1 1 No. Date N I - 1 I 1 / I / 1 / I / • Scale Title. � 1 1 SITE PLAN SUBMITTAL Description 100 200 1" =200' Cn U) w D CD 400 NORTH PROPOSED IMPERVIOUS AREAS Project number: C13098 Sheet: J� Date: 03/03/2015 Drawn by: BL SW2.0 Approved by: TS M CV 0 0 0 CV co CD / 1 \\ \ \ / ( \ \ \ \\ \ \ ���J` — / / /// f \ /�Jll \// )J \ (�/` /J // // y _ / / \ / / / / /ice / / /// �\ / /�L� = = =^'` ti - - -\ ��! l / -- - -- -, 1 \ \ / / � // / I (� tip\ --�— / / � --/ // \ / / / // / r / / J \ /t /j /ll / \ - - / —/� / (r ti) /� /J // / / //r // - -\ \ \ \ < 1 \ \ / // )III \ / ( // // /i/ / /// // J } �� /� \ \ \ \ \ ( — _ // //^ \ Z­- \ J 1( //i r l// I "J /xj //j �\\r_ /J \/ // j l ) \ \\-./ /// / /r \ \ \� \.� -- J � � //% —� J� /� \�1 \(1\� � J l/ / /rr jll( // / \ \✓ / /J( / / \� \\ \� C / \ \(J /((1 /1 /�\ \\� \ti_ ._n /i >> // /� > > )II II �� �� �)���� —r \\ \\ 1111111r1�1� / \ / \ \ \ \\ \✓ � / I / \ \ 1 \ \— / —� \\ \1\ \\ \ �� �� — J /� � / 1 JJ /\\ \ /\ �� i — // l I JII =— // < < T � -- — _= r /))� — ��7L —_/// / / / /// / /�' /� ji /j �,,. —/ �� i / / /r-J /// / j\\ I / TIME OF CONCENTRATION�/ l ll(I( /� \\ / //t J( /% ( I /..-\ `. — ���f J (( —�_ /' J \ \��\ �� \ \��� \i /% I f � /�� � � - - / /// �� \ \�`_�<1 \` >\ \ / ( , 1 . SHEET FLOW �.\ / /� / \ \\ \' 1 \\ /L \\ \�-� (I/(\ \\ -rte 12 � I 1 \ \ - -' \-/ � � / 1 \' \�'�'•� '� � �\ =� // t \ \ / / ) \�I ) .,- -/ / .,� ( / / � v,14 /J� �- -\ \ \\ \r ^ � ,-�►. -'� �� \ \ \ \\ �� \ \� = —_J ) \�\\ \ /// /� / / ? 11 " \\ \ ---..� / / J,—/ I 1 / \ J / /// / / / //i � - /��� —� � /1 ( \ 1 > \ \\� 1 \ 1 \\ \ t \ \\ \\ � � � �/ \ \ \ / ) 1 1 I X / \ \\\ \\ \ ( �� \ \ \ \ 1 \ \ \\ \ 1( � ♦ ` \ \ \ �\ \ \\�\ lr\\ _ _ / / /�� 1 I J� / \ / / 1 I / / / 1 \�`\\ \ \ f I � \� \�,�\\� ✓� ,( /!!IJJ�i � \\\ \a \ \\ 1 I { '' � /J I � 4 II — � \ \\ ) 1 \\ �// �— ^ - ---- �/J J% / �( j /�/ / //J j l I 1 \ \ I� (( � 1 IJn�� \ )r/ r\ / t / 1 I II � J ()J 1 11 I l r/ ( ((/ I /, /I I �(( (�� \ 1 \ \ \\ I ,��✓/ ) \ \\ � \_\_�1 !/ 11( ^\ \�. _ —/ 1 l / // / `> / / / / / /// / /I // 1 \/ \I J /�� ./ TIME OF CONCENTRATION (//// 11 ) l )( I I/(/ ( // \ -' , // ,1l�'(l 1 1I J� ld l � l / t / l l / (// / / (�J � � `� � \ \ \ \ \ \ \ \ \ \ ♦ � / / 1/ 1 II() J J( S \ / s' ./ ' ..., /- r SHALLOW CONCENTRATED FLOW '2' \/ \ / l / f r' — � � (/( / // /I� / (/ // //t ) ` / --�" ` J \ \ — / / I ll / 1 I I 1 I � 1 \ \ I III 1 I ((� — // J 11 / I I � ' l►` \ \1 `'`. \ 1 l 1 \ \ \ — � \ ` . � / ,//f \ I I , �,� {III \I \ \\ \\ / // /1 1I /� --� \ \ �� ♦ ( — \,, \ / 1 l)� �\ L �.`— J— �- \ \ \\ �\ �\ti ^ / / ..< /I 11 \ I I / �/ /JII .-.1 / / J/1 (I I ``/ / //) \G�` �� , _\ \ ` \ \ \\\ �\ /ll /) � � — \ -� �.\ \ \ � `����\ \ / / \ -��/ /- I� t J \ 1 l �/_ -rte-. 1 \ 1 J/ / )� J„_� -�,)S / f / / ,\— L% 11 r) /l�/ f\ \� ��J /-- J-J/ J /iJ 1 /lrJ �) J y \ \ // C (� /\ \ \\ �// /1111 / \\ �/ I ICI /)I \ \ \`�\ \ \\ \\ / /� // , / \ \ \\ \ \�\ — \~♦ 1 / — 1 \ S ( — \ < > 1 - \ \ / _ �_���� \ \ \`_z 1 J //� L��\ \ �_J ///(II{ ll(r�\ \/ i�� /�11 _�� �•= � i� /// I 1 �r \\ I I \\ \\` ♦r l \ > ) j -- / r� .� \ / � 11\� �/ J �\mil J I / / 1 �\ •--J�— �` l- -, - 1 1 (\ 1 (1 � — � \���- \� � I 11 rr �� / /�-c - � \�_ _��� ��'/ `\_l_._./ \ 1 f � \ ( \� ♦ � ( / 2_ � \\ \\ J / / ►Il 1 \ ��� —^ 1 \\ _ / Vim. /1 / —/ ) 1 \5 � \ ♦ 1 1) \ 1 Jai \ \ \ \ \ \\ \\ \ /) 11 1 \ r/ —� �--��� \— ���J \ —\ \� —` J I 1 I �\ \ \�� \ter j� / ) \ \ \ /J" ( ( /Jr\ > \t ti l( //I f —� � \ \ \ 1 1 1) \\ \ \ \ \ \\\l \\ / /(/ %/ l/ i� \`\ \� \= r— __�� \������ I II �\ \� / , l \ \ �•. r — \ \ \ \ \ ` \\\\ 111 \ J \�I\ �� )) /l1 / / j( 1 f J�✓`/ I / J / / �_ I \ \\ I) r ti � \ \ 1 1 -� \ 5,.. ,� ,, —. \ \\ \ \ � a � J III \ I 1 l l t / f � - � \ � � \ 1 \ \ / I) J 1 \ 1( / / 1 J / r-- ► � \ � V If / / / `' / 1 (I \ \ \ \\ �% ,lJ/ �l ( \ \l\ \ l \\ -- / \ \ \\ \ \ \ \ \ \ \\ i � , Jj ��� \� \ � \ ( ) I 1 J ( � �\ \\ I1 \ \ \ /// r \ \�\\\\�� \��\ \\�` // \ \\ \ / -- r — 1 \ \\ l ► 1 \1 \ \/�i --- \// / -- \\ � \ \ \ \11 \\ \111 \ \\ I �� \ � � --'\ L 1 1 ( 1 I(\ \ \ \\ (t \l- ^ \— : / % —� / //� J �(I //• � ( , / (/ // 1 l // /j //� /'% /i /, �� //� \ \ _— \ \ \ — \ \� �/ / l // I I� i� / I 1 ♦. J \ — \ \ \\ \ \ \--1 i \ ) / 1 –YR STORM ANALYSIS 1, POINT 1 //C 1 1 ( / r 1 � \ / — J f I( l 11{ J ��r/ / / 1// L,;ll 111 \� = -- --�-I� `��\ —J { l I` {t \ \ \\ /j / /// /i /�� \\ l l 1 JI 1111 I1 II I/ i �I' \, /1 \\\J^ \ ✓/ r /rJf//� /% ,/\ \l1I / /lam \ \\ �` \) L \ \ \ \ ^ — \ / ��/ > > J IIII �� 1 ( % PRE– DEVELOPMENT DRAINAGE /T J 1111 IIIII \ I \ 1 I — FOR 1 –YR STORM ANALYSIS 1l ( l 1 111 l 1 \ __ — \\ �- �/ // //l J I III \ I `. s � � ,-\ / �'i �l / \ \� � � \ \ \ 1 1 1 / r 11\ 1 \\ \ << — /i / /J /! / / \ � �i /""�. \ \1 \ I 1 \ / / / — II � — I _ it ( / � / / // >`"� ) 1 1 \1 t ) I 1 / ) r-- �_- ^-�_ -- l 111( I \ \ 111 \ 1 1 / / / / /'�t-�� \ \ \ \I 11 � _\ / � �' � .) / / /� /�� \ \\ ✓ t / 1� -, \/ —--- 1 I J i- / (( -{-(� / kit- \ / J /r\ V ( J t /J/ 7:__ � _= I \ \ \ \ \� \ / \� \\ \111 / / /� / /_ =� `c ti��•Z —_ _=�`� � ��_ =__ Z \`\ (�\\ � %/T1111 / � / q /) — -- =__— / /� / �/ — i// / r — �'� 1 r \ J 11111\ / -�= / � J / J I/l r/ /r�^ // — -- J I / �, I � 111 /; J /t�/ �/ �__ = = _ _ � =_ � \ \\\\ \ \\ �'-/ / — � 1 J) /(f J ( ) �` \\ 1 J �� / /- - . a�1' (/ / �r�.- \\ � \ ✓ 1 / // � -- / - r / , ._._ — _ l \ 1 � n J � (/ (/ l 1 I ) / / / i // / / /i /� % :\ \ �.. ` r 'i �` ��) I ( / / /�-- � // f \/ / / \ J I � � / / // � � \\ 1 111(( ((( I \ \ \11 I ( l J \\ \ I / \ \\ \ �— 111111 \ / \\\\\ / �� r \ l/ I/ //� > \ / / / / / \� `' � (1 I /// 1 . 1(11I 11 1 II ) � k\ r l _ J / //l / / / _ \ ,� � .-� -� � - //j✓ 1 /( �� %(1 rl / / /// \� �\\ %' / /� /J J�J'JJ /�� _ 1 �. )/ ( / / \ / /— -- �-- — ¢ROASbAILEJFARM \PION f \ � \ \ \ ,� I \ r � / r r\ \ \\ N I � /I // _=-= _= _=—= il)Illllll 1'! >T`I - // �� // / IjJI 11((1((111 (/ 1llllll11 I /II1 >111 J r/ / // J/ \ G I I I \1\ `\\\ ( /1 I 1 1 // J r JJ 1 I J l )— \, \ , J _ \ \ r I ( ► /J/ J II / rz�_ 1 1 ( \ 1 (1 ( ---� _— // /i/ , �J- 1 J J c l % / //jljl/ jl //� J1111 I � JJ111� �\ 1)I (J l l J(I J l J / 1 r _ — ..\ v/ � it / / /l \ \� \ \� \� - -/ //i \ ti� / /� /// /// / / / / %l( / ' t II l 11 1 1 J I — l/ \\ \\` — / i / /11 y� / / J \ \ C J / �\ f~—,,. .� t /�yii / /�/ / �i /// ._-- = �\\\\\\\\\ \\\\\ \1 I \ \ \ \( \(�(l( / \<«��\\C / ( ) 1 I I 1 1 \ Jl l l l JI (/ ( �/ / � �___ _ —J f' — — 1 ( \ \�� ( 1\ J �� /��/ J I ✓/ , i ,-- 1 / / / / / / / //� / // / �5 f ( 11 I 1 / \ `'ll\ 1 ► (c� 1 1 1 ( / / / J t / if -- �.,� j r / / 1 J \�,II)IJ( //f `N \ \�� \\� \\�_ /% /ii / / //i/ ,// I fl l ► ► / 1/ / / /fl/I1 /1 \1 /(r / /i /� J 1 / , ( (^ / ( l \ \ \ _ J / r I / 1 1 �/ STEWART 101 WEST MAIN STREET DURHAM, NC 27701 T 919.380.8750 Client: FIRM LICENSE #: C -1051 www.stewartinc.com PROJECT #: C13098 GARDEN VIEW REALTY, INC 2451 CROASDAILE FARM PARKWAY, SUITE 101 DURHAM, NC 27705 ATTN: MR. DAVID BEISCHER PHONE (919) 383 - 5575 dbeischer @gardenviewrealty.com Project: CRYSTAL LAKE SUBDIVISION AT CROASDAILE FARM Vicinity map: Seal: •�N CARD `.••FESSio •� "'L, )RTON RD 6143u= S PRELIMINARY - DO NOT USE FOR CONSTRUCTION Issued for: SITE PLAN SUBMITTAL No. Date Description 0 o! U) Lu W 0 0 100 200 400 NORTH Scale: 1" = 200' Title: 1 YEAR STORM PRE DEVELOPMENT DRAINAGE AREA MAP Project number: C13098 Sheet: Date: 03/03/2015 Drawn by: AH SW3.0 Approved by: TS M co 0 0 0 CV 0 M 2 / ` ^ _\ \ / \, — – —� \ r \ \ \ �� - i —� \ I / O / i / 1 ) I \ � 1 —/ r , , � S S1, r_ '- - -- \; \\( �` - --. , \ \_— / r \ I I I — 1/ // ( /(( / till \/ \ / j r / 1 / I 1 / /J/ _ J =_� J. / / / / / / �% / / 1 ( } / / ((( / \ �(� �r \ �^ \�, DRAINAGE AREA 'B' r - \ \ ( DRAINAGE AREA 'B' I J / ( (/ \ _ / - / / //i / /i J / - ) \ \ \ TIME OF CONCENTRATION - \ / \ - 1 TIME OF CONCENTRATION / - -/ / _ / / I /iir �\ - - �u \ \ / / / /// // / // // // / y \ CHANNEL FLOW 'S', 1) _ yr\ \ // \\ 1 I ( SHEET FLOW '1' f,/ % ( (I \\ /lJ %` ( /DRAINAGE AREA 'B' /�( ✓^ /j / /�\/ / /(J(1 `( \? ( % // //- / /J /�l( \�1- �� /// /�1 / \\ � �// // / / / / /�/ /i i / _ \ /1�. 1� ` ( ^� \�)( ty \� �/ /// / r• / \ r //� % /� / //i — /r / / /// r / /llt, // TIME OF CONCENTRATION /II,. r� /// ( r- �� ( \II 1\ (r \ \� \iJ /�J� / / /�Z) \ \�Jf�� /�� % \ \��` r 'i % / / / / / /� / /J � f/ // /) ( 1 DRAINAGE AREA 'A' \ \'SHALLOW CONCENTRATED FLOW 2 /� / i / / \ I (III 11)II( �; - � I \ _ �� r TIME OF CONCENTRATION SHEET FLOW'1', \� �, JJ /" / \ / ��- / / J I/I jVi / \/ .- I (' ✓ / // // �- /� /Gi j � ,J- L / ( / / // \ \ I / < { / / \ \ \\ \ti�� \ \ \✓ )\ / ^ = I \\ �.�` \ \\ DRAINAGE AREA 'B' ref_ /� ✓_ ^/\ / \ \ \\ \11 \ \`\ \ 1 / �\ \ %C /� \, \tit \� \ - \) \\ ��` \ / \\ TIME OF CONCENTRATION / / i/ _ \ \`� \� j / /j / /%/ / /� / /- \\` -� // / / / )I \((I 1's// yr' �� jj / / / / / / / /// J// / ///� / i % -� f ✓ /%� /i %j / / /j /�/ / I i f \ 1 \ \ \ \\ 1 \ \ \ �� �I` " \ \ SHALLOW CONCENTRATED FLOW '3' JI DRAINAGE AREA 'A' I l \\ . \ �.. \ � // \_% _ iii 5i ��• \ \ \\` -. � (Irr- 11 1 j /--- //j/ / / / '�\ -- / / 11/ \\ \ \\ � ^1/ '1- v\� -/// / /// /�� /J // ( Z / //^ ' � �� —��i "� ' \/ I i \ \\ � - - � �►-` - � TIME OF CONCENTRATION _ _ / \ \ - - - / - _ — DRAINAGE AREA B ;SHALLOW CONCENTRATED FLOW '2' \�� � ��� � \ - A ti - _"_ ��`( \\ \ \L ' TIME OF CONCENTRATION SHALLOW CONCENTRATED FLOW 4 / \ ll(III(,\\�- )1�/�//�'//'/ -- \ \ � ( / / . \ \\ \ � \ / (J I I I I � l \ - � -\ / -- o, ( / J . \ \\\� \\ \ � \� � \- — � / /1111 \ \\ /// / // J \\ \ �• /' J / ) � \ \ \/ !l / ( 1 /J��r /��'��� � /�i /� / / // � J / //' ` �J /(11 \ �\ \ .-i / / / /• \ \ \\ � (1 1 \\I\ \(/v-- .�11 - \I \ \� \� r \-• II i 1 \ \ ) \ I / /_✓ ✓ \ \ \\ \ \ \ -i�/ )) \ \ \..-. J/ / / � \ `V \ \ - \ / / � r / � \ \ \ \\ \ ` / / / / /// / %// . 'i ,-' r `1/ I \ J\ / 11 / I ( I > 1\\\ 1 \\ \ t \\ \ \ \ I / r- \ l \ \� �► \�, \ \ /� // \\ \ , \\ \\/ /) IIJII / / / /// /L\\ \ \ \\ \<<(� \ \\\\ \\ \ \ ♦ \ \ \ \\ II\ \1J 1 �� \ \ \� \� \ \ \��\\ \�)lr� \\ \_ /j \ /// / / /., /J 111` \\� \- r( / J J 1 f .�'\\ \\ - \// / // ( \ \ \ I (\ \\` (/ ( / /\ 1 '%�- \�� � \` \ \ \ \ l ♦ /III I \) \ <(I ,o �t \ - \ ---s 1 11 1 Illldll�(� \„ � / / - -•__ -/ / 1 �// /l1/ / � '// /l 1 1 /lJ /1 \ \( ) // c/ /(( l I / _ t, ( 1 I _J I1) \ \\ \ \ \ \\ / , / / / // III 1 r � ) f / ll \� / J / 1 �L -- - -- J / / //y 1 / J Ir� l DRAINAGE AREA 'B' � / � � _ ) 1 \ \ / J / / / r ( TIME OF CONCENTRATION 1 ,, 4► SHALLOW CONCENTRATED FLOW 6 1 I ) / 1 // / / / // Jfi/ j J ) ✓\ 1 (111 ( r/ / r / / / J / I / J \ 1 I /\ ( �I 1/J �l �-� ���/ \ \\ � —'` � ,� / /l /// / / / /�� 1/ 1/ ) \\\` J /JI ( 1 ) 4, I (II / (\ �/ I 1` / / /�/ // ��I /� J \ 1 1 \l \ \ \ \ - \ / 11 ^ \\ _ / I 1 / (l� / /1111 11 �/ \_ ,c \�`�� \\ 1 / 1 \ ­ -/\ I \lam /) /1 /l // \ \ / / \ \ \ \ I ) / / 1 1 �/ / \ 1 /J I / 1 I (J 1 \ \\ \ J I 11 ( ^ �• �► f \ I \ l�\ \� \\ \ / I I �\ - ' / / / / / i \J ► // / v (/ / / I / /// / / � I r ` �1� � 1111 \ \ \\ \_/ ) / /�/ ---- / � I \ \ \\ \ \\ \ \ ._„ J� ._.. =�_ i 1 \ \- ---` -/ / I (J \/ � � 1 -,�/ / / / /�J% - /// /// 1 � - \JcJ / �_� \\\ \\ Jam, -�-.� \ 1 \\ - �ry 1 1 \ \ \\ \ \t\ \ �\�\-ti ( PRE DEVELOPMENT ) J✓ 1 / /(�► I \ I I I I I / J / / - / 11 _ " \ 1 (\ / 2 /10 -YR DRAINAGE J// ANALYSIS AREA 'A' \ \ \\ \ \\ \ 1 I \ \ \ JJ S\l `'J \ ) \s , I ( /_ 1\ • r I J \ G f 1� � \ - \� �_�� -.\ � � \\\ � � � ��� /) / `�. � � r 1 r) \ 1 � \ -.� l/ / )��J„� -��)� / S � > c > > Mr 11((111 ✓, -- \\ \\��\ \� ( j \�\� \\ \\ �� /// II111 (\ �/ �/ / !( � \\\\ s�-- -`�`- J / /i > v J � \\ - 1 1 _ _ J 1 TT \� -_-- )1 J 1 / l 1 f \ \\ \\ ( J l ( ) 2 10 -YR DRAINAGE ANALYSIS AREA 'B' / \ 1 /1 / l ,)1 \ \ \ \ \ \ o / // �'' �� ����� -� --� -- - .\� \ \�. �__/ � 111 � \\ l ) l - - -_ \ \ \ \ 1., \ \ \\\ \ \\ r \ I lJ/ (1( / 1/\ > / ( 5 / >=t \.'' %)� ) • 1 \ \\ � \ 1 11 \ \ \ \1 \ \ \ \l � � \\\ \��j ( / % / /IJJ �= �� �`\ \� \�- -�.�_. -- _�`"���� \���_ /)��111111 � \1111 \ / /Il , -� I 1 l \ \\ \ \\ � -_� \ � \ ♦� - \ \\\ 1 �1�11 \1�1) 1 / // �J� \1J 1 r � / / � \ r <\ \l i = \\ \ \ \��.� / -� -- -. � \ \ \ 111 \ \\ (/ / ( 1 ✓ J / / - \ // l 1 L \ \\•r� \` \�`�j j /// l 1�l /ll / / / /// _� \ \ \� \ \\ \� �/ -,_ .i / -_ \ \�\ _..\_�- ) \� \1 \I � ) / / � � \ I II / \� ) J / l // I � 1 // \ IIIII(r- / ti / / /\�J \� / \� //// \ / (I (1 J/ /)\ ))I 11(x`\ 1 \` \\ \ \\\ I1 \ \ \ \ \ \ \ \\ \�ii�/ / / �\ \�\� \�\\ \\\ \�� / \\ \ / / J / I1/ // / � l \ � \ \ \ �.� 11 /' \ / / / l \ \ \\ � \ r \ , - - / / / �� i(/ / < \ I � 111 III / I t - � � 1 \ � / l / ,� �J ( \1 � \�\ \ \/ \ / / 1 1 \ \ ,\1 _ -,J /// / �/� \ \I IIII(I I / ��\ 1 J/ /� -/ ( \� / \ Jr �1 I /( / /// / Fi // ii /� 1 (1 II► I / \ - 1 \ 1 \-. c I� ♦ ) // 1111(1 /\ 1 I 1 J \ \ \ 1 I J �\\ ~ � \ \e1 \ I J � \ ( Il 1 / �/ / \ \1\ (1 ( l ^� J /�! / /�f / l J ���_ ��-- /j��!_- �`v1 \ \ \\ 1 11111(II((< \ \ \ \���= \ \ \ \\ \ \ ` \ \\ \ \\ \ \ \ \ \\�(� c� %i�11 \ ( \ 1/l �i� v� r J 11(x- I ( \ (J / / )l �i / -- - --� //, _ 1 1111 1 I \ \\ < \ \\ \ � / / 1 l 1 \ \1 II / / / / � < � \- PRE /POST 2 /10 -YR STORM �_ \�- / DRAINAGE AREA 'A' ANALYSIS POINT // / \ 1\ Il II \ \\ 11 1111 I\� I111SIIIJ J / 1/� 1 (X%> 1 l S J \\I \` !// ' r // /// / �j / / /l �( / //� �- -, ( J 1 \ I > \ / l S �\c J /r�� / /�� / / / -_ - __-- ;�-- .,,\\ -1)1 ll / /- = -�1= =� +� Il)I1' \ \`�� r 1111 / 2 ,.._. 1 / ✓ / /� � -� j / \l\ \. \\ \ \• �� y /i/ ( ��� � >/I \� 0 1 �, \1 1 \ ~ \ \ — / r \ / „ r -� / / ; ) / II / J I - ( 1 J� l( \\ \\\ I / / \ ) (\ /\ — — �l // 11 I ) ` \ \\ \\ `-, 1 I (r ( 1 �. \ /-' / \'lf / / /� /�' \ �/ / /i /,� ✓ �\\ )1111 ^ \ I ( (Ill( (tC \ \\ \ l / / PRE POST 2 10 -YR STORM \\ \ \1 \ \\ I \ 1`- `' /J /� /j 11 / / DRAINAGE AREA 'C' ANALYSIS POINT I %// \ \ \\ ✓ \� / 1 ( ( / IT I_ / / \ ())J / / %// \- � \1111 t � I \ \� / / -,> � / /� f // / \ /•Z�\ / 1 � f !,/ ( J / / (< I (( 1 \1 I I III\ ♦ � /�- � J�� \ 1 \lN- _ \ l \ ( / � � /i/ // -(-1 � 1 (1 r / J S t \ J /I � 111 1111 I ♦S - / < / /- J Y \ )\ 1 \ \1 I ( 1 /- <<- /� ��/r /� � ''� ': i \ \- - -= ��� J / 1 \ `_/^`� III (l (1 _- /\ \\ 1 1 / / / / /_�= ��.z, -_ -- _��� � \ \`� -__ . �� l�\ � r � ) III I/ \ \ l� - - / `C ((1/ (I 1l _ �� \� \\ \ \ 1 \\ \ \ 1 %) I //` (! / / / r DRAINAGE AREA A i / / //� - / N \'\ \1111 2 I/ ( \ / \ \_ f� - - TIME OF CONCENTRATION- J ' ' r/ / /— - -f /�• 1 „) \ l / /I l 1 ► )/ / /� //. SHALLOW CONCENTRATED FLOW 4 . / / J i / \ - .✓ f \,1 1 I l ) .. ,, 1 / J / // / I \ 1 / / / Z ,,� / //i �� / \— ._✓ / /— —\ J 1 ) � / l> \ � // /(1 1 I \ / /)\ 1 / /� � STORM 1`- _ /�/i DRAINAGE AREA 'B' ANALYSIS POINT r \\ 11 III ( ��II III/ i '-- =5 \ \ \\ \\ 1111 ( I /- // ,1\ � II I // / � _ _ , � \\ \� \� \\�\\ 1 IIIIII Ji( I II / / l / / / ✓ / / / -��� %/� _= \ \�\ \ \��, /_- ��JI1J)I 1111�'lll(I /-'\ � \ \llllllr / /�� / / / /�Jfl /IIIIII/ /11 /J 11 � \1� \IJI>I / /��/ 1 j�� /(111 ( / /// / � ,•� \ \\ // j-./ \ / / // - - J ., � � I 1 SHALLOW CONCENTRATED FLOW DRAINAGE AREA 'A' i�/ \ 1 I\ � (PROASIDAILE FARM _- TIME OF CONCENTRATION ( J //J ) 1 I / _I , , � / / / 1 >( >\ � ( 11 ( 3 1 / \\ \ \ � \1i\ \ \\ 1\\\\ \\ c I� II1 1 I J /�Il / \ ,1/ ( . \ \\ / / "— ', _ — — -�ti \` ( _ 1 i \ \I► 9), /'� / / / / /// /� /� — /� / /r_\ \\ \ \\ \_�__= =1 11 I \ \\ \�' 11 \I1 III 1111 \1111111 \ I I I 1 / /// / / � /i� // // 11 / ,-.,\ \��. \\ r�s• --\ 1 1 s� � / \� \\ ) 11 1 \1 \ \ ,� , \� 1 ( 1/ \ � 1 /r )1 / / II (/ III � / / J/ j Il / / / _�___ - = = /�i /J 1 lJ \ II11111(111 I(1 / /� /i / / / / /11 I�I I I I J 1 /J I I ( / /// / / /! C \ ♦ ( // _ / / \ \ \ 'A' I � CONCENTRATION TIME OF >// /� \1 \) �'1'/ JJ / / / //i �_ %'�'�' =`�_�� � =___ `_� —) /// JjJ / /JIII(1111(1(�Il(lll(� /J /(( /�/ IIII(III(I 1 (III � I 1111 )1(I 1 iJ/ / // /� 11 / J ---♦- \,-` -- 1 / / s� \ 1 J"� '2' , I (II (' Jj/ / ♦ _ / /!! %1 IlJ 11 III\ \ \1 j \\ ( j //( �JIII(I I I I 1 1 ( 1 )I (((J ( \ // l l (J JJ 1 / • ♦ � \ - ,- � -\ J %( ' J� /� -� - � \ \\ \ - . J / J l I // � ! SHALLOW FLOW IM./� -� 1 (l J l l J l (l 1 / / _ _ \ / // // I� - \ \ \ \ l / // _ / / l I '� l ` _ \ -.✓ '� // /// JI l / / // �� / / / —, _ - -�,_— \ \�` \\ (( // / J��'ll` c\ )I I J 1 f / i// /l / —\\ / J ( / 1 1�/1 J/ � / /� / / / / / /// / / /// / / //j / //f / /ice — �\ � �\ \ \ \ \ \ \ \ \\ \ \\ %( II / / / /// /� / � / ) / / f / / � /� //i � ji/ /� / / / /i / /' %= == ��� \ \� \\\\ \\ \ \\ 1111 1111 11 \(1(�(� < /� / /� / / // / / / /���i/ /(I(I 1 \ \ \\ 1 �II1 /j / /// I(1 \\ \1 // JII(l // /(I )I l / ! l ( / 1 � \ z� , �,�� /� � / \\/ J �__ = =_� / //J -�-' / / /� /J /' X11 I\ 1 ��� ) � \ > ( r--�/ %�`�r /J / ✓ � _- � % / / / /' /'��/ �i //, � /� / /// j/ /// /i i /// �_ J - — ��� \� \\� \\ \� \\\\\ \ 1 I \ \ \ \\ ((l ((< C«��\ \( ( ) 1 I I r) ( \ l (l I ( -. ♦ / � \ - = _ - - _ - , / _ 1 1 > \ ._ ,- / � / I / /♦ \ L PRE DEVELOPMENT _ i / - , % / J 2 10 -YR DRAINAGE / DRAINAGE AREA A ( A \ L / / / / - TIME OF CONCENTRATION I ANALYSIS AREA 'C' / '1' \ /' ��/ i/////// 'j ///�.��)111� \l� \ \I \I \1\1 \Il // _ �\\ Ili \I \I1 \1 \jl �IIII111�1j11 Iljlllllllllllljlllll (1 % /! /�i %J /�ll tjl'/ /Ii'-'I/\11�lllllj Ill /�i� \ \ \(ll IIJ( /// I 1 `) SHEET FLOW _ / - - -_- 1 ` ((-� 1 / ( I /l 111(1 (( r, �O)II\ 11 /1 // � � � i�iii �r - �\J lI / / � �;� `_ r /� 1 /`/ / / / /r //� �_ -�� / -_�_/ / J J /!/ / / �-� /// J/ \/I I J1 �1 r (�`/ ,J %j // J J I 1 ( I f \� / � \ Z \\ �1 J( 1 Jll /11 /Ill // l STEWART 101 WEST MAIN STREET DURHAM, NC 27701 T 919.380.8750 Client: FIRM LICENSE #: C -1051 www.stewartinc.com PROJECT #: C13098 GARDEN VIEW REALTY, INC 2451 CROASDAILE FARM PARKWAY, SUITE 101 DURHAM, NC 27705 ATTN: MR. DAVID BEISCHER PHONE (919) 383 - 5575 dbeischer @gardenviewrealty.com Project: CRYSTAL LAKE SUBDIVISION AT CROASDAILE FARM Vicinity map: N Seal: .0N CARD '�. 4q /_- )RTON RCd OIJA 0' Q201 S PRELIMINARY - DO NOT USE FOR CONSTRUCTION Issued for: SITE PLAN SUBMITTAL No. Date Description 0 U) LU W 0 0 100 200 400 NORTH Scale: 1" = 200' Title: 2/10 YEAR STORM PRE DEVELOPMENT DRAINAGE AREA MAP Project number: C13098 Sheet: Date: 03/03/2015 Drawn by: AH SW4.0 Approved by: TS M It 0 0 0 CV co 0 \ ) r 1 // 1 ( / / / ( / 1 ( s' ( ' ��_ -� \ \_,s > i I l / �j /( �zz i t s �- t \ \ �, // / / / // ' - / / I \ r / �_ \ 1 I / ! r I _ —� ` \ \� l > // // \\`\\\ /s \ C c r< / DRAINAGE AREA 'B' r — — \ \ \ \ 1 DRAINAGE AREA B / / / /� / / / / / I \ — \ \ // / // / i' i / / / / — J /r / / // I \ / —� /i/ / / / / BYPASS TIME OF CONCENTRATION \ / — \ / BYPASS TIME OF CONCENTRATION/' / (I I — //— CHANNEL FLOW '5' — ` , .r ' \ \ SHEET FLOW '11' /\ \ \� %, / /jam � .�/ 1 111 �\ �-- -��-�1 \l � ���% -. \ ,Ij ( - - \k,k 11 11 )j \ \\ ) 1/ . , � �. _ . \ \ 1 //� 1\ %�/ \J II \\ \\ \` \ ( \\ 1 I \ / \\ / / / / \\ \'\ \11� // l _` DRAINAGE L � �, %; \ J r \ /v — \ 1 � -- \1 � � \ � �. / k \ V / // \ f \ / // / \\ \ \ \ \ \ \ \ \\ .' \i1 �iJ \ \\� /.i �\ ~ll ( \v� '/ /// /' BYPASS TIME OF CONCENTRATION //f \ \ \\ \ _� ) / \ I( \ `\\ \ - /// ///� / ✓ SHALLOW CONCENTRATED FLOW .2_. DRAINAGE AREA 'A' \ \ \ \ / / / / — ✓ c / 1 111 11 I /' \\ ` � / i \\ / /// // / / / / // � — / / /// \ \\ \\ \\ ✓ L \ _ BYPASS TIME OF CONCENTRATION \ \\ \ \ \ — _ J / I / / 1 111 / \ \\ \\ _ f / ,i /i ✓ // ( I 1 — / c r �— — = // i)� L � — — / // / / ° / / / / / / / /� %\ SHEET FLOW 1 \< / AREA 'B' ; /�� ✓ //� J/^ \\ / / / / / /J % /// / /� \`. -- // / / /J Il /r ., /s✓ //i f, ^ -- /// // / /i /i L j- ^. /�_ —r /Jj/ / / /// i BYPASS TIME OF CONCENTRATION SHALLOW CONCENTRATED FLOW '3' / ` / j / 5 J ) \ \- -\\\ \ J' )l�\ ?� \`� \\ �/ �� ��J /."ilia•• • ', • -, ` / ( (� / /DRAINAGE AREA . A l - DRAINAGE AREA 'B' TIME OF CONCENTRATION BYPASS TIME OF CONCENTRATION SHALLOW CONCENTRATED FLOW .2 ,. SHALLOW CONCENTRATED FLOW 4 _ l DRAINAGE AREA TO DETENTION = — =J\ .,' / / / / /// � \ \�� \� �/ / IO1 \\ \�\ \\ Il J /Ill \ \ \ \ \� \\ \/� \, \\> �((��- / 11 �♦-\�/ J ,.BASIN 'A' .,.� \ \ \��\= ;/ / /(I(,- \ \\y/ / /// / // �1�\ �\ \ •.. \ J/ , I /rte N_, ^, / (/` �\ \�, \ \J \`� / / / / i / / / / / /ii / / /��j��i / //� � / /l�\ /1( \ I � 1 \ \ \ \�„ /� ? \ 1 / / � �'/ JII/ / DRAINAGE AREA \ 1 1 \\ \ / / / J / / /JI / // \ \ � //!) \ \ \ \\ \ \� \\\ \\ ( /C!\ ) \\ ( ( • -•�� /i /// \ \\ ?, /A \`- • \� \ \\ \ \ 1 \ ` \ 1 \ \ \� �� \ \ \ \ \\ \ \` \\ 1\ (rr� l� \l�) (I 11( I I \ J //) /1 \ \ \ \ \1 \ \\ \ \ �,, \ r / j/ SHALLOW�CON�ENTRATED FLOW TION 6'_ /�J ( ) J I IS \ \ \\ / ( / / �/ )/� // j J //� ff �/J ( ✓ J J !r/ / ( / / \ \ / ) \�( \\ 1 1) ( I 1 \ \ s ( .L., _ _ t J \ \ ) -�i / / / (�\ l l / I ) J I / / /�i // l c- - r - //��•1 \ \\ \ 1 \ �l ���\ /J // \�•��\� � \\\' \���� -'_-- ( J/ II /�`' /n // � d �� // �/ /f � /I /1 / /ter // .-� 1) � W / / �\ \ \ \���� J /// / /ll � ` \ \\\ \\\\ 1 I I 1 � I I I I III I IJI ti 111 I -� \/ / /( // // / \ \ \ \�� ,♦,,�'0 1 \ � \\ , \---- (/ � \\\__ / I J ('" / / / /i /rte / 1 ( 1 1 (\ A ( \\ \- \_-\•- /J \ \ \ \ \ \ \\ 1 I( - l J / / /)l / /// .� J \ � 111 \ -�''� %- r., I \\\\\ \ \ ll -- ti,- / \\ /- - / /- / // /// / S / i � \\ \ ` -- �_ / 1 I) / \ \ \\ \ \\ \ � \ > / l)) (J I ((/ / ;\ - /) J J J(J111/ (lJ lI/ / / \ I (/ '_ • \\ \ \ \\'`�\ / I ( / 1 I � / .' - � � � / \ � \ \ \\ \ \�\ � � �-`'� r � � ,; =� / l) f \ - _ ; _ / 111 IJ(l�l /1 / / / /If / \ \\ \ `!- I ♦r I \ \ \ \ \ \\\ ,� ��� J��\`- / / / l / //1 / % /ll(� /� \( /< I / II / 1 `♦ �♦ / >11) _ \` -�\ l �` - / i ((I 1 / r _ 11 1 ( / \\ \ r-L -~ \ / \ \ \ \ \ \ ✓ / l ldl, 1 \ \ \ ' 1 I \ \\\� - / 1 I l 1 . � \ / ( \) \\ \ 1l 1 11 \� �. \ � � \ \_ � � \\ \ � ` L `- � \�- ' % /Ji j JrIII / / /( //1 l I I / /JI /JII( � J / 1 I v \ l \ \\ ) _ � \\ \� S .� BYPASS DRAINAGE -�\ l I / I III1 \ \\ 1 \ \ / / (11 J \ \ t _ I 1 J J �l' S 1 1 ` ` = \ \ ` / ` c // 11 \ \�\ 1 . \ ( /r ,� / 1 l� \\� \ \\ti ^-, -, / /)..< /Ill \I I /�/ /Ill �/ / J/ //t AREA '/ � l \ J1 11 l c �= I� \ \ \ \ — \ \I I I (- \\ \ \\ \ \ � \ 1\ \ \\� \- -�' 1 I✓ � ( —``/ �( / // I \ <-- �� \/ _-'— \ \ \ \ \� \ \) � \� J� \ I / \ -- ,�J,�\ \I I � � /J1 J) (� ( J l/ /S\1 1 � s�. I \ ( J \ J\ 1 IJ J �\ \ ��\ I \ \ \ \ \ \\ \\ �' /// lj)1 /(�'l \ \I \ \�) \//(1111(1111, \ \ \ \ \ \ \�� \\\ \��y J� /, / �\\\ \ I 1 // ♦r — t l — �� — ~1 I; r 1 / (\ ( %�l� r� \�� \— \cJl� J��)% r J,)�J /J /lrJ J — 1 J /�( =__ //i 1, \ l )�\ J _� ♦� \ \ / / / / \ \ \ \ \ r � r I \. ) I S� \� \ \ \\� \ \\_�— / / 111(1 � �� /� /� ,-__- _�\ ,- / /viii )1 \� - /I 1 11 \1 \ \-\ \� '`� ( - - J -'�►� \ � / ,- -- //� \� ♦ / \ ) / /III Vim. I (l ( /� 11 J/t / ((J S i�\.J � \ \ � � ( / l) / III \ -, DRAINAGE AREA TO DETENTION BASIN / /ice- ��� \�\ \\ \ -, \ -- _ � \ \� \��� _�— � ) \ \\ \ _ \ \ `\ ♦ — ' I � \ll Jll J / / / l,, �I / J / �, \ �< \\ BYPASS DRAINAGE �J AREA 'B' a� \\ / / /\ �1 /// ti I \\ \\ �/ l /I((l \) \ \ \\ \\ \ / /ii/ � ` \ \ \ \ \ \� \\�� — �;,i /�( 1\ \� � \ \ � / / / // / ♦ / l / 1 I \ 1 111/ l t - � \ I � 11 ��/ --- I III J t / J, ,. / // — %�� _ ✓— \\ ; / /// /// 1 / ` - �/ �� %''�/ / /�'= \ \\ `,/ — \ \\ \ \ 1\ / / (I III II I1 \ \ \ \ \ ( I I J ) \� / �) z� S r \ - \( / �l /l (lJ PRE POST DEVELOPMENT ANALYSIS \ / l POINT FOR 1 -YR STORM ANALYSIS. t \ \\ — . — = r / ( / // / / ( - \ \\ \ \ \ \ 1(1) ( // � � ( i ` ) I j= - • - \ \ � V j / 1 )// /1 /Il r \ \ s i/ EXISTING CULVERT UNDER HILLANDALE. --' // /// / / / / / / -_ -- -�_/ /� � l l / / /// ij /�� \I\ _�_� \ �\ --� �\ \r \\ l ///�1 ))111 !1/ 1 / I J� � \ � / I I / /�- � \ \ \ 2 � 1• / /i ,J / /�� /\ \ , , - �_/ \ � 1 j l / / /// '/ �/ , - �/ /�/ � //�i �— � � - __ — — — � - - = _ _ _ _ = = / — /i �j = ="— \ \\ \\\ \ , , I I ll 1 ) f I ) I (I I II (I 1I I 1( ►1 \ \\ /_`_` \ �� \� / / ) / � � / ( `\l \ \ \\ 1 \ \ \ \ \ \\ \ \ I \ \ \ \\ \.\ \ \\ � � \ . \ \ �\\ 1\\� \ ,1 � 1�1�11\, l x� (1�\1 1, 1(1 II / I(I I / \/ \ J / c \e //- / / f J( / l ((1 J/ (� 1 I 1 \ / _ ' / // / / / // / / / ' / � / / . f / / // / i (l/ �//l' / � i f/ J l / �?\ ► , �-� ( (\ _ / � / 1 1 /�j ( / j \ ( \ l -7 > (I PR/POST 2 /10 -YR STORM DRAINAGE AREA 'A' ANALYSIS POINT / J / / / 1s I BYPASS DRAINAGE %'i/ "/i / /iiii �— �f= \ \� /(11)1\ \ \\\ i " / /�� // %i /i / /�� \\ J►/ AREA BII/ 1—. � I / � / ,. �/ � „i.. �I 1 ( J ���))I � / •1 \ 1 \ — / ,_ / S /" / / I ) , /�/ �! / /( // �-- /i' l \\ \\ \ \\ \��O � ) / / /�� /�(� ;�J J I \ \\ l�\ \ \ 1 � \--._ " JJ ) ` = �-/// '''✓ / -``= ) � � _- `\ \ \\ � (/ / /// I Ill/ ((/ ( //( .- \- _� / /✓ /JII JJ /III II II 111 1 - \ Ill Lf -,/ / \\ / / ;) /// // \ \ \\\ \�\� \`.. f /i // /// (" / / % 1 � L � -.. _ -_r - `-J / =, \� / � J / ? \��((/ // (/ / ,- /I \ \ -\\ � - / l // / ) � / ) I 1 1111 \ ( `_- - - -' J/ ll I I I\ I \ \ I _� / ) / � \ \\\�\� / � / /// r \\ . \\ � � \ \ l ✓ � / _ _ 1 r -YR STORM PRE /POST 2 /10 / — \ l \ 11111 v J J J f \ \) \ \ \ \\ ((1 — — ` I Ill/ ) I ( \ `\ \ 111 \ 1 \ I \ \I /// / 11 \ \\ !� ✓ l / r i ^^ // r DRAINAGE AREA 'C' ANALYSIS POINT J /l1 %/� / ll / Ji/ � �!_ -/ l l (( \ �\ %/ / / / (/ //I 1 \\ ✓� / I ( 111 Ill\ - � / / / / / /i / /�f ;-� \\ 1 1\ \ l ( l ( / -�- s �r /-- l (! \\ t / / 1 \� \\\ ♦S I \ \\ \ \ � \�I % /// /� /// // I I / - - --- \ \ ( /' �-___ r-` / / r �\ � / / \( \\ \ / / / /- --,// / / I I l 11 /_--- __f,/ / ( ((/ /( 111 /I►I / / / //� (I � rJ ,r/ \> 1 _ .- J \ / / (\ 1 I (/ // 1 / "� ) I \� _ // _ / / / _— %/� �__ = = %i % /�� /� \�; \ - \� ✓ / ) 1 Il \ /f -` I // - 1 h / BYPASS DRAINAGE \ \ 1 II I I I I \ ( (( ) AREA 'C' \ \ I (I (� r I) // (/ DRAINAGE AREA 'A' BYPASS TIME OF CONCENTRATION / /r / —/ —^ — I II/ \ , � \ \ I )( J I✓ l f / / / //( l I ) I 1 ( j 1 / / / /�-JI /j/ / _ -- _/_ \ / I /ll 1(J( ^ -� I // %/� = - _ \ \\ \ \\ \ \ \� / h I JJ111( 1 �\� \ \\ ) / l / \ \ \\ \�` \ \ 11 I J J SHALLOW CONCENTRATED FLOW '4' �riii /i'� _._..- / \��//T \ JII II(Ilr /�i ^�I( /l % / /=== ==� - =� = ���\ \ \ \� \� � \ \\ ✓ / /� \ \11(( I�' \ >/� \ \ \11 /i //\ \�\ 1 f � { - _/ \� -/, JI f / __ __ -_ - - __ I / / \ (III lllllll //���✓1 /I�ll��'i == — \ \� \�� \\\�\� 1 1111111\ c\r, / I / 1 , ✓ / / \ 1 (1 / / /I / /1 / /�� (I (IIJI l \\�\\ \ \ \\ 1)11 IIJ PRE /POST 2/10 -YR STORM r /lI DRAINAGE AREA 'B' ANALYSIS POINT 1 1 1111 I Ili I 1 111 \ \ \\ I 1 / - \ \\� \��_ = , \1\ \� II I I/ / /- - -� � \ \ \ \�\�\\ 1111 �I ( ► �( /� 1 \ I((ii � I � �J / J i � /�iji���`L" -: \ � ��\ - /� / _ .� � ( ( �- -' \ /i/ //l l/ ( �\ / /� / I \ // Il�� / /�r\\\\\J / / / /�_�`��� \ \��IIIIII (1111 J - \ \ \\ \ \11 \1 \ \ \�� \ \ \ll II)111 1 I IJI( - ,� / \\ \ \� / /i - _ \, �_�\���. % /�/- \I I I III / // / 1 I \ \ 1 I I 1/ 11 )J 1 \ / /l (( ,, 1 ( Jj,, /// /- _--"- ., II I II (// \\ \ 1 I J 111 \IIIII /III/ l l lI 1 / 11 \\ 11 (/ S / J /III /III III II /, \ I I l /,) IjJj) J��JlJlllllllll /l %lII)�JlllllJl // IIIII ti/ \ / J J J /�'`' �- \ • , ,' / / ✓ / / \ _ / � - \\ � // -`\ � I II 111(1 I I I / 1 11111/ / / / /// / / \ \\ \ I / �" / / (� 1 ) / / // L `' \ \ / '_ / — � � � . �! I 1 DRAINAGE AREA A / I( / / ` \\ / i— / / CRO SDAILE FARM _ ._ / — ( \ l ( \ r \ \ \ \ \ 1 I I II( / /ij / / /i / /J /// Jj (I /lllllll J 11 ) 1 I I I 1 \- J/( () f i / / / — \ \ v /' -- J <_ _ t ) BYPASS TIME OF CONCENTRATION - / ( JI/ J I 1 1 /'mil , r // / / / J/ (J / \ \ \ \/ l //� - _— " ( — _ �\ \ ✓ \\ `.SHALLOW CONCENTRATED FLOW 3 J1(/ / 1 � / // / /� ) / ♦� ' / \ • / t./ / , \ J / \ ' ( / - . .-C ; � �-� -- ,� \ _\ / , I > ) \ , \ I I () J-/1El 1 , ^\ � (_ - -I J \ 1 `\ D R\A\ I\ N \ AG \ E l AREA \ 'A' 1 BYPASS 'DRAINAGE' DRAINAGE AREA 1 1I l 1 / 1 1 � <_ BYPASS TIME OF CONCENTRATION SHALLOW CONCENTRATED FLOW '2' - / /// z i / / // lllllll \� \�� \ \1((l /j /Jljlll(111111 1111 1) � )111 /( / /!( l!\ � / /1''1 � ./� ,'I( /1 /1 / /.\) � _\ _- �/ 1 /, \ � - =� \\ ( I� \_J l / /// �J J( // - Jl l / l l ��i \,r �J�/ / / /// 1 /� \✓ % /�\( ii -' / Jl \ y I / / / J I �" / . \ _ l/ / // / / % / / / / / / / / / /// /�/ /� j/i %� /i — _ `� �� ��\� \ \� \ \ / / // // / % / / / //� �( / /j/ \ \ I J ~ — — 1 / DRAINAGE / ll /�/ \1( I% /1111\ �\ 1)(� �// 1 1 (I J J/ / J / 1 TO DETENTION 1 l / ) 1 J 1 /JII BASIN 'c'' \ = =_ )I I \ \ \\ 111\\ \ \ \ \1 ) Illlll 1JrJ)\\ (1 S 11 1 /Ill/ I / lI Jli (( ) ^J / r/� /. - / /� -_� 1 / / r \\ \ \ \\\ \ \ \11 I 1 I l 1 1 111\ \ \\�\ \ \ \\ \ \\\ / III -11 l < \< 1 J I ) l ( 1 / \ I t ?' >// / 'A' / DRAINAGE AREA / / i / 11 III \ \\ 1 \\ \ J 1 ) J \ l I // / / 1 ( %� \ / / / ✓ \ BYPASS TIME OF CONCENTRATION /r / / - — ✓ / / J ) ( ( 1 \ \ 1 \ C- SHEET FLOW '1' _• /— J / — /_ -- ...r � I ( ) 1 l�) 1 � Y-7 JN III /l/ (� ... ALI/ � STEWART 101 WEST MAIN STREET DURHAM, NC 27701 T 919.380.8750 Client: FIRM LICENSE #: C -1051 www.stewartinc.com PROJECT #: C13098 GARDEN VIEW REALTY, INC 2451 CROASDAILE FARM PARKWAY, SUITE 101 DURHAM, NC 27705 ATTN: MR. DAVID BEISCHER PHONE (919) 383 - 5575 dbeischer @gardenviewrealty.com Project: CRYSTAL LAKE SUBDIVISION AT CROASDAILE FARM Vicinity map: Seal: .0N CARD •oFESSioti., "'k )RTON RD- Of`S'u+�"at S PRELIMINARY - DO NOT USE FOR CONSTRUCTION Issued for: SITE PLAN SUBMITTAL No. Date Description U) W 0 0 100 200 400 NORTH Scale: 1" = 100' Title: POST DEVELOPMENT DRAINAGE AREA MAP Project number: C13098 Sheet: Date: 03/03/2015 Drawn by: AH SW5.0 Approved by: TS Appendix 6 6. Miscellaneous Information a. Wetlands Study b. City of Durham Site Plan Checklist A tip V- NCDENR North, Carolina, Department of Environment and Natural Resources Pat McCrory Governor r June 18, 2014 S &EC Steven Ball; 8412 Falls -of the Neuse S_ uite'104_ Raleigh', NC:27615 John E. Skvarla, III Secretary Subject: ,Surface Water Determination NBRRO #14 -169 Wake County Determination, Type: Buffer Call Isolated,or EIP'Call '® Neuse (15A NCAC 2B :0233) ❑ ,Tian- Pamlico (15AN- A 2B )0259) El Ephemeral /Intermitt'ent/Perendial Determination ❑ Isolated 'Wetland Determination ❑ Jordan (15A NCAC 2B, 0267) Projeci'Name: Lakefield Farm'Hillend'ale Road Tracts Location/Directionsa Property is located Hillendale and Guess, road in Durham Subject Stream:' UT'to Eno, River befeirminafion •Date: June 3', 2014 Staff: James Graham Feature/Flag Not Subject E/IYP *' Start@ Stop@ Soil USGS Subject To; Survey Topo to Buffers ,Buffers A X P throughout; throughout X' X. B X P• throughout _ throughout X C X P, throughout throughout X D X •E X - ;E, X P throughout, throughout X F X I na,S01 throughout X Pond X -X X _ *E!T - Ephemeral/IntermitteriUPerennial None Carolina - - - atura!!r� North Carolina Division of Water Resources, 1628 Mail Service,Center Raleigh, NC'27699 -1628 Phone (91'9),791--4200, Internet - www ncwateroualb -or4 Location 3800 Barrett•Drive Raleigh, NC 27609 Faz (91,9) 788 -7159 AwEqual Opportunity /Affirmative Action Employer -.50% Recycled /10 %PostConsumer Paper Lakefield Farm Hillendale Road Tracts Durham County June 18, 2014 Page 2 of 2 Explanation: The feature(s) listed above has or have been located on the Soil Survey of Wake County, North Carolina or the most recent copy of the USGS Topographic map at a 1:24,000 scale. Each feature that is checked "Not Subject" has been determined not to be a stream or is not present on the property. Features that are checked "Subject" have been located on the property and possess characteristics that qualify it to be a stream. There may be other streams located on your property that do not show up on the maps referenced above but, still may be considered jurisdictional according to the US Army Corps of Engineers and/or to the Division of Water Resources (DWR). This on -site determination shall expire five (5) years from the date of this letter. Landowners or affected parties that dispute a determination made by the DWR or Delegated Local Authority may request a determination by the Director. An appeal request must be made within sixty (60) days of date of this letter or from the date the affected party (including downstream and /or adjacent owners) is notified of this letter. A request for a determination by the Director shall be referred to the Director in writing c/o Karen Higgins, DWR WeBSCaPe Unit, 1650 Mail Service Center, Raleigh, NC 27699. This determination is final and binding unless, as detailed above, you ask for a hearing or appeal within sixty (60) days. The owner /future owners should notify the Division of Water Resources (including any other Local, State, and Federal Agencies) of this decision concerning any future correspondences regarding the subject property (stated above). This project may require a Section 404/401 Permit for the proposed activity. Any inquiries should be directed to the Division of Water Resources (Central Office) at (919)- 807 -6300, and the US Army Corp of Engineers (Raleigh Regulatory Field Office) at (919) -554 -4884. If you have questions regarding this determination, please feel free to contact James Graham at (919) 791 -4256. Res6ehtfully, Danny Smi , Supervisor Water Quality Section Raleigh Regional Office cc: RRO /SWP File Copy •9 �,� ,I! it ', � - ��, + Y / ,GY�h 11 !1 A, � Y s6 kltC 1 N _ � -_• 21. -• _ _ -_ _ __ Yom✓ _ _ _ Mf j Gr \ TI- B Ai C MfB MfB y i 1118 � r� We - j M118 - V y Cc WSB r HeB N58 w It ��• .+ fie F HeB t - r !' Fr8 lri V 'u a . y rr3iyy W w C UO wo CrB r ! Web tr i yC r . ...._ � ._ Project No. Figure 2 -NRCS 10656.W?! Soil Survey Map Project Mgr.: Croasdaile Apts SB Crystal Lake Site Soil bF Environmental Consultants, PA Scale: Durham County, NC g411F&Ihof'— Rwd.Suiu 104 Mcigh S(' 27613• Phone<919)84&5%0-1u(919)94(9460 ..nde..� 1" = 1320' Durham County Soil Survey 515114 Sheet 16 i ue1 ..J• 1 011111 mill 1 1.11 iii L Soil & Environmental Consultants, PA 8412 Falls of Neuse Road, Suite 104, Raleigh, NC 27615 • Phone: (919) 846 -5900 • Fax: (919) 846 -9467 sandec.com May 9, 2014 S &EC Project No.: 10856.W7 Lakefield Farm, LLC Attn: David Beischer 2451 Croadaile Farm Pkwy, Suite 101 Durham, NC 27705 Re: Detailed Wetland Delineation and Stream Buffer Evaluation Lakefield Farm Crystal Lake Site Durham County, NC Mr. Beischer: On May 8, 2014, S &EC personnel completed the wetland delineation and stream buffer evaluation on the Lakefield Farm Crystal Lake Site is Durham County. You will find the attached report detailing our findings. Maps that further document the wetland and stream related site characteristics are also attached. Please review this information and call our office if you have questions. The next step in the wetland and stream verification process is to perform a site visit with the Army Corps of Engineers' agent for Durham County. In addition, a site meeting will also need to be conducted with the NC -DWR agent for Durham County and possibly the local municipality representative. Please contact S &EC is you are interested in proceeding with these verification meetings. As you move forward in planning your development, S &EC personnel are available for site plan review and permit consultation services. Please contact S &EC if you have any questions related to wetland and stream regulations or if you need clarification of the attached report. since ly, Steven Ball, RF Project Manager Attachments: 1) Wetland Delineation Report 2) USGS site vicinity map 3) NRCS Soil Survey 4) Wetland & Stream Sketch Map 5) Requirements for Delineation Maps 6) Agent Authorization Form S& Soil & Environmental Consultants, PA EC 8412 Falls of Neuse Road, Suite 104, Raleigh, NC 27615 • Phone: (919) 846 -5900 • Fax: (919) 846 -9467 sandec.com DETAILED WETLAND DELINEATION & NEUSE RIVER STREAM BUFFER EVALUATION REPORT FOR THE LAKEFIELD FARM CRYSTAL LAKE SITE On May 8, 2014, S &EC personnel completed a detailed wetland delineation and Neuse River stream buffer evaluation on the Lakefield Farm Crystal Lake Site. Please see the attached sketch map for evaluation area. The subject property is located on the west side of Hillandale Rd. approximately 2 miles and 1.5 miles north of I -85, respectively. Figure 1 and Figure 2 show the location of the site on a USGS topographic quadrangle and Durham County Soil Survey. EXECUTIVE SUMMARY We have determined that jurisdictional streams and a number of wetland areas generally account for the jurisdictional waters observed on the site. The attached wetland sketch map depicts the approximate location of the streams and wetlands identified during our evaluation. Please refer to the sketch map and the results and recommendations section below for more detailed information. SCOPE OF WORK The detailed wetland delineation consisted of traversing the property on foot to examine soils, vegetation, and hydrology across the site to identify areas that meet the criteria for jurisdictional wetlands as described by the procedures set forth in the Coms of Enaineers Wetlands Delineation Manual (January 1987 — Final Rebort). Areas on the site with positive indicators of hydric soils, evidence of wetland hydrology, and presence of hydrophytic vegetation were flagged and approximately sketched on a topographic map. Proof of wetland hydrology would be the existence of hydric soils with oxidized root channels in the upper 12 inches of the soil profile, water borne deposits, drift lines, scour marks, drainage patterns, regional indicators of soil saturation, etc. Surface waters such as intermittent and perennial stream channels, ponds, and lakes, which are also subject to regulation by the US Army Corps of Engineers (USACE) as waters of the US, were also identified. These surface waters may also be referred to as jurisdictional waters to indicate that they are within the jurisdiction of the USACE. It is important to note that wetlands are also classified as waters of the US and regulated by the USACE. S &EC's Neuse River stream buffer evaluation consisted of examining each feature on the site that is shown on the most recent version of the US Geological survey's 7.5 Minute Quadrangle or Durham County soil survey for applicability to the Neuse River Basin riparian buffer rule using NC -DWR stream evaluation techniques. Figure 2 shows the location of the site on the relevant Durham County Soil Survey map. May 13, 2015 S &EC Project #: 10856.w7 Page 2 of 4 RESULTS & RECOMMENDATIONS The result of the wetland delineation and Neuse River Buffer evaluation is discussed below. Wetlands and Jurisdictional Waters: We have determined that jurisdictional waters (i.e., streams and wetlands) exist on the site. Please refer to the attached "Wetland Sketch Map" for approximate locations. Three jurisdictional streams were observed during the site evaluation, the approximate locations of which are illustrated on the attached wetland sketch map. Streams identified on -site include: • Feature A (Mill Creek) is perennial throughout the property. Below the dam of Crystal Lake, there is a spillway and main channel. Both of these will likely be perennial. • Feature B (UT to Mill Creek) will likely be perennial from the property line to its confluence with feature A. • Feature C (UT to Mill Creek) is a perennial channel that flows from the southern property boundary to a confluence with feature A. ■ Feature D (UT to Mill Creek) is believed to a broken segment of linear wetlands. ■ Feature E (UT to Mill Creek) originates off property and then flows into feature A. This feature will likely be considered perennial. ■ Feature F (UT to Mill Creek) is an intermittent channel that originates at flag S01 and flows south into Feature A. There is a marginal stream above flag S01 that will need to be reviewed by the regulatory agencies. Surface waters on this site flow into Mill Creek in the Neuse River Basin, which has been classified in NC -DWQ's "Classification and Water Quality Standards Applicable to Surface Waters and Wetlands of North Carolina" as WS -IV; NSW. The wetlands onsite were identified as being a Bottomland Hardwood Forest wetland type as outlined in the publication "'A Field Guide To North Carolina Wetlands." This wetland type is common throughout the piedmont region of North Carolina and is found mainly along headwater streams like the one onsite. The USACE should verify our wetland delineation. Water Supply Water Rules: The surface waters on -site (i.e. perennial stream) potentially subject to the Water Supply Water Rules includes Feature A (Mill Creek) below the dam. No other surface waters are indicated as perennial features on the most recent USGS Topographic Quadrangle. A representative from the NC -DWR must confirm our determination regarding the subjectivity of the aforementioned channel(s) in order for our determination to be valid. 1 "A Field Guide To North Carolina Wetlands "; Department of Environment, Health and Natural Resources, January 1996. May 13, 2015 S &EC Project #: 10856.w7 Page 3 of 4 Neuse Buffer Subjectivity: The surface waters on site (i.e., intermittent stream, perennial stream) potentially subject to the Neuse River Buffers include features, A, B, C, D, E, F and Crystal Lake. Features A, B, C and E will likely be subject throughout. Feature F will likely begin at flag SOL S &EC does not believe feature D should be subject. A meeting with the NC -DWR will be necessary to confirm the subjectivity of these features as well as the required buffer width. Please also note that this site is located within Durham Watershed Protection Overlay E -B. All perennial streams (A (including Crystal Lake), B, C and E) onsite will likely contain a 100 foot buffer per City of Durham UDO. Regulations A general list of regulations that apply to jurisdictional wetlands and waters present on the site are discussed below. Please be aware that other local, state, and federal regulations not included in this list may also apply. S &EC personnel are available to discuss these regulations as they apply to your project. Neuse River Buffer Rules: The Neuse River Basin: Nutrient Sensitive Waters Management Strateav: Protection and Maintenance of Riparian Areas with Existing Forest Vegetation 115A NCAC 2B.0233) rules apply to 50 -foot wide riparian buffers directly adjacent to surface waters in the Neuse River Basin (intermittent streams, perennial streams, lakes, ponds, and estuaries), excluding wetlands. The rule defines surface waters as features approximately shown on either the most recent version of the soil survey map prepared by the Natural Resource Conservation Service (MRCS) of the US Department of Agriculture (USDA) or the 7.5- minute quadrangle topographic maps prepared by the US Geologic Survey (USGS). Surface waters that appear on these maps are not subject only if an on -site determination by the NC Division of Water Quality (NC -DWQ) shows that they fall into one of the following categories: 1) Ditches and manmade conveyances other than modified natural streams; 2) Manmade ponds and lakes that are located outside natural drainage ways; or 3) Ephemeral (stormwater) streams. Water Supply Waters Rules: Mill Creek (A) is mapped as a perennial stream below the dam on the USGS topographic quadrangle. Those perennial streams identified on the USGS within a classified water supply watershed require a 100 -foot buffer for new development activities with greater than 24 percent "built upon" area (i.e., percent covered by impervious or partially impervious cover) and a 30- foot buffer for activities with less than 24 percent built upon area by the NC -DWQ. (These buffers are in addition to the any other stream buffers. The stricter of the two buffers applies to these stream channels.) May 13, 2015 S &EC Project #: 10856.w7 Page 4 of 4 Wetland Permitting: The current Nationwide Permits were issued by the USACE on March 19, 2012. The USACE Wilmington District issued revised Regional Conditions for the 2012 Nationwide Permits. We recommend you forward a conceptual site plan to our office for review by one of our permitting specialist, who can best advise you of the specific permitting needs as you progress through the planning process. Generally, wetland impact permits are issued on a per - project basis as determined by the USACE. The USACE has determined that impacts on parcels sub - divided from larger tracts are sometimes considered to be cumulative to existing impacts for the large tract. If this is the case, then thresholds for notification may not apply to your project and impacts to streams /wetlands must be considered in light of existing permits. Limitations Our evaluations, conclusions, and recommendations are based on project and site information available to us at the time of this report and may require modification if there are any changes in the project or site conditions, or if additional data about the project or site becomes available in the future. This report is intended for use by Lakefield Farm LLC on this project. These findings are not intended or recommended to be suitable for reuse on extensions of the project or on any other project. Reuse on extensions of this project or on any other project shall be done only after written verification or adaptation by SOIL & ENVIRONMENTAL CONSULTANTS, PA, for the specific purpose intended. CONCLUSION The Lakefield Farm Crystal Lake Site evaluated by S &EC during May 2014, contains both jurisdictional streams and wetlands that would require preconstruction authorization for impacts (i.e. road construction, lot fill, stormwater pond construction, etc.). The next step in obtaining jurisdictional feature approvals is to conduct a site meeting with NCDWR and USACE to confirm our buffer start points, as well as the wetland delineation. .�7 Heights-- e' Jf! A[� .'UMSTEAQ 16 ` A KI 5 Ni -Soo-- A�O 1; CAnpr J. r 1-P 3, tE9A RRVIEW 4� r LYR40CE LDW4"L NDA RIRG SS F 7`1 Oon A.- i oRl tq, �7 50 MARNE Vf� 0';1 ' E-,&f DRS a _ . Ury"') I. J 4 11 t. Bus A'11 70 Project No. 10856.W7 Project Mgr.: SIB Scale: 1" = 1320' 5/5/14 Figure 1-USGS Quadrangle Map Croasdaile Apts Crystal Lake Site Durham County, NC NW Durham Quad D ✓ K L*e A 0 RD A ILE", KIRKWOODDR WRLAV CAMMIF ST C T, 41 CAHYER5T a KINK RD AVE Soil & Environmental Consultants, PA M 12 1'.11-or N.— Ih.d, Suit, 104. Nal.idi. NC 1%,.w (919) .40A91 • Far (919) 1-16-9 167 y No f � }� Esc Now W .� k1,1 - 511N r MfG �' sB r Ch ApS Mt M}B Mf Gr GaB r1 1 , ��.a i�,y ;,r• 1� � . Ire `� 1 C 'rote I __.. Mt6 • h � ` W56 Z r H M fC 'rS I �,� • 1'L fi _ .... - .NSB w WwiC '� u was f �. ✓ i HeB ar p i 114 �, �.� wwc iie8 { 4y 4rrr * WwC rB � , r C. L I4 ,� � '\J 't i � �y r •�.�?''p• i iNWCi CfB cra Project No. Figure 2 -NRCS 10856.W11 I Soil Survey Map Project Mgr.: Croasdaile Apts SB Crystal Lake Site Soil i Environmental Consultants, PA Scale: Durham County, NC 9 F.Us.rNe eR..SS. 04 .RJ.igh.VC?7615•Aanr.(919)546. 5900- F.:(919)SI6.9467 ��.� 1-- = 1320- w -_ Durham County Soil Survey a 515/14 Sheet 16 Oro F t rl.%K—kt!�ff "ll .1211-orl Detailed Delineation of Waters of the US Suitable for Preliminary Planning Only S&-EC reserves the right to rl this map based on more fieldwork, .0 0 1 and any other additional information. Approximations were mapped using X\ topographic maps, air photos and ground truthing. If the site is going l detailed delineation should be approved and to be disturbed, S& 14 permit te d by the U. S. Army Corp s of Engi neers as requ ired. If the u ser oL_ 'V this work desires ani accurate map of the regulated features flagged by S&EC, they should retain a NC Registered Professional Land Survey r to 0 N;�' N\ locate S&ECs flagging. . k'j1' A- M ilk IF N�\ f 11B ft CH lit VF F of It T 11 Id' ja Y/ 25B tt 18B 96-110 ft ch y 95ft82 65 C1 Stop M Ike V oil EM.N . . . • I Fri I %VM111 NFT"" It 't, fill 77-81 ft Pond N V tip Y Q.. di I 1. V11 -- - - - — - " - !� W I. Jurisdictional Determination Request REQUESTS FOR CORPS APPROVAL OF SURVEY PLAT Prior to final production of a Plat, the Wilmington District recommends that the Land Surveyor electronically submit a draft of a Survey Plat to the Corps project manager for review. Due to storage limitations of our administrative records, the Corps requires that all hard - copy submittals include at least one orir-inai Plat (to scale) that is no larger than l 1 "xl7" (the use of match lines for larger tracts acceptable). Additional copies of a plat, including those larger than 11 "x17', may also be submitted for Corps signature as needed. The Corps also accepts electronic submittals, of plats, such as those transmitted as a Portable Document Format (PDF) file. Upon verification, the Corps can electronically sign these plats and return them via e-mail to the requestor. (1) PLATS SUMUTTED FOR APPROVAL Must be sealed and signed by a licensed professional land surveyor 0 Must be to scale (all maps must include both a graphic scale and a verbal scale) Must be legible E] Must include a North Arrow, Scale(s). Title, Property Information Must include a legible WoUS Delineation Table of distances and bearings /metes and bounds /GPS coordinates of all surveyed delineation points Must clearly depict surveyed property or project boundaries ElMust clearly identify the known surveyed point(s) used as reference (e.g. property comer, USGS monument) F] NVhen wetlands are depicted: • Must include acreage (or square footage) of wetland polygons • Must identify each wetland polygon using an alphanumeric system Version: December 2013 Page 8 Jurisdictional Determination Request When tributaries are depicted: • Must include either a surveyed, approximate centerline of tributary with approximate width of tributary OR surveyed Ordinary High Water Marks (OHNIr'M) of tributary • Must identify each tributary using an alphanumeric system • Must include linear footage of tributaries and calculated area (using approximate widths or surveyed OHWM) • Must include name of tributary (based on the most recent USGS topographic map) or, when no USGS name exists, identify as "unnamed tributary" all depicted WoUS (wetland polygons and tributary Ivies) must intersect or tie -to sluveyed project/property boundaries Must include the location of wetland data points and/or tributary assessment reaches Must include, label accordingly, and depict acreage of all waters not currently subject to the requirements of the CWA (e.g. "isolated wetlands ", "non - jurisdictional waters "). NOTE: An approved JD must be conducted in order to make an official Corps determination that a particular waterbody or wetland is not jurisdictional. Must include and survey all existing conveyances (pipes, culverts, etc.) that transport WoUS Version: December 2013 Page 9 Jurisdictional Determination Request 11 (2) CERTIFICATION LANGUAGE F] When the entire actual Jiuisdictional Boundary is depicted: include the following Corps Certification language: "This certifies that this copy of this plat accurately depicts the boundary of the jurisdiction of Section 404 of the Clean Water Act as determined by the undersigned on this date. Unless there is a change in the law or our published regulations, the determination of Section 404 jurisdiction maybe relied upon for a period not to exceed five (5) years from this date. The undersigned completed this determination utilizing the appropriate Regional Supplement to the 1987 U.S. Army Corps of Engineers Wetlands Delineation Manual." Regulatory Official.. Title: Date: USAGE Action ID No.: When uplands maybe present within a, d picted Jurisdictional Boundarv: include the following Corps Certification language: "This certifies that this copy of this plat identifies all areas of waters of the United States regulated pursuant to Section 404 of the Clean Water Act as determined by the undersigned on this date. Unless there is change in the law or our published regulations, this determination of Section 404 jurisdiction may be relied upon for a period not to exceed five years from this date. The undersigned completed this determination utilizing the appropriate Regional Supplement to the 1987 U.S. Army Corps of Engineers Wetlands Delineation Manual." Regulatory Official: Title: Date: USACE Action 1D No.: Version: December 2013 - Page 10 Jurisdictional Determination Request (3) GPS SURVEYS For Surveys prepared using a Global Positioning System (('rPS). the Survey must include all of the above, as well as: be at sub -meter accuracy at each survey point. 0 include an accuracy verification: One or more known points (property comer, monument) shall be located with the GPS and cross- referenced with the existing traditional property survey (metes and bounds). Rinclude a brief description of the GPS equipment utilized. Version - December 2013 -_ Page it Soil & Environmental Consultants, PA 8412 Falls of Neuse Road, Suite 104, Raleigh, NC 27615 • Phone: (919) 846 -5900 • Fax: (919) 846 -9467 smidec.com PROPERTY OWNER CERTIFICATION / AGENT AUTHORIZATION Project Name/Description: S &EC Project # Date: The Department of the Army U.S. Army Corps of Engineers, Wilmington District 69 Darlington Avenue Wilmington, NC 28403 Attn: Field Office: I, the undersigned, a duly authorized owner of record of the property/properties identified herein, do authorize representatives of the Wilmington District, U.S. Army Corps of Engineers (Corps) and Soil & Environmental Consultants, PA (S &EC) staff, as my agent, to enter upon the property herein described for the purpose of conducting on -site investigations and issuing a determination associated with Waters of the U.S. subject to Federal jurisdiction under Section 404 of the Clean Water Act and /or Section 10 of the Rivers and Harbors Act of 1899. This document also authorizes S &EC, as my agent, to act on my behalf and take all actions necessary for the processing, issuance and acceptance of a permit or certification and any and all associated standard and special conditions.This notification supersedes any previous correspondence concerning the agent for this project. NOTICE: This authorization, for liability and professional courtesy reasons, is valid only for government officials to enter the property when accompanied by S &EC staff. You should call S &EC to arrange a site meeting prior to visiting the site. PARCEL INFORMATION: Parcel Index Number(s) (PIN): Site Address: City, County, State: PROPERTY OWNER INFORMATION: Property Owner (please print) Property Owner Signature Date We hereby certify the above information submitted in this application is true and accurate to the best of our knowledge. Soil & Environmental Consultants PA 8412 Falls of Neuse Road, Suite 104, Raleigh, ITC 27615 • Phone: (919) 846 -5900 • Fax: ()19) 846 -9467 sandec.com June 9, 2014 S &EC Project # 10856.W12 Lakefield Farm, LLC Attn: David Beischer 2451 Croadaile Farm Pkwy, Suite 101 Durham, NC 27705 Re: Division of Water Resources / Water Quality Programs(DWR/WQP) Verification Meeting of the Neuse Buffer Rules for the property known as Hillandale Road (Crystal Lake property) ( + / -115 acres); Durham County, North Carolina Dear Mr. Beischer: On June 3, 2014, James Graham (DWR/WQP) and I reviewed the features potentially subject to the Neuse Buffer Rules on the property. Mr. Graham agreed with our determination that feature D is not subject to the Neuse Buffer Rule. Feature F will be subject beginning at flag SOL All other features will be subject throughout. Please refer to the attached maps showing the approximate location of stream buffer origins. Please note that the stream origin points and top of bank should be surveyed throughout the project for accurate location. Mr. Graham will send written confirmation of our findings. Neuse River Buffer Rules The Neuse River Buffer rules protect up to 50 feet from the edge of existing "surface waters" (intermittent streams, perennial streams, lakes, ponds and estuaries) found within the Neuse River Basin. The 50 -foot buffer basically consists of two zones. The first zone is measured 30 feet landward from the top bank of streams and intended to contain an undisturbed- forested area. The second zone is measured 20 feet from the edge of the first zone and is intended to contain a vegetated buffer. A couple of notable points of the rules include; the allowance of grading with re- vegetating within Zone 2 (the outer 20 feet) and the requirement of mitigation for road crossings greater than 150 feet in width and utility lines running parallel and within Zone 1 of the buffers. Please call if you would like to discuss the rules in more detail. Additional Services If the buffer determination described above interferes with your site plan, please contact S &EC to discuss the possibility of a stream buffer appeal. An appeal with DWR/WQP must be filed within 30 days of the determination. Please call or write if you have further questions. We will gladly make time to discuss any permitting issues that may arise from this or other wetland/stream determinations. Sincerely, even Ball, RF Project Manager Attachments: 1) Site Map i 50 -56 CL �W 32B tt 26B C•orlfl ,ri -ned Stan- S01 Start F F'. l."VI ..� Detailed Delineation of Waters of the US Suitable for Preliminary- Planning, Oniv S &EC reserves the ri,ht to modify this map based on more fieldwork. and any other additional information. Approximations were mapped using topographic maps, air photos and ground truthing. If the site is going to be disturbed. S &EC's detailed delineation should be approved and permitted by the U.S. Arm} Corps of Engineers as required. If the user of this work desires an accurate map of the regulated features flagged by S &EC, they- should retain a NC Registered Professional Land Survevor to locate Sa -EC's flagging. 57 CI 3' �r r 95 tt 82 65 CI Stop L 66 CI . W, 4 s • f. f , � � arRiir ■rr arrrrrrrr . • • 1 ■iiirRrr■ � � + fiiir•iii �P • ti. f ! Pty_ 4` S � .- r• ��r • •� �l���lll!r'i � —�,4 i�� �� /r � 1 � .+ 1 \ err ✓�yE �.` 1 ■�'fr frP /,rte` ^, _ °°4 i �.�.•.., I � r j i �'^ f � rl�f+rrrr. Nil yjr .f r. -- v lffl �f • it � I rY "mil , J P 1 i. • 1 !r r 1 1 r f 1 � 1 1 Ln � `n a —_ Ln E m Z at CL ct1 D moue Soil & Environmental Consultants, PA 8412 Falls of Neuse Road, Suite 104, Raleigh, NC 27615 • Phone: (919) 846 -5900 • Fax: (919) 846 -9467 sandec.com June 19, 2014 S &EC Project # 10856.W13 Lakefield Farm, LLC Attn: David Beischer 2451 Croadaile Farm Pkwy, Suite 101 Durham, NC 27705 Re: U.S. Army Corps of Engineers (USACE) Site Meeting to verify the Wetlands and Waters of the U.S. for Hillandale Rd /Crystal Lake Site, Durham County, North Carolina Dear Mr. Beischer: On June 17, 2014, Mr. Eric Alsmeyer of the USACE and I reviewed the areas on the site potentially subject to USACE jurisdiction. Mr. Alsmeyer determined that feature F will begin at flag SO1. The upstream wetland will be jurisdictional. The drainage within feature D will also be considered non jurisdictional. Mr. Alsmeyer agreed with our delineation through the remainder of the property. Please see the attached sketch map for determinations. Impacts to "important streams" count toward the maximum 300' allowable under a Nationwide permit. If a project exceeds 300' of important stream impacts, the responsible party must apply for an Individual permit. The USACE has a 45 -day maximum review period to evaluate a Nationwide permit. However, an Individual permit has no maximum review period. Streams deemed to have `.`important aquatic function" may also require mitigation by the USACE for any impact and will require mitigation by DWQ if impacts exceed 150'. Unimportant streams require impact justification but do not require USACE mitigation. The next step in this process is to generate a wetland delineation map for submission to the USACE for approval and permitting. S &EC has not received a draft copy for a sign -off map to date. If you choose to have S &EC submit a map on the owner's behalf, please contact us or send a draft map for our review. Sincerely, _ Steven Ball, RF Project Manager Attachments: 1) Site Map S &EC Project #: 10856.W13 June 19, 2014 0 Q! Jurisdictional wetaInd mar " kr figh Ff J. V 7 rl, 'Confirmed by James Graharn of NCDWR -June 3, 2014 and Eric USACE 'o f srneyer of the 'on 6117114 X jiJAA.Ai. Cirilk Detailed Delineation of Waters of the US Suitable for Preliminary Planning Only M. k and any other additional infortnation. Approximations were mapped using S&EC reserves the right to modify this map based on more fie]dWOTk. topographic maps, air photos and ground truthing. It the site is going t I/ o be disturbed, S&ECs detailed delineation should be approved and it 14, M I permitted by the U.S. Amy Corps of Engineers as required. If the user of , this Avork de�ires an accurate map oftbe regulated featuies flagged by 'SeN y S&EC, they should retain a NC Registered Professional Land Suneyor to • locate S&ECs flagging. ago son f f man C, man NN „J ^- / ilff 1 f �� i 1 fir! is ` /�f I y 1 ;1,11 ! ; \ �� 7 ` r` 1fli f tit {f r ♦p♦ \ ..*, r . .- NA •t % Ir it 11 , , �11 I I ” . • \W,31 t t N NA • 11BftCH 45A ft CH r I MEN A o feature D • t not 'Subject or jurisdictional per 2 Ali *VVI A. 4 7 1% --,;6 7 W% - _ -4Z- 7 Fil ft Pond 7- f —::— Z 0 "r Z V. JI A Jr F% "Pill 7URHAM CITY OF DURHAM — STORMWATER SERVICES SITE PLAN SUBMITTAL CHECKLIST Department of Public Works 101 City Hall Plaza I Durham, NC 27701 919.560.4326 1 F 919.560.4316 Date: 03/03/2015 1869 www.durhamnc.aov ❑iY OF MEMNE PROJECT INFORMATION Project Name: Crystal Lake Subdivision at Croasdaile Farm Phase: Previous Project Name(s): N/A PIN (s ): 0813 -16 -68 -9042 Contact Person: Aaron Hutchens Company: STEWART Email Address: ahutchens @stewartinc.com Planning Case Number: D150OXX Phone: 919- 866 -4793 Fax: For each review submittal, including re- submittals, the entire Stormwater Impact Analysis (SIA) and submittal checklist shall be submitted. Partial SIA and checklist will result in notification of an incomplete submittal with no review performed. Contact Stormwater Services regarding redevelopment or expansion projects for modified requirements. The following checklist outlines submittal requirements. Initial in the space provided to indicate the following submittal requirements have been met and supporting documentation is attached. Initials AH (Check One) r INSIDE I_ OUTSIDE Watershed Protection Overlay (WPO). Indicate the WPO(s) where the project is located: (Check all that apply) _ F /J -A _ F /J -B _ E -A ✓ E -B _ M /LR -A _ M /LR -B If inside WPO, notation of WPO Standards is required on plans. AH (Check all that apply) _ Jordan Basin ✓ Falls Basin _ Lower Neuse Basin AH A legible copy of the United States Geological Survey 7.5 Minute Quadrangle map is provided, including map reference, with site boundary clearly shown and labeled. The map clearly shows all streams. AH A legible copy of the published Durham County Soil Survey is provided, including map reference, with the site boundary clearly shown and labeled. The map clearly shows all streams, soil types and soil type boundaries. AH Tops of banks for the streams are shown on the plan. [Contact the North Carolina Department of Environment and Natural Resources for stream identifications in the Neuse River Basin (Falls and Lower Neuse Basins). Stream determinations in the Jordan Basin shall be submitted per the Letter to Industry found on Stormwater Development Reviews' web site at New Stream Buffer Reauirements [First Revision to LTI 07 -03 -081 (25Auaust2011)1. AH All Watershed Protection Overlay, Neuse River Basin, Jordan Basin, and City riparian buffers, measured from the tops of the stream banks, are shown on the plan. Page 1 of 6 AH The 10 -foot no build setback, measured from all riparian buffers, is shown on the plan. AH Diffuse flow is achieved into riparian buffers. AH (Check One) f � Yes F No Regulated floodplain located on site. AH A legible copy of the effective Federal Emergency Management Agency National Flood Insurance Program Flood Insurance Rate Map is provided. Map number, map date, and site boundary are clearly shown and labeled. [This map is required regardless of whether floodplain is located on the site.] The effective and /or future FEMA 100 -year floodplain, with base flood elevations (if applicable), are shown on the plan. AH All applicable notes, per the Standard Notes section of the Reference Guide for Development, have been added to the plan. AH Stormwater Impact Analysis (SIA) sealed and signed by a registered North Carolina Professional Engineer (NCPE) is provided, including narrative report and drainage calculations. Note: If a site is exempt from stormwater requirements then a narrative advising of the exemption can be submitted by any designer. Initials AH An introductory narrative describing pre- and post - development site conditions and site improvement changes, is provided. Note: The baseline conditions for the 1 -year event varies based upon the regulatory basin in which the project is located. AH Drainage area maps (one map for pre- development and one map for post - development) are provided with the following items: X Scale and north arrow (Note: Except in the instance of site -to- drainage area maps, the scale of each drainage area map shall not exceed 1" = 30'). X Sub -basin area(s) delineated with area(s) in acres indicated. X Analysis points clearly identified and labeled. X Segmented TR -55 time of concentration flow paths showing and labeling each segment. AH Methodologies and procedures are fully described. AH A site plan with contour lines or grading plan identifying pre- and post - development drainage patterns is provided. AH Pre- and post - development times of concentration, calculated by TR -55 segmented approach, are provided. AH Calculations for the pre- and post - development peak discharge rates are provided for the 1 -, 2 -, 10 -, and 100 -year, 24 -hour storm using TR -55, TR -20, HEC -HMS, HEC -1 or Rational Method as applicable. Note: The Rational Method is not accepted for the 1 -year analysis, areas that drain more than 50 acres, or watersheds that are not homogeneous. Page 2 of 6 AH A Summary of Results is provided in the following format: Site Analvsis Point # Site Condition Storm Event (cfs) 1 -year (cfs) 2 -year (cfs) 10 -year (cfs) 100 -year (cfs) -year (cfs) Pre - Development Post - Development without Detention Post - Development with Detention AH Conclusions providing detailed findings are provided. AH Stormwater control measure(s) (SCM[s]) are provided (indicate number of each type of SCM): Level Spreader w/ Vegetative Filter Strip 3 Stormwater Wetland Wet Detention Basin Sand Filter Bioretention Grassed Swale Restored Riparian Buffer Dry Extended Detention Basin Permeable Pavement Green Roof Disconnected Impervious Surface Rainwater Harvesting System Proprietary Systems or Other Not required (provide explanation): AH The SCM(s) indicated above are required to control the following peak discharge rates: 1 -year 2 -year 10 -year X 100 -year Other AH A downstream analysis in accordance with the Reference Guide for Development is provided with findings, or is Not required (provide explanation): Initials N/A The project is exempt based upon cumulative land disturbance as of the applicable baseline date. AH The proposed project is >_ 16% impervious (Falls and Jordan Basins) / >_ 24% impervious (Lower Neuse Basin), 85% Total Suspended Solids (TSS) removal is provided for this project, and all the impervious area as reasonably practical is treated by an SCM. OR The proposed project is X <16% impervious (Falls and Jordan Basins) / <24% impervious (Lower Neuse Basin), 85% Total Suspended Solids (TSS) removal for all runoff from non - vegetated conveyances is provided for this project, and all the impervious area as reasonably practical is treated by an SCM. N/A The project is low density without non - vegetated conveyances, thus TSS removal is not required. Page 3 of 6 N/A SCMs for TSS removal are provided (indicate number of each type of SCM): Note: Not all of the SCMs listed below provide 85% TSS removal as a stand -alone SCM and must be used in series with other SCMs to achieve the minimum TSS removal of 85 %. Level Spreader w/ Vegetative Filter Strip Stormwater Wetland Wet Detention Basin Sand Filter Bioretention Grassed Swale Restored Riparian Buffer Dry Extended Detention Basin Permeable Pavement Green Roof Disconnected Impervious Surface Rainwater Harvesting System Proprietary Systems or Other Not required (provide explanation): AH Both hard copies, and Excel- format electronic copies on a DVD or compact disc, of the following: • Pre- and post - development nutrient calculations using the Jordan /Falls Lake Stormwater Nutrient Load Accounting Tool found at : http: / /portal.ncdenr.orq/ web /iordanlake /implementation - auidance- archive or http: / /durhamnc.gov /ich /op /pwd /storm /Pages /SWDevReview.aspx Note: Nutrient calculations are always required regardless if the project is exempt from treatment requirements. • The Nutrient Reporting Form (including the Compliance Worksheet tab) per the 3/7/2013 Letter to Industry http: / /durhamnc.gov /ich /op /pwd/ storm /Pages /LTI- SWDevReview.asiDx AH Pre- and post - development land use area maps that correspond to the categories used in the Jordan /Falls Lake Stormwater Nutrient Load Accounting Tool for the nutrient calculations, to scale no smaller than 1 inch = 100 feet. The maps shall show the map scale, north arrow, and are to have the different land uses either hatched or shaded with areas indicated in a legend on the maps. Note: The land use area maps are always required regardless if the project is exempt from treatment requirements. Page 4 of 6 AH SCMs for nutrient control are provided (indicate number of each type of SCM): Level Spreader w/ Vegetative Filter Strip 3 Stormwater Wetland Wet Detention Basin Sand Filter Bioretention Grassed Swale Restored Riparian Buffer Dry Extended Detention Basin Permeable Pavement Green Roof Disconnected Impervious Surface Rainwater Harvesting System Proprietary Systems or Other Not required (provide explanation): N/A After meeting the minimum on -site treatment requirements, additional treatment and /or offsite credit purchases, if needed, is provided by: Additional SCMs Nutrient Offset Payment to the North Carolina Ecosystem Enhancement Program Nutrient Offset Payment to an Approved Nutrient Bank Land Bank Credit Transfer (Commitments shall be made prior to October 1, 2015) N/A The project site is located in an area subject to a state - approved Total Maximum Daily Load (TMDL) for bacteria. (As of April 2014, only Northeast Creek has a TMDL for bacteria). N/A SCMs rated as medium or high for bacterial removal are provided (indicate number of each type of SCM): Bioretention Area Stormwater Wetlands Wet Detention Basin Sand Filter Level Spreader w/ Vegetative Filter Strip Restored Riparian Buffer Dry Extended Detention Basin Permeable Pavement Other (specify) Not required (provide explanation): Page 5 of 6 Initials N/A 85% Total Suspended Solids (TSS) removal is required for this project, and 100% of the impervious area will be treated by an SCM. Note: Not all of the SCMs listed below provide 85% TSS removal as a stand -alone SCM and must be used in series with other SCMs to achieve the minimum TSS removal of 85 %. N/A SCM for TSS removal are provided (indicate number of each type of SCM): ,Level Spreader w/ Vegetative Filter Strip Stormwater Wetland Wet Detention Basin Sand Filter Bioretention Grassed Swale .Restored Riparian Buffer Dry Extended Detention Basin Permeable Pavement Rooftop Runoff Management Disconnected Impervious Surface Rainwater Harvesting System Proprietary Systems or Other Not required (provide explanation): Page 6 of 6