HomeMy WebLinkAboutSWA000206_Supplement-EZ Form_20230524SUPPLEMENT-EZ COVER PAGE
FORMS LOADED
PROJECT INFORMATION _
1 Project Name Villages At Waxhaw
2
Project Area ac
7.44
3
_
Coastal Wetland Area ac
_
0
4
Surface Water Area ac
0
5
Is this project High or Low Density?
High
6
1 Does this project use an off -site SCM?
No
COMPLIANCE WITH 021-1.1003(4) .
7 Width of vegetated setbacks provided feet N/A
8 Will the vegetated setback remain vegetated? N/A
9 If BUA is proposed in the setback, does it meet NCAC 02H.1003 4 c-d)? N/A
10 Is streambank stabilization proposed on this project? No
NUMBER AND TYPE OF SCMs;
11 Infiltration System
12
Bioretention Cell
13
Wet Pond
1
14
Stormwater Wetland
15
Permeable Pavement
16
Sand Filter
17
Rainwater Harvesting RWH
18
Green Roof
19
Level Spreader -Filter Strip LS-FS
20
Disconnected Impervious Surface DIS
21
Treatment Swale
22
Dry Pond
23
StormFilter
24
Silva Cell
25
Bayfilter
26 1
Filterra
FORMS LOADED
DESIGNER CERTIFICATION
27 Name and Title: Weston Boles, Senior Consultant
28
Organization:
W.K. Dickson
29
Street address:
1213 W. Morehead St. Suite 300
30
City, State, Zip:
Charlotte, NC 28208
31
Phone numbers :
704-305-2331
32
Email:
wboles@wkdickson.com
Certification Statement:
certify, under penalty of law that this Supplement-EZ form and all supporting information were prepared under my direction or supervision; that the
information provided in the form is, to the best of my knowledge and belief, true, accurate, and complete; and that the engineering plans,
specifications, operation and maintenance agreements and other supporting information are consistent with the information provided here.
CARO
_=�:•� SFAS � : =
0- 037833 _
:.0
0N' G\\Q, \\\�
Signature of Designer
z3
Date
Seal
DRAINAGE AREAS
1
Is this a high density project?
Yes
2
If so, number of drainage areas/SCMs
1
3
Does this project have low density areas?
No
4
If so, number of low density drainage areas
0
5
Is all/part of this project subject to previous rule
versions?
No
FORMS LOADED
DRAINAGE AREA INFORMATION
Entire Site
1
Wet Ponds
4
Type of SCM
5
Total drainage area (sq ft
208226.00
208226.00
6
Onsite drainage area (sq ft
204830.00
204830
7
Offsite drainage area (sq ft
3396.00
3396
8
Total BUA in project (sq ft
110451.00
110451 sf
9
New BUA on subdivided lots (subject to
ermitting) (sq ft
sf
sf
10permitting)
New BUA not on subdivided lots (subject to
sf
110451 sf
110451 sf
11
offsite BUA sq ft
sf
sf
12
Breakdown of new BUA not on subdivided lots:
- Parking (sq ft
sf
sf
- Sidewalk sq ft
15335 sf
15335 sf
- Roof (sq ft
52762 sf
52762 sf
- Roadway s ft
42310 sf
42310 sf
- Future (sq ft
sf
sf
- Other, please specify in the comment box
below (sq ft
44 sf
44 sf
13
New infiltrating permeable pavement on
subdivided lots (sq ft
sf
sf
14
New infiltrating permeable pavement not on
subdivided lots (sq ft
sf
sf
15permitting)
Existing BUA that will remain (not subject to
s ft
sf
sf
16
Existing BUA that is already permitted (sq ft
sf
sf
17
Existing BUA that will be removed (sq ft
sf
18
Percent BUA
53%
53%
19
Design storm inches
1.0 in
1.0 in
20
Design volume of SCM cu ft
11930 sf
11930 cf
21
Calculation method for design volume
Simple Method
Simple Method
ADDITIONAL INFORMATION
22
Please use this space to provide any additional information about the
drainage area(s):
WET POND
1
Drainage area number 1
1 __—IY
2 Minimu_m required treatment volume cu ft
GENERAL MDC FROM 02H .1050
3 Is the SCM sized to treat the SW from all surfaces at build -out?
cf
Yes
4
Is the SCM located away from contaminated soils?
Yes
5
What are the side slopes of the SCM H:V ?
2:1
6
Does the SCM have retaining walls, gabion walls or other engineered
side slopes?
Yes
7
Are the inlets, outlets, and receiving stream protected from erosion
10- ear storm)?
Yes
8
Is there an overflow or bypass for inflow volume in excess of the
design volume?
Yes
9
What is the method for dewatering the SCM for maintenance?
Pump preferred
10
If applicable, will the SCM be cleaned out after construction?
Yes
11
Does the maintenance access comply with General MDC (8)?
Yes
12
Does the drainage easement comply with General MDC 9 ?
Yes
13
If the SCM is on a single family lot, does (will?) the plat comply with
General MDC 10 ?
N/A
14
Is there an O&M Agreement that complies with General MDC (11)?
Yes
15
Is there an O&M Plan that complies with General MDC (12)?
Yes
161
Does the SCM follow the devicespecific MDC?
Yes
17
Was the SCM designed by an NC licensedprofessional?
Yes
WET POND
MDC FROM 02H .1053
18
Sizing method used
SA/DA
19
Has a stage/storage table been provided in the calculations?
Yes
20
Elevation of the excavated main pool depth (bottom of sediment
removal) (fmsl
613.00
21
Elevation of the main pool bottom (top of sediment removal) (fmsl
614.00
22
Elevation of the bottom of the vegetated shelf fmsl
618.50
23
Elevation of the permanent pool fmsl
619.00
24
Elevation of the top of the vegetated shelf fmsl
619.50
25
Elevation of the temporary pool fmsl
620.26
26
Surface area of the main permanent pool square feet
6742
27
Volume of the main permanent pool cubic feet
23125 cf
28
Average depth of the main pool feet
3.13 ft
29
Average depth euation used
Equation 2
301
If using equation 3, main pool perimeter feet
N/A
31
If using equation 3, width of submerged veg. shelf feet
N/A
32
Volume of the forebay cubic feet
2237 cf
33
Is this 15-20% of the volume in the main pool?
Yes
34
Clean -out depth for forebainches
61n
35
Design volume of SCM cu ft
11930 cf
36
Is the outlet an orifice or a weir?
Orifice
37
If orifice, orifice diameter inches
1 in
381
If weir, weir height inches
na
If weir, weir length inches
na
Drawdown time for the tem ora ool da s
5
Are the inlet(s) and outlet located in a manner that avoids short-
arcuitin ?
Yes
r
Are berms or baffles rovided to im rove the flow ath?
Yes
Depth of forebay at entrance (inches
66 in
De th of forebay at exit inches
60 in
Does water flow out of the foreba in a non -erosive manner?
Yes
Width of the vegetated shelf feet
6 ft
Slope of vegetated shelf H:V
6:1
Does the orifice drawdown from below the top surface of the
ermanent 001?
Yes
r5048
Does the pond minimize impacts to the receiving channel from the 1-
r, 24-hr storm?
Yes
Are fountains proposed? (If Y, please provide documentation that
MDC 9 is met.
No
51
Is a trash rack or other device provided to protect the outlet system?
Yes
52
Are the dam and embankment planted in non -clumping turf grass?
Yes
53
Species of turf that will be used on the dam and embankment
Native Grasses
54 Has a planting plan been provided for the vegetated shelf?
ADDITIONAL INFORMATION
No
55
Please use this space to provide any additional information about the
wet pond(s):