HomeMy WebLinkAboutSite inspection MayWetland Inspection Report
Proiect Num: 20201820 Version: 1 Status: Issued
Proiect Name: TPB NCDOT - Julian Road Widening (U-5738) Proiect Type: Road/Highway Widening
County: Rowan Region: Winston-Salem
Location: TPB NCDOT -Julian Road Widening (U-5738)
Latitude• +350 38' 32" Longitude: -80° 29' 38"
SW Plan Location:
Site Owner Name: NC DOT Division 9
Inspection Date: 5/19/2023
Reason for Inspection: Routine
Inspection Type: Site Inspection (DOT)
Inspection Contact Person: Title: Phone:
On -Site Representative(s):
Primary Inspector: Dave Wanucha Phone: 336-776-9703
Secondary Inspector(s):
Facility Compliance Status: 0 Compliant ❑ Not Compliant
Program Areas: 401 (includes isolated/non-404)
Question Areas:
Permit (401 WQC)
Inspection Summary:
page 1
Site Number: 20201820 Owner: Tippett, Lvndo
Inspection Date: 5/19/2023 Inspection Type: Site Inspection (DOT) Reason for Visit: Routine
Permit (401 WOO Yes No NA NE
Does the impact(s) match what was approved in the 401 WQC or non 404 permit? 0 ❑ ❑ ❑
Are the culverts and/or filled areas installed properly? 0 ❑ ❑ ❑
Is the site compliant with additional conditions of the 401 WQC or non 404 permit? 0 ❑ ❑ ❑
Comment: I met with Div 9 staff and contractors to review status of proiect. The culvert extension was complete
at the inlet side but needed some repairs along the invert of the high flow barrel. Staff would install
riprap to plug the hole that developed along the flood plain bench at the invert. Outlet extension was not
started. At the bridge, temporary impacts were assoc with sediment basin. Bridge was currently under
construction with no issues to report.