Loading...
HomeMy WebLinkAbout20160742 Ver 6_Monitoring Report_20230502Cedar Cliff Hydroelectric Development Auxiliary Spillway Upgrade Project - Spillway Excavation, Summary of Water Quality Monitoring Results. Prepared for: Duke Energy Carolinas, LLC Prepared by: Jon C. Knight, Ph.D. and Josh R. Quinn May 2023 Introduction In 2014, the Federal Energy Regulatory Commission (FERC) established the Inflow Design Flood (IDF) for Duke Energy Carolinas, LLC's (Duke Energy) Cedar Cliff Hydroelectric Development (Cedar Cliff Development) as the Probable Maximum Flood (PMF). Prior to the FERC notice, the OF had been 40% of the PMF. The existing spillway discharge capacity is insufficient to pass the PMF without overtopping the dam, resulting in the potential failure of the structure. Engineering design and analyses have indicated that expanding the auxiliary spillway channel (width and depth), installing Hydroplus Fusegates as the spillway control mechanism, and replacing the existing parapet wall with a taller PMF wall (additional storage) will provide the necessary physical site measures to safely pass the OF without overtopping Cedar Cliff Dam. As discussed by HDR (2018a), pyrite (FeS2) was identified in rock exposures at the site and in the rock core from boreholes drilled for the subsurface investigation (HDR 2017). Based on the boreholes drilled during the geological/geotechnical site investigation, it was estimated that approximately 26% of the total excavated material (73,600 cubic yards) will be comprised of rock lithologies containing 2% to 7% pyrite by volume (HDR 2017). Even though there are no known instances of acid -drainage related to the to the site lithologies, rocks with greater than 1 % pyrite and/or pyrrhotite by volume are considered to be potentially acid -producing. Even though HDR (2017, 2018a, 2018b) has discussed the project in detail and has projected minimal, if any, acidification impacts from pyrite oxidation. Duke Energy submitted a water quality monitoring plan to the North Carolina Department of Environmental Quality (NCDEQ), Division of Water Quality, on May 19, 2019. Subsequently, NCDEQ issued Section 401 Water Quality Certifications (#WQC004077), and the permit (SAW-2015-02543) issued by the USACE dated June 21, 2019 required Duke Energy to adhere to the water quality monitoring plan. The summary of the water quality data collected during the 26-month baseline period' (July 2018— September 2020) was reported by Knight and Quinn, (2021) and was submitted to NCDEQ as the first annual (baseline) report. Water Quality sampling resumed in March 2021, just prior to rock excavation, and continued through March 2023 while the rock was excavated and spoiled into the lake.2 The required 2021 and 2022 annual reports were not submitted due to medical issues with the primary author. In 2023, Duke Energy submitted a modification request to the approved Clean Water Act (CWA) Section 404 (Action ID 20215-02542) and Section 401 Individual Permit (DWR # 20160742 Ver 4) for design changes related to the Cedar Cliff Auxiliary Spillway Upgrade Project. Since the NC Division of Water Resources and the USACE will review the request, this summary report of the water quality monitoring at Cedar Cliff will highlight the principal findings of the monitoring program for agency review. A complete detailed report comparing the baseline data to the entire period of rock excavation is planned after excavation is complete (expected mid-2023). The Duke Energy monitoring plan was designed to evaluate the extent and influence of pyrite oxidation on the pH in the waters of Cedar Cliff reservoir and the East Fork of the Tuckasegee River down stream of Cedar Cliff Hydro. Pyrite can react in the presence of oxygen and water to form ferrous sulfate and sulfuric acid (2FeS2 + 702 + 2H2O --+ 2FeSO4 + 2H2SO4). Further oxidation of ferrous iron would produce ferric hydroxides and/or ferric carbonates. The stoichiometry of complete oxidation of one mole of pyrite would produce two equivalents of hydrogen ions. Most natural freshwaters are buffered by the bicarbonate -carbonate system, the following equation is applicable: ' When referenced in this report, the 'baseline' period refers to the time period of July 2018 through September 2020. 2 The final rock placement in the lake was on April 14, 2023. Where: 1 _ [H+] [HCO3 1] K1 _[CO2] Ki' = First equilibrium constant as a function of temperature H" = Hydrogen ion concentration (moles/L) (10-p") HCO3-' = Bicarbonate concentration (moles/L) CO2 = Carbon Dioxide concentration (moles/L) Bicarbonate concentrations usually result from the weathering and subsequent dissolution of parent rock material within the watershed. The pH is a function of the ratio of carbon dioxide to bicarbonate concentrations, the relative rates of biological respiration or photosynthetic rates determine the carbon dioxide concentrations. Other minor acid -base reactions may occur as water percolates through the soil or rock formations. Chemical precipitation and/or chemical adsorption onto clays also influence pH. Therefore, the purpose of the monitoring plan is to identify the various processes controlling the pH in the project waters, in particular pyrite oxidation influencing pH. Site Description and Phase II Construction Activities Since July 2018, activities at the Cedar Cliff Development have centered on the routine maintenance and repair of the hydro station, installation of the new hydro station transformer, principal spillway gate maintenance and installation of the new gate hoist and gate hoist building, and the implementation of the Phase I auxiliary spillway upgrade construction. Phase I construction began in late -December 2019 and involved site preparation, road improvements, installation of the Sediment Basin Dam at the upstream end of the bypassed reach channel, installation and maintenance of erosion sediment control measures, tree clearing, and construction tasks involving the installation of the Soldier Pile Wall above the auxiliary spillway channel and placement of vertical rock anchors in the left abutment of the Cedar Cliff Dam (Figure 1). Knight and Quinn (2021) describe in detail the Phase I construction activity of the Auxiliary Spill Channel Upgrade project. In the first quarter of 2021, Phase I activities were completed and the commencement of Phase II spillway excavation began. Auxiliary spillway excavation and spoiling of rock was originally planned to span less than 12 months. Initially, a test blast program involved small excavations of the auxiliary spillway rock wall as well as trials to spoil the excavated material into Cedar Cliff Reservoir. The preliminary barging and subsequent dumping of excavated material in the reservoir revealed increased turbidity in the East Fork turbine flow. In an attempt to maintain turbidity levels below the NC state turbidity standard of 10 NTU for trout waters, barging rates, spoil placement, and hydro operations were varied and compared to the observed tailrace and reservoir turbidity levels. These trials led to the use of a tracked mobile screen to minimize the fine material deposited in the reservoir. It was used to separate the excavated material into rocks larger than 6 inches, material less than 6 inches but greater than 1'/2 inches, and material less than 1'/2 inches. After blasting the rock from the auxiliary spillway `wall', large rocks were reduced to manageable size, put into the mobile screen, and separated into the 3 size fractions. Sizes greater than 1'/2 inches were loaded into barges and spoiled in Cedar Cliff reservoir. Material less than 1'/2 inches was temporally stored in the auxiliary spill channel until loaded into trucks and removed from the site to an authorized spoil site. As a routine, the area of rock excavation and temporary rock storage was sprayed with water to control dust. Figure 1. Cedar Cliff Development Site Features and Water Quality Sampling Locations Additional plans to reduce turbidity levels downstream of Cedar Cliff hydro, approved by NCDWR and the USACE, included: • An underwater weir constructed at the downstream end of the 8.5-acre rock spoil footprint. The weir and spoil repository footprint was located further upstream in the reservoir than the originally planned in 2019. This change was proposed to help reduce turbidity levels in the downstream tailrace. • The weir and turbidity curtains assisted in mitigating sediment and turbidity levels downstream of the spoil repository footprint. • The design of the 1951 Access Road was revised to reduce the volume of material excavated as well as placement of the rip rap (rock) material on shore while the lake was drawn down. These plans eliminated the need to drop the material through the water column, also reducing turbidity. The permitted rock spoil area was divided into grids. Each barge was equipped with GPS and depth transducers to accurately place the spoiled rock in the reservoir; ultimately creating the submerged weir with an elevation of 2250 ft-msl. Beginning In 2021, rock was spoiled at the most downstream portion of weir, slowly building the slopes of the weir from the channel depth of 2210 ft-msl to the top of the weir at 2250 ft-msl (Figure 2). 4 c 1Pm zan rr -,o .,. pb Pare se TYIetl INtl, Cedar Cliff Iiii etry Lake toUM 10-Foot Luke are kmemne.ani Figure 2. Cedar Cliff Reservoir Features and Water Quality Sampling Locations —Rock Placed in the Lake —Truck Loads of Fines Deposited Off -Site —Truck Loads of Mixed Size Placed On -Site 180000 160000 u 120000 to VI a 100000 m O m 00000 at m � 6000D a, m 40000 u LI W 20000 Lake Placement Trials Began 14 Mav 2021 Production Placement Began 21 June 2021 Production Placement Ended 14 April 2023 Q I I I M J J A 5 0 0 N D J F M A M J J A 5 0 N D J 2020 2021 F M A 2023 Figure 3. Record of Excavated Material (Rock Spoil into the Lake and Fine Material Removed from the Site, May 14, 2021 — Mar 31, 2023). With the exception of a few trial barge dumps during the "experimental period", active spoiling of the excavated rock began on May 14t", 2021. Trucking the fines off -site began about a week later. The average daily barging rate was 263 cubic yards per day (yd3 /day), but ranged from 0 to 972 yd3/day. Trucking rates were equally variable with an average of 199 yd3/day, and ranged from 0 to 885 yd3/day. Both material disposal rates were a function of rainfall, crew availability and excavation rates. Barging rates were also impacted by hydro operations. 5 Water Quality Sites and Sampling Methodology The water quality sampling sites, or Environmental Monitoring Points (EMPs) were the same as described in the baseline report. (Knight and Quinn, 2021). Those sites (Figures 1 and 2) were chosen to represent the various hydrology, construction activities, and excavated material storage or spoiling areas. A summary of those monitoring sites is presented in Table 1. Table 1. Water Quality Monitoring Sites for the Cedar Cliff Auxiliary Spillway Upgrade Auxiliary Spillway Upgrade Project Monitoring Sites Description Symbol Latitude (°) Longitude (°) water Sample SamplingartofDeploymentLogger Cedar Cliff Lake - Forebay EMP 4 35.25486 -83.09882 16-Jul-18 N/A Hydrolab Van Dorn Cedar Cliff Lake - Upstream of Construction EMP 7 35.25030 -83.09201 16-Jul-18 N/A Hydrolab Van Dorn Aupliary Spillway Sampling Site Conductivity Hydrolab (flows into Upper Sediment Basin) EMP 3 35.25233 -83.09914 28-Aug-18 Water Level Grab Sample Single Stage Upper Sediment Basin Sampling Site Conductivity Hydrolab (flows into upper Bypassed Reach) EMP 5 35.25250 -83.09931 28-Apr-20 Water Level Grab Sample Single Stage Conductivity Hydrolab Upper Bypassed Reach Sampling Site EMP 6 35.25212 -83.09951 14-Jul-20 Water Level Grab Sample Single Stage Conductivity Hydrolab Lower Bypassed Reach Sampling Site EMP 2 35.25295 -83.10299 28-Aug-18 Water Level Grab Sample Single Stage Minimum Flow Unit Discharge EMP 1 35.25344 -83.10274 28-Aug-18 Conductivity' Hydrolab Grab Sample Modified Rain Gage Rain 35.25344 -83.10274 24-Mar-21 N/A Hydrolab Grab Sample East Fork Upstream of West Fork Confluence EMP 8 35.26893 -83.11633 28-Aug-18 N/A Hydrolab Grab Sample Conductivity Logger Placed at Minimum Flow Gage Field Instrument Calibration Prior to each sampling, the Hydrolab data sonde was laboratory calibrated with various standards (Table 2). If the instrument did not calibrate within the manufacturer's stated accuracy, the sensing electrodes were cleaned and/or complete maintenance was performed as recommended by the manufacturer. If any sensor failed to calibrate again, the instrument was returned to the manufacturer for repair or sensor replacement. After sampling, each Hydrolab sensor was checked using the same standards. Table 2. Hydrolab DS5 Data Sonde Specifications and Calibration Methodology4 Parameter Units Method Calibration Method Manufacturer's S ecified Accurac Depth m Pressure In -field immersion ±0.05 m Temperature °C Thermistor Checked with NIST ± 0.10 °C tracable thermometer Dissolved Oxygen mg/L Luminescence Barometric pressure of ± 0.01 mg/L air saturated water Specific Conductance psi Electrical bridge Calibrate to 75 pSi ± 1% of reading checked with 25 psi Calibrate to 100 NTU Turbidity NTU Nephelometric checked with 10 NTU ± 5% of reading ORP my Platinum Calibrate with Zorbell's Solution ± 20 my electrochemical corrected for temperature pH glass Calibrate to 7.00 pH pH units electrochemical ± 0.2 units Calibrate to 4.00 pH Reference electrode n/a Saturated KCI Shared with ORP and pH (see Appendix B, Baseline Report) 3 The instrument was allowed to achieve thermal equilibrium in the lab prior to calibration. 4 Hach Company 2005. Chemical Analysis of Water Samples Upon collection of a water sample, it was either poured into a pre -labeled bottle with the appropriate preservative or field -filtered through a 0.45 pm membrane filter and then added to the sample bottle. All of the sample bottles were stored on ice until delivery to the laboratory. All sample analyses (Table 3) were performed within the recommended holding times. Table 3. Monthly Laboratory Analysis of Cedar Cliff Auxiliary Spillway Upgrade Water Samples Ionic Chemical Type of Bottle Type Summary of Analytical Parameter Category Symbol Sample Preservative Analysis Method Alkalinity i 2 HCO3- CO3- Whole water PET Titration (0.025N HCl), SM 23206 Ice Fixed end -point Alkalinity HCO3' CO3.2 Whole water PET Titration 0. 01036 N HCISM 23206 Ice Complete Titration Cn .0 Choride Cr' Whole water PCe Ion chromatography EPA 300.0 Q Sulfate SO,- Whole water PCe Ion chromatography EPA 300.0 Nitrate NO,-' Field filtered Colorimetric EPA 353.2 SuIHDPE ric Calcium Whole water HDPE ICP Ca" EPA 200.7 Dissloved Ca Field filtered Nitric Acid total recoverable Magnesium Whole water HDPE ICP M g 2 EPA 200.7 Dissloved Mg Field filtered Nitric Acid total recoverable Sodium Whole water HDPE ICP Na EPA 200.7 Dissloved Na Field filtered Nitric Acid total recoverable Potassium Whole water HDPE ICP N K j EPA 200.7 Dissloved K Field filtered o Nitric Acid total recoverable U Aluminum Whole water HDPE ICP AI 3 EPA 200.7 Dissloved AI Field filtered Nitric Acid total recoverable Manganese Whole water HDPE ICP -mass spec Mn" EPA 200.7 Dissloved Mn Field filtered Nitric Acid total recoverable Iron 3 Whole water HDPE ICP -mass spec Fe Nitric Acid total recoverable EPA 200.8 Dissolved Iron Field filtered Reduced Iron Fe+2 Whole water 60 ml BOD Colorimetric SM 3500 Fe B water sealed Note: PET = Polyethylene terephthalate; HDPE = High -density polyethylene; BOD = Biological Oxygen Demand; ICP = Inductively Coupled Plasma; EPA = U.S. Environmental Protection Agency; SM = Standard Methods. Colored cells represent samples added in 2021 compared to the baseline period. In the 2020 Baseline Report, rain chemistry was estimated from the literature and rainwater was assumed to contribute to lower pH values and to the dissolution of local substrates. Beginning in 2022, rainwater was collected in a modified rain gage between sampling dates. Since the modified rain gage only held 1.25 liters, not all samples had enough water volume to analyze all parameters. The priority of analytes for the rainwater samples were alkalinity, Hydrolab parameters, anions, and cations. As suggested in the Baseline Report, commencing in 2021 additional parameters or procedures were performed to address the chemical imbalance of the cation -anion totals. First, was the additional analysis of alkalinity utilizing the measurement of a titration curve with an acid of = 20% lower concentration than during the baseline period (see Table 3). Beginning in 2021, alkalinity was calculated from the inflection point of the titration curve, rather than a fixed end point. In 2022, an acidity titration (APHA, 1998, SM-4500-CO2 C) was performed on each sample to measure the amount of base (NaOH) required to neutralize the sample as well as the measurement Of CO2, to a pH of 8.3 standard units. Second, again beginning in 2021, the routine cation measurements in the baseline period were performed on whole water samples, yielding a total elemental concentration. The calculation of the anion -cation balance assumed the parameters were dissolved. Since the baseline period, the cation samples were filtered yielding a more direct measurement of dissolved cations (see Table 3). Reservoir Sediment Characterization Reservoir sediments either receive material settling from the water column or may diffuse compounds into the water column, with the latter occurring especially under chemically reduced (low ORP) conditions. In addition to the sampling protocol presented in the original monitoring plan, reservoir sediments were collected in the Cedar Cliff Reservoir forebay (EMP 4) to further characterize pyrite dynamics, if present. Sediment pyrite could have been present from the original construction of the Cedar Cliff Development in 1951-1952; pyrite may have formed in the water column or sediments if sufficient chemical reduction of iron and sulfur (sulfate--).sulfite--+sulfide) had occurred, enabling FeS to form and precipitate, or the spoiling of material excavated from the auxiliary spill channel. A sediment sample was collected in either October or late -September of each year with a ponar grab sampler. Particle size analysis was performed on a portion of the sample. Another portion was dried at 100°C, and then ashed at 5000C to remove organic carbon. Both dried samples were analyzed using a scanning electron microscope (SEM) with a backscatter (BSe) detector and energy dispersive spectrometer (EDS) to determine their elemental composition. The SEM analysis on all sediment samples revealed trace amounts of iron and no sulfur, indicating no pyrite (or extremely small amounts) present in the lake sediments. The sediment samples were composed of extremely fine grained material with 16.8% organic content. This material overlaid the original bottom, which existed when the reservoir was built. The particle size distribution indicates that over time, clays and organic material were transported into the reservoir and, along with organic material produced in the reservoir (e.g., phytoplankton), settled to the bottom. Also, the amount of organic material in the sediment would provide the necessary substrate for both aerobic and anaerobic respiration. Consumption of these organics would no doubt contribute to the formation of reduced compounds and the subsequent diffusion of those products into the overlaying water. SEM spectra analysis showed the bulk of the material to be alumina -silicate minerals, such as kaolinite clay enriched with feldspar and mica. A few very small titanium -enriched particles were scattered throughout, and even fewer iron -enriched particles were observed. Very little sulfur was present and no particles consistent with iron pyrite were identified. Most soils of the world contain kaolinite in the clay size fraction (< pm). In highly weathered soils, such as those of Southeastern U.S., kaolinite is usually the dominant clay mineral because of its relative resistance to chemical weathering. Kaolinite has a large cation -exchange capacity (adsorption) (Millar et al.1966). When formed in well -weathered soils and transported into water, the hydrogen ions adsorbed unto the kaolinite may be exchanged with other cations, especially multi- valent cations such as iron. Approximately 25% of the particles were less than 1.5 pm, suggesting a very high cation exchange capacity of the sediments. The lack of sulfur in the sediments suggests that pyrite was not formed in the chemically reduced environment. As mentioned previously, sulfide formation was not favored since the oxidation- reduction potential did not favor sulfate reduction. The trace amount of sulfur observed in the dried sample was likely associated with the organic fraction in the sediment since no sulfur was observed in the sediment sample ashed at 500°C, which eliminated the organics. Also noteworthy, was the lack of phosphorus in the sediments and the presence of carbon in the ashed sample. These spectra indicate that the primary compounds associated with iron were bicarbonates, hydroxides, or oxides, rather than phosphates or sulfides. Hvdroloaical Data Duke Energy Regulated Renewables Operations Center (RROC) provided the following operations data from the 2018-2023 Plant Information (PI) database: Recorded at 15-minute intervals: • Cedar Cliff Unit 1, Primary Generation (MW) • Cedar Cliff Unit 1 Flow (cfs) • Cedar Cliff Unit 2, Minimum Flow Generation, (MW or KW) • Cedar Cliff Unit 2 Flow (cfs) • Cedar Cliff Reservoir Level (ft) • Cedar Cliff Tainter Gate Position (ft)5 • Cedar Cliff Primary Spillway Flow (cfs)6 Recorded at 1-hour intervals: • Bear Creek Reservoir Level (ft) • Bear Creek Unit Generation (MW) • Bear Creek Unit Flow (cfs) • Bear Creek Tainter Gate Flow (cfs) • Cedar Cliff rainfall? 5 During normal operations, the lake levels were managed to achieve target lake levels of 95-96 ft local datum, the lake level is greater than the 75 foot level, as the tainter gate opens, water flows under the tainter gate. Based on the gate opening and lake elevation, the original engineering calculations provided the flow into the principal spill channel. The water released (cfs) into the principal spill channel was calculated and recorded in the RROC PI data base. 6 Beginning in September, 2020, the lake levels were lowered to accommodate tainter gate maintenance and to accommodate baring activities. From this date through 2023, lake levels were managed to achieve levels of 60-70 ft local datum. During this time, the tainter gate was fully open and, if lake levels rose above the tainter gate sill (75 ft ;local datum), reservoir surface water entered the principal spillway as an open flow channel over the tainter gate sill. Water height over the Tainter Gate sill was determined by subtracting 75 ft from the PI reported reservoir level. Flows were then calculated for this report from a rating curve provided by HDR, When the reservoir level was less than 75 ft DE level, no reservoir water entered the principal spillway A rain gage was installed on the Cedar Cliff Dam in January 2019. Rain gage data were recorded in the RROC PI database as inches per hour. 10 Cedar Cliff Site Hydrology The four distinct Cedar Cliff site drainages and sources of water contributing to each are: 1. Cedar Cliff Reservoir Bear Creek Reservoir (Tainter Gate and Unit Generation) Tributary, Overland Runoff, and Groundwater Direct Rainfall 2. Auxiliary Spillway Channel and Sediment Basin • Seepage and Leakage • Overland Runoff and Groundwater • Direct Rainfall • Water Sprayed for Dust Control of Excavation Site 3. Principal Spillway Channel and Bypassed Reach • Reservoir surface water via the Tainter Gate channel • Tributary, Overland Runoff, and Groundwater • Seepage from Sediment Basin, via the Auxiliary Spillway Channel • Direct Rainfall 4. East Fork • Cedar Cliff Hydro: Unit 1 (0-555 cfs) • Cedar Cliff Hydro: Unit 2 (0-35 cfs) • Minimum Flow Control Valve (0-10 cfs) • Bypassed Reach Channel (including tainter gate channel releases) • Tributary, Overland Runoff, and Groundwater • Direct Rainfall Each of the drainages has the potential to influence water quality of the reservoir and East Fork; however, the potential for water quality changes due to pryite oxidation in the various drainages is not only a function of rate of the formation of the of oxidation products, but also the volume of water the reactions occur. Mathematically, the volume -weighted concentration of the water quality parameters in all contributing flows accounts for downstream concentrations. Cedar Cliff Reservoir and East Fork of the Tuckasegee River In 2018, Cedar Cliff reservoir was managed to achieve a target lake level of 95-96 ft local datum while Bear Creek was drawndown for maintenance and construction. Prior to the auxiliary spillway construction, both Cedar Cliff and Bear Creek lake levels were managed to achieve normal seasonal target levels. However, during the auxiliary spillway construction project the reservoir level was being managed between 60 and 70 ft local datum to accommodate barging the spoiled rock. To manage these lower lake levels relied solely on the generators. When significant rainfall and/or increased releases from Bear Creek caused Cedar Cliff reservoir levels to rise above the 75 ft level, water would flow down the principal spillway as an open channel flow (Figures 4 and 5). On August 16 and 17, 2021, the Tuckasegee River received significant rainfall from Tropical Storm Fred, causing Cedar Cliff Hydro Unit 1 to trip due to water backing up into the powerhouse and flooding the unit. The Unit was returned to service September 8. During that time the East Fork only received water via the principal spillway. Also, after that forced outage, Unit 1 was de -rated to 4 MW due to lower lake levels. The de -rating was reflected in lower discharges from Unit 1 after September 8, 2021. The de -rating will continue throughout the auxiliary spillway project. 11 As expected, the volume of water in Cedar Cliff reservoir paralleled the lake level (Figure 6). The volume of water released through the hydro station varied reflecting the lake management strategy to maintain the lake level between 60 and 70 ft (local datum). Weekly average water retention times were calculated by dividing the average weekly reservoir storage by the average weekly volume of water released from the reservoir (Figure 6). The longer the time water is retained in the reservoir, the greater effect biochemical reactions have on the observed water quality in the water column. Principal Spillway Channel and Bypassed Reach Water Levels The level loggers were placed in small depressions in the channel, which enabled continuous recording of water level and were used to measure the intermittent water rise over the level logger, indicating the timing of increased flows (Figures 7 and 9). No rating curves were developed for any of the spill channel sites; primarily since the flows were so low and were very intermittent when not subjected to Principal Spillway flows. The average bypassed reach flows without spill from the reservoir were estimated to be 7-8 cfs8 in the baseline report (Knight and Quinn, 2021). Almost negligible flows entered the East Fork of the Tuckasegee River from the Bypassed Reach compared to flows recorded at the minimum flow gage, located immediately downstream of Cedar Cliff Hydro. Typically, the higher flows in the Bypassed Reach originated from the spill into the principal spillway and, to a much lesser extent, from rainfall. These higher flows, especially from the main spill channel, flushed the Bypassed Reach. As flows decreased and water receded, the pools drained slowly through the check dams providing flows into the lower Bypassed Reach. All pools were subject to significant evaporation until the next high-water event. The high water spilling into the primary spill channel through the tainter gate opening periodically destroyed the single stage samplers and the level logger located in the lower Bypassed Reach (EMP 2). If destroyed, each logger and the single stage sampler were replaced on each return sampling trip. Auxiliary Spillway Channel and Sediment Basin Water Levels The auxiliary spill channel and the sediment basin were at a higher elevation than the primary spill channel and therefore were not impacted by the highwater levels spilling from the lake. Periodic high water in the Principal Spillway and/or construction activities prevented crossing the Bypassed Reach to sample the auxiliary spillway channel and sediment basin. Rainfall, and subsequent groundwater seepage, and as excavation progressed, water sprayed on the excavated material to control dust were the major sources of water into the auxiliary spill channel (Figure 7). As designed, this water flowed into the constructed sediment basin. The rapid rise of water and subsequent rapid decline of water in both the auxiliary spill channel and the sediment basin illustrated the permeability of both channel substrates. After excavation began, rarely was surface water collected from either site; only periodic samples from the single stage samplers were available for chemical analysis, The rain -driven flow events from the auxiliary spillway channel rapidly entered the basin to a level above the USGS sampler, allowing the sampler to fill (Figure 9). The basin rapidly lost water as it filtered and drained through the sediment basin dam into the Bypassed Reach at the EMP 6 site. Only water samples retained in the single stage samplers were collected for analysis. s The Bypassed Reach flow was calculated using a flow -weighted conductivity from the bypassed reach and the East Fork 12 Cedar Cliff Reservoir ■ Sampling Dates — — —Tainter Gate Sill Level — — —Full Pond Lake Level Generation Flow Tainter Gate Spill Flo}r5, 100 90 80 L<J 70 60 a� D 50 J 40 J 30 20 10 0 3510 3DDD Z5ff[3 _-L8 c� LL lvvv 5�.. J A 5 0 N Q J F M A M J J A 5 0 N d J F M A M J J A 5 0 N d J F M A M J J A 5 0 0 N d J F M A M J J A 5 0 N d J F r.1 2018 2019 2020 2021 2022 2023 Figure 4. Cedar Cliff Lake Level and Outflows Bear Creek Reservoir Lake Level — — —Full Pond Bear CreekTotal Outflow 100 90 80 U1 TO G0 a� � 50 J aD 40 _J 30 20 10 0 3500 3000 2500 2000 1500 2 LL 1000 500 0 J A S O N Q J F M A M J J A S 0 N D J F M A M J J A 5 4 N 6 J F M A M J J A S 0 4 N D J F M A M J J A S O N C J F M 2018 2019 2020 2021 2022 2023 Figure 5. Bear Creek Lake Level and Outflow 13 100 � 90 rl 80 70 Q 60 50 40 30 J 20 10 0 Cedar Cliff Reservoir • Sampling Dates Percent Lake Volume Average WeeWy Retention Time 250 >, as MOE F- c 0 150 as 'D ioa-2 ID 50 a� as as 4 _ C rd = r_i _ r_i _ _ _ S C rJ C J F r.1 = NI J J _ C N C J F M= ra J, P 5 C C rd v J F r'+1 = r.l J J .` C rj C J F rv1 2018 2019 2020 2021 2022 2023 Figure 6. Percent of Cedar Cliff Reservoir Volume and Weekly Average Reservoir Water Retention Time 14 10 9 7 as 6 J 5 aJ 4 3 2 1 Q Cedar Cliff A Sample Dates Auxilary Spill Channel Water Level —Lower Bypass Water Level East Fork Water Level -Daily Rainfall 5.00 n c 2.00 0� 1-00 t4 0.00 1-ao -2 -00 -3 -00 -4-00 -5.00 J ` 0 N D J F N1 A M J J A S U N D J F M A het J J A S 0 N D J F M A M J J A 5 0 0 N D J F M A M J J A S C N D J F M 2018 2019 2020 2021 2022 2023 Figure 7. Rainfall Compared to Water Levels in the Auxiliary Spill Channel, Lower Bypass, and East Fork Downstream of the Hydro. Cedar Cliff Auxiliary Spill Channel CondtictIVIN' Lower Bypass Conductivity East Fork Conductivity 1000 + • • 100 * i 0 • 0 •r r • • • * • • 0 10 -. r 1 -- J A S O N D J F M A M J J A S O N D J F M A M J J A S 0 N D J F M A M J J A S 0 4 N D J F M A M J J A S 0 N D J F M 2018 2019 2020 2021 2022 2023 Figure 8. Conductivity of the Auxiliary Spill Channel, Lower Bypass, and East Fork Downstream of the Hydro (Circles Represent Conductivity Values Collected at the Time Water Samples Were Collected) 15 w J W 10 9 7 6 5 A 3 2 1 0 Cedar Cliff Auxilary Spill Channel Water Level Sediment Basin Water Level — East Fork Water Level daily Rainfall J A S 0 N❑ J F M A Art J J A S 0 N❑ J F M A M J J A S 0 N Q J F M A M J J A 5 0 0 N❑ J F M A h•1 J J A 5 0 N❑ J= PO 2018 2019 2020 2021 2022 2023 Figure 9. Rainfall Compared to Water Levels in the Auxiliary Spill Channel, Sediment Basin, and East Fork Downstream of the Hydro. 10000 -_ 10 00 v] 21 .> 100 3 CJ 10 Cedar Cliff Auxilary Spill Channel Conductivity Sediment Basin Conductivity Upper Bypass Conductivity East Fork Conductivity p OOp O D 0 0C. 1 J= S C N o J 2018 I _. MI � 141 11 . �. I F M A M J J A 5 0 N 6 J F M A Art J J A S O N❑ J F M zi. p.1 ; J A S 0 0 N❑ J F M A M J J A S 0 N D J F M 2019 2020 2021 2022 2023 Figure 10. Conductivity Measured in the Auxiliary Spill Channel, Sediment Basin, and East Fork Downstream of the Hydro (Circles Represent Conductivity Values Collected at the Time Water Samples Were Collected) 16 Conductivity of the Auxiliary Spillway Channel, Sediment Basin, Bypassed Channel, and the East Fork East Fork Tuckasegee River The conductivities (an indirect measure of dissolved solids) measured in the East Fork at the minimum flow gage were similar throughout the entire monitoring period. (Figures 8 and 10) indicating little change in the total dissolved solids, both in the lake and the East Fork. The conductivities measured in all of the Bypassed Reach channels were substantially higher than the East Fork, especially after excavation of the auxiliary spillway began. These data indicated little, if any, influence from the spill channels on the East Fork chemistry. The sporadic readings from the conductivity loggers (Figure 10) usually resulted from the conductivity loggers being on the surface and not well submerged. However, the conductivity loggers were prone to failure preventing a complete data set. The conductivity from the auxiliary spill water was substantially higher than from any other site. The higher conductivities in the auxiliary spill channel likely resulted from seepage flows through the rock and soil substrate. The dissolved solids in the auxiliary spill channel increased substantially after the fine material separated from the excavated material was temporarily stockpiled in the auxiliary spill channel. The water sprayed for dust control in the auxiliary spillway likely added to the increased conductivity. Also, as the auxiliary spillway channel flowed into the sediment basin during the rain events, the water from the sediment basin rapidly filtered through the sediment basin dam, carrying dissolved compounds with it. Periodic rain events, and especially spills from the lake through the primary spillway, temporally diluted the sediment basin dissolved solids in the Bypassed Reach. The dilution and/or precipitation of dissolved compounds continued through the bypass reach (Figure 11). Low flows and reduced dissolved solids in the bypass reach had little, if any, impact on the East Fork conductivities, as evidenced by the similarity of East Fork values to those measured from the reservoir (Figure 11). ■Baseline Period ■Excavation Period 1000 100 10 Figure 11. Median Conductivities Calculated During the Baseline and Excavation Periods, Measured at All Sampling Sites.) 17 Turbidity of the Auxiliary Spillway Channel, Sediment Basin, Bypassed Channel, and the East Fork East Fork Tuckasegee River The turbidities of the bypassed reach and East Fork rarely exceeded the state water quality standard of 10 NTU. More excursions of 10 NTU occurred prior to rock excavation (Figure 12). Higher turbidities generally resulted from higher flows associated with tainter gate releases which suspended material from the river bed. This material rapidly settled out of the water when flows subsided. Cedar Cliff ♦ Upper Bypass ♦ Lower Bypass East Fork at Hydro • East Fork above Confluence — — —State N!Q Standard 20 18 Excavation Period 16 ■ 14 • • 12 • ,a10 ————————————— ———————— ———————————— ———————————————————————— — — — —_. 8 ■ ■ -2 J A S O N❑ J F M A M J J A S O N❑ J F M A M J J A S O N❑ J F M A r.1 A 5 Q Q N❑ J F M A M J J A S Q N❑ J F M 2018 2019 2020 21i21 2022 2023 Figure 12. Turbidity Measured in the Upper and Lower Spill Channel, and both East Fork Sites Down Stream of the Hydro IN Water Quality - Cedar Cliff Reservoir In Situ Measurements Temperature Reservoir water temperatures are typically driven by meteorological conditions, primarily solar energy and wind. Advective inflows may also significantly impact water temperatures. Cedar Cliff Reservoir is located in a steep valley that is sheltered from wind by the surrounding terrain, which minimized the surface wind shear, limiting wind -induced stratification. The rate of heat exchange with the atmosphere is a function of the difference between the water temperature and the equilibrium temperature. Cedar Cliff reservoir water temperatures followed the seasonal heating and cooling pattern (Figure 13) driven by the seasonal meteorological conditions (air ter 2018 2019 2020 2021 2022 2023 Figure 13. Cedar Cliff Reservoir Water Column Temperatures, 2018 - 2023 The reservoir did not develop a classical epilimnion or hypolimnion separated by a thermocline with strong horizontal thermal gradients. Rather, weak vertical thermal gradients developed, indicating that the deep- water removal via the penstock removed the cooler bottom water as it was replaced by warmer water originating near the surface. Hence, the development of the vertical thermal gradients followed the rate of the Cedar Cliff hydro generation flows. Even though a traditional thermocline did not develop, the strongest horizontal gradients were observed at and below the penstock invert, indicating that the penstock had very limited access to the water below the penstock and reduced vertical mixing below that level. This small volume of water (26 acre-ft)9 exhibited characteristics similar to a traditional hypolimnion with vertical exchange of heat and compounds limited by diffusion and low turbulence. Dissolved Oxygen and Carbon Dioxide The water column dissolved oxygen (DO) concentrations followed the pattern established by the temperature distribution; namely, DO decreased as the water column temperatures increased (Figure 14). The most consistent pattern of DO loss was in the water below the invert of the hydro penstock. Water below this level had reduced vertical mixing and was not removed or replaced until fall cooling was sufficient to mix that water. Until that water was mixed, either 9 Calculated from the invert elevation and the storage curve presented in Figure 5, Knight and Quinn, 2020.. 19 aerobic or anaerobic respiration continued until the DO was completely depleted in that deep water. Even with periodic high retention times (Figure 6), primary production appeared to be limited since summer oxygen concentrations in the water column decreased rather than exhibiting high oxygen in the upper, euphotic zone. Below the surface of Cedar Cliff Reservoir, the DO decreased due to warmer temperatures, coupled with respiration by algae and bacteria. Like temperature, as Cedar Cliff hydro continued generation, the water was removed from the lower reservoir levels and was replaced by warmer water along with the associated lower DO concentrations. With the initiation of fall cooling and subsequent mixing, DO increased as temperatures decreased and atmospheric oxygen exchange progressed. 1 ii1f1- l l'3f1 2280 W 2270 - -y 22so - C 4 � 2259 - n a :Li 22an- 2230 - 2220 - 2210- 2209 - %1'3I1 - 2018 2019 2020 2021 2022 2023 Figure 14. Cedar Cliff Reservoir Water Column Dissolved Oxygen, 2018 - 2023 2330 _ y 2320 ' 7 10 a 2]10 0. 2300 .r ►�+1[y.11J �a 2290 2280 �db � c • Ou n, 2270 � � �•44 2250 N v[yjjY• 1!J 2240 220 h. 1:0 2220 I II 2210 2200 hC L e t �. III � 2018 2019 2020 2021 2022 Figure 15. Cedar Cliff Reservoir Water Column Carbon Dioxide, 2018 - 2023 The water column carbon dioxide values (Figure 15) throughout the entire sampling period exhibited lower values deeper in the water column during the summer/fall season. The highest CO2 values were observed in the surface waters during the spring/summer months as a result of the limited photosynthetic activity. :I 2023 C According to Hutchinson (1975), most natural freshwaters are buffered by the bicarbonate - carbonate system; whereas pH is controlled by the ratio of CO2 to bicarbonate. Since the reservoir pH values ranged from 5.69 to 8.45 units (Figure 16), there is no evidence of strong acids influenced the pH rather biological respiration (production of CO2) dominated the buffering system. Additionally, if CO2 was produced from autochthonous production, DO and CO2 concentrations would show opposite concentration trends. The timing of high CO2 generally precedes that of lower DO indicating an organic source other than algae produced in the reservoir. The timing of high CO2 generally follows higher releases of water from Bear Creek indicating the organic substrates originate from Bear Creek reservoir. Mir 233C 232c ,Y . pH 23tC • • m ill i • : i 229C � � • • • • w • • • . • 225C • • • •pi• • i i • • i .--. 227C • • • : :� � 225C • : . � � : • • F - fb - - 223C : E{ 2200: rn. ; ; • 2018 2019 2020 2021 2022 2023 Figure 16. Cedar Cliff Reservoir Water Column Carbon Dioxide, 2018 - 2023 Conductivity and Turbidity Conductivity values were generally less than 20pSi, indicating waters of very low ionic concentrations (Figure 17). However, conductivity values were significantly higher in the water below the penstock invert. The relatively high concentration of ions did not originate from the upper water, but rather from ionic diffusion from the sediments. The conductivity increase persisted until the water temperatures cooled and mixed the bottom water. 233L 2s�r. Conductivity 231C MU • - • • • : : :' 229C � • • � � • � � � � 228L : • : � � • � i � 226L • • - 225C 661 W 224L i ; • • • • • i 223C .. 222L • • • • • • • � • • 225C 220C vq,�,: • = E • : : i • • • • i 2190 �1lJl.�1771� • : ' . !� • _ • • =!'� • - 2Q-L . 2018 2019 2020 2021 2022 2023 Figure 17. Cedar Cliff Reservoir Water Column Conductivity, 2018 - 2023 a 235� 2320 - - : Turbidity 2300 2290 � • : : 2280 : e 2270 • • • : • • ' i 2260 22so : . u, 22ao ; � • • • : • • i ' 2230 . • 2220 • ■ • � • • • : : :: 22to 2-110 2018 2019 2020 2021 2022 2023 Figure 18. Cedar Cliff Reservoir Water Column Turbidity, 2018 - 2023 Cedar Cliff Reservoir had very low turbidity levels, only exceeding the state standard for trout waters of 10 NTU (Figure 18) in 2018 (i.e., before spoil placement began). These higher turbidity values originated from water released from Bear Creek Reservoir during the extensive drawdown and maintenance of Bear Creek. Comparison between Reservoir Forebay and Up -lake Water Quality The sampling site (EMP 7) was a reservoir location upstream of the proposed rock spoil area. This site was included in the monitoring proposal to serve as a `control' site for comparison to the forebay site (EMP 4) after the rock from the excavation area was spoiled in the reservoir. Very little water quality differences were observed between the two sites. The obvious difference between the two sites was with the water quality below the forebay penstock invert. Water at the same elevation from both sites had almost identical quality, with the minor exception of slightly higher turbidities at the up -lake location. 22 Rock Experiment In October 2022, a random selection of unwashed rocks greater than 1'/2 inches were placed in a 5-gallon bucket. Another bucket was filled with 10 liters of lake water. A calibrated Hydrolab data sonde was placed in the lake water and set to record pH and conductivity every 5 seconds. At approximately 2-3-minute intervals, a pre -weighed rock was placed in the lake water and agitated to dislodge the rock dust into suspension. A total of 3 kg of rock was added to the 10 liters of lake water. The 3 kg of rock, dislodged 26,000 mg of material (2,600 mg/L suspended solids). 55 6-4 U-3 6-2 CL 6-1 £7 5-9 �. H Conductivity —Suspended Solids Cl 5 10 15 20 25 30 35 40 Elapsed Time (min) 45 3506 35 3000 30 J 131 230D 25 {fi 3 p 2i30G (�7 20 wr m 75G0 a - � 1060 m 10 o 0 540 ~ 5 J-0 O 50 Figure 19. Conductivity and pH Compared to Suspended Solids from Rock Samples Greater than 1'/2 inches The pH and conductivity exhibited little change from the rock dust until the suspended solids reached a concentration of over 100 mg/L (Figure 19). Even at this concentration of solids, which far exceeded Total Suspended Solids (TSS) concentration in the lake, showed minimum change in pH and conductivity. With the addition of more solids the pH increased slightly until a concentration of 1,500 mg/L TSS, at which point the pH decreased until the original pH of 6.1 standard units was reached at a TSS level of 2,600 mg/L. SEM analysis of the suspended solids again showed trace amounts of iron and no sulfur but rather showed the dominance of aluminum -silicate clays. This experiment illustrated that the rock dust originating from spoiled material into the Cedar Cliff Reservoir had little, if any, impact on the pH and conductivity in the lake. Trace amounts of iron and no detectable sulfur compounds were in the rock dust. The rock dust temporarily contributes clays to the water column and added to the existing lake sediment. 23 Chemical Characterization of Cedar Cliff Sites A summary of the analytical procedures listed in Table 3 revealed a wide range of ionic concentrations collected from the various sites (Table 4). The ionic composition in the reservoir and East Fork were very similar for both the baseline period and the excavation period (as the rock experiment suggested). The most notable difference was the lower HCO3' concentrations since the methodology was changed to yield a lower detection limit during the excavation period (Figures 20 and 21). The chemistry of the auxiliary spill channel during the baseline period could be classified as a calcium -sodium: bicarbonate sulfate system. However, during the excavation period the water changed to a primarily a sodium: sulfate system. The temporary storage and subsequent leaching of the fine material temporarily stored in the auxiliary spill channel transported the dissolved compounds, primarily sodium and sulfate, to the surface and into the sediment basin. The sodium and sulfate dissolution and/or ion exchange were indicative of the chemical composition of the parent rock. Even though sulfate was the dominant anion, only trace amounts of iron were detected indicating very little, if any, pyrite oxidation occurred in the fine, excavated material. No ferrous iron was detected in any of the samples collected during the excavation period; again, indicating a minimal potential for pyrite oxidation. Both sodium and chloride decreased throughout the bypassed reach, and since both ions are extremely soluble (Stumm and Morgan, 1981) with no interaction with other compounds, the decreased sodium and chloride concentrations were diluted with inflowing accretion water throughout the Bypassed Reach. 24 Table 4. Analytical Results (Median Concentrations) from all Samples Collected from the Cedar Cliff Samplinq Sites Median Concentration Anions Median Concentration Cations Baseline HCO3 Cir, 2 SO4 NO3" TOTAL Na j K +2 Ca .z Mg .3 Mn .3 Fe .z Fe A+ 3 TOTAL Location (2018 - 2020) Excavation Anions Cations (2021 - 2023) (meq/L) (meq/L) (meq/L) (meq/L) (meq/L) (meq/L) (meq/L) (meq/L) (meq/L) (meq/L) (meq/L) (meq/L) (meq/L) (meq/L) 2018-2020 0.100 0.030 0.690 0.009 0.828 0.089 0.087 0.411 0.122 0.0121 0.00035 0.00000 0.084 0.806 Auxiliary Spill Channel EMP 3 2021 - 2023 0.079 0.056 5.855 0.052 6.095 1.096 0.609 3.857 0.593 0.090 0.002 0.000 0.024 6.696 2018-2020 0.100 0.023 0.386 0.001 0.511 0.058 0.061 0.214 0.068 0.0022 0.00091 0.00011 0.050 0.454 Auxilary Spill Channel High EMP 3 2021 - 2023 0.028 0.020 1.431 0.010 1.577 0.665 0.298 1.332 0.740 0.194 0.012 0.000 0.799 4.803 2018-2020 0.100 0.015 0.528 0.001 0.644 0.099 0.119 0.386 0.132 0.0134 0.00449 0.00000 0.098 0.853 Sediment Basin High EMP 5 2021 - 2023 0.001 0.100 0.041 0.032 6.204 0.477 0.033 0.005 6.312 0.614 0.730 0.104 0.524 0.054 2.852 0.325 0.873 0.107 0.117 0.0120 0.003 0.00107 0.000 0.00000 1.060 0.070 6.448 2018 - 2020 0.673 Upper Bypassed Reach EMP 6 2021 - 2023 0.001 0.042 2.876 0.019 2.978 0.362 0.204 1.370 0.394 0.066 0.000 0.000 0.300 2.913 2018-2020 0.100 0.026 0.614 0.004 0.744 0.078 0.050 0.368 0.096 0.0200 0.00066 0.00000 0.053 0.666 Upper Bypassed Reach High EMP 6 2021 - 2023 0.027 0.039 0.865 0.010 0.918 0.119 0.062 0.486 0.137 0.023 0.002 0.000 0.107 0.934 2018-2020 0.111 0.057 0.174 0.003 0.345 0.102 0.031 0.170 0.073 0.0017 0.00121 0.00019 0.011 0.390 Lower Bypassed Reach EMP 2 2021 - 2023 0.105 0.062 0.378 0.003 0.530 0.141 0.043 0.309 0.119 0.002 0.001 0.000 0.002 0.626 2018-2020 0.118 0.044 0.110 0.001 0.273 0.089 0.040 0.135 0.087 0.0016 0.00193 0.00079 0.032 0.387 Lower Bypassed Reach High EMP 2 2021 - 2023 0.079 0.030 0.060 0.019 0.332 0.090 0.024 0.055 0.029 0.002 0.001 0.000 0.004 0.202 2018-2020 0.100 0.028 0.019 0.002 0.149 0.054 0.015 0.048 0.028 0.0017 0.00292 0.00090 0.017 0.167 East Fork EMP1 2021 - 2023 0.060 0.028 0.022 0.001 0.122 0.053 0.016 0.045 0.026 0.001 0.003 0.000 0.005 0.156 2018-2020 0.100 0.030 0.021 0.002 0.153 0.056 0.016 0.048 0.029 0.0020 0.00294 0.00069 0.019 0.173 East Fork EMP 8 2021 - 2023 0.079 0.031 0.024 0.001 0.132 0.055 0.016 0.046 0.028 0.001 0.003 0.000 0.005 2018-2020 0.100 0.028 0.019 0.001 0.149 0.055 0.014 0.052 0.028 0.0006 0.00192 0.00093 0.013 0.164 Forebay Surface Aerobic EMP 4 2021 - 2023 0.055 0.027 0.020 0.001 0.110 0.052 0.013 0.046 0.027 0.000 0.002 0.000 0.005 0.151 2018-2020 0.100 0.028 0.019 0.001 0.149 0.055 0.014 0.056 0.029 0.0007 0.00193 0.00095 0.013 0.170 Uplake Surface Aerobic EMP 7 2021 - 2023 0.080 0.027 0.019 0.001 0.127 0.054 0.013 0.050 0.027 0.000 0.002 0.000 0.005 0.153 2018-2020 0.100 0.026 0.019 0.001 0.146 0.051 0.012 0.042 0.027 0.0013 0.00258 0.00018 0.020 0.156 Uptake Bottom Aerobic EMP 7 2021 - 2023 0.054 0.025 0.019 0.001 0.102 0.050 0.012 0.043 0.025 0.001 0.003 0.000 0.006 0.143 2018-2020 0.100 0.028 0.020 0.002 0.150 0.051 0.013 0.050 0.029 0.0056 0.00623 0.00228 0.033 0.190 Forebay Bottom Aerobic EMP 4 2021 - 2023 0.065 0.026 0.022 0.001 0.115 0.051 0.013 0.045 0.027 0.001 0.004 0.000 0.005 0.152 2018-2020 0.205 0.027 0.015 0.001 0.247 0.052 0.015 0.087 0.042 0.1102 0.19303 0.02138 0.019 0.540 Forebay Bottom Anaerobic EMP 4 2021 - 2023 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25 2018 - 2020 Baseline Period ■ HCO3-1 ■ CI-1 ■ SO4-2 ■ NO3-1 10.00 S_ t` off. `' 5z`y e ipc aJ aJ �¢ ,tie cpa JQQ `��Qa o�z `��Q F��a e e Qo JQ�a JQ� 9 JQQe pie Sam cam, F,a 10.00 J 1.00 0 2018 - 2020 Baseline Period w Na+1 ■ K+1 w Ca+2 E Mg+2 ■ Mn+3 ■ Fe+3 ■ Fe+2 ■ AI+3 iiiiiiiii N U _ U 0.10 O O.Ol a�yd \ �c e,�a 0a QQe pig °�2 6'�Qa d`F,D `oc as av e P \<,-0 e aicc J a apt ¢ Qua Fo J Q�`f J PJ+a JQQ �o �,D2;� F1:0- Figure 20. 2018 — 2020, Baseline Period - Median Dissolved Anionic and Cationic Species from all Sampling Sites 10.00 J N 1.00 O N V 0 2021 - 2023 Excavation Period ■ HCO3-1 ■ CI-1 ■ SO4-2 ■ NO3-1 cP°co ace°� ea�O JQ�av �a 2021 - 2023 Excavation Period m Na+1 m K+1 ■ Ca+2 m Mg+2 m Mn+3 ■ Fe+3 m Fe+2 ■ AI+3 10.00 1 I I N O . s= U ca 0 0.01 PJcy�� �0 S;a°ca �a Figure 21. 2021 — 2023, Excavation Period - Median Dissolved Anionic and Cationic Species from all Sampling Sites 26 Evaluation of Analytical Results to pH The median pH values from the various sampling sites ranged from 4.5 to 7.0 standard units (Figure 22), with the lowest values observed in the auxiliary spillway channel, the sediment basin, and the upper Bypassed Reach. Highest pH values were recorded from the reservoir forebay surface water. The pH of water from the sampling sites suggests that the low pH values in the auxiliary spillway channel (EMP 3) and the upper bypass site (EMP 6), coupled with high sulfate concentrations; undectable ferrous iron could not be associated with dissociated pyrite of the exposed pyritic rock and fine excavated material stored in the auxiliary spillway channel. However, a detailed review of the analytical data is warranted to elucidate the probable cause of the pH variability. An evaluation of the pH variability is based upon the following chemical equations: • Major pH Buffering in Most Surface Water (Alkalinity): (Stumm and Morgan 1981) H2O H H+ + OH- CO2 + H2O H H2CO3 H H+ + HCO3'- H H+ + C032- 0 Overall Reaction of Pyrite Oxidation (Stumm and Morgan 1981) H2O H H+ + OH- 2FeS2 + 702 + 2H2O --)- 2FeSO4 + 2H2SO4 ■ Baseline (2018 - 2020) Excavation (2021 - 2023) 8.0 7.5 7.0 v 6.5 I 6.0 5.5 N 5.0 4.5 4.0 Im ¢t�� ay5 PJ+� \a�e�� J�� et�� `Dya e��aq Figure 22. Median pH values from all Cedar Cliff Sampling Sites 27 Alkalinity (Bicarbonate/Carbon Dioxide Buffering System) The alkalinity (HCO3-') measured during the baseline period was a consistent 0.1 meq/L) from all samples. In addition, carbon dioxide concentrations seemed unusually high at most sites (Figures 23 and 24). During the baseline period, alkalinity was measured at a fixed pH endpoint with an unknown acid normality. To provide for a more accurate alkalinity method, during the excavation period, alkalinity was determined by a titration utilizing 0.01036 N HCI with the alkalinity calculated from the maximum slope of the titration curve (Figure 25). The titration curves from samples collected from the Lower Bypassed Reach, the East Fork, and Cedar Cliff Reservoir all had titration curves that followed the titration curve of the standard solution. This trend indicated that the pH from those samples was controlled by the bicarbonate -carbon dioxide buffering system. The total alkalinity (HC031) calculated from the titration curves performed during the excavation period revealed much lower concentrations than from the analyses performed during the baseline period (Figure 26). Bicarbonate concentrations were similar in all sites except the sediment basin and upper bypassed reach. The pH at these two sites was less than 4.5 standard units, which is lower than the endpoint of the alkalinity titration curve, hence very little alkalinity. However. at the lower bypass the alkalinity (and pH) exhibited values substantially higher than the upper bypassed reach. The significant changes in alkalinity and pH between the Upper and Lower Bypassed Reaches suggest that accretion flows containing higher bicarbonate contribute to the extremely low flows upstream of the Lower Bypassed Reach. The carbon dioxide concentrations in the lower bypassed reach (EMP 2), the East Fork (EMP 1 and EMP 8), and the reservoir sites correspond to concentrations expected from biological metabolism of respiration and photosynthesis and gaseous exchange with the atmosphere. For example, median CO2 concentrations from the lake surface samples were lower than the median concentrations observed in the deeper depths, which would correspond to photosynthetic and respiratory activity, respectively. Whereas the auxiliary spill channel and the Lower Bypassed Reach the CO2 concentrations appear to be dominated by gaseous exchange with the atmosphere since the concentrations approximated the CO2 atmospheric equilibrium concentration. 51 0.09 0.00 ■ Baseline Period 2018 - 2021 Excavation Period 2021-2023 m 41 S x� Figure 23. Median Alkalinity (HCO31) at all Sites during the Baseline and Excavation Periods a:] 1000.0 , J U E 1000 m a 10.0 `m G C m L0 m 0.1 ■ Baseline Period 2018 - 2021 Excavation Period 2021-2023 IIIIJIlllIl ,4a fo� a v� ,a Figure 24. Median Carbon Dioxide (CO2-) at all Sites during the Baseline and Excavation Periods Relative to Saturation with the Atmospheric CO2. • 0.16 IN NaCd3 Standard —Slope of Standard • Forebay Sample —Slope of ForebaySample nr Upper Bypass Sample —Slope of Upper Bypass Sample 7.00 6.50 5.00 5.50 Q 5.00 4.50 4.00 3.50 3.00 0.00 1.00 2.00 3.00 4.00 = 00 Volume Acid (ml) Slope of Ttration Curve Figure 25. Alkalinity Determination Utilizing a Titration Curve and Endpoint (maximum slope) Comparing Titration with a Known Standard, a Sample from Cedar Cliff Forebay, and a sample from the Upper Bypassed Reach. W Pyrite Oxidation As the chemical equation for pyrite oxidation implies, iron, sulfate, and hydrogen ions are the final products of the reaction. The elevated concentrations of sulfate in the auxiliary spill water, the sediment basin, and the upper bypass (Figure 26) suggest that the low pH levels were the result of pyrite oxidation. The evaluation of the extent of pyrite oxidation centers on the ratios of the pyrite oxidation products. Even though the very soluble ferric sulfate is a product of pyrite oxidation, the oxidized iron reacts to form relatively insoluble ferric hydroxides and ferric carbonates (Stumm and Morgan, 1981). Since the particulate iron, which was approximately 2 orders of magnitude greater than soluble iron, could have originated from pyrite oxidation, it is included in the molar ratio analysis. The molar chemical pyrite oxidation reaction yields 4 sulfates to 4 hydrogens (or 1:1), 4 sulfates to 2 irons (or 2:1), and 4 hydrogens to 2 irons (or 2:1). Even though some ratios may approximate the ratio of individual pyrite oxidation products, if the concentration ratios approximate all three ratios, pyrite oxidation would be considered the primary reaction controlling pH. The ratios involving sulfate and iron (Figure 27) illustrate that most of the ratios are at least and order of magnitude greater than the pyrite oxidation reaction would imply. The exception was observed in the single stage sampler from the auxiliary spill channel, however, that ratio was an order of magnitude less that the chemical equation predicts. The hydrogen ion molar ration to sulfate and iron fractions (Figure 28) showed the sulfate to hydrogen ion ratio was again orders of magnitude greater than the pyrite oxidation reaction predicted. Hydrogen ion ratios to particulate iron were extremely low whereas hydrogen ion to filterable iron approximately equaled the reaction prediction in the auxiliary spill channel single stage sampler, and of the median of samples collected at the lower bypassed reach location. None of the locations exhibited the predicted ratios all three ratios of 4 sulfates to 4 hydrogens (or 1:1), 4 sulfates to 2 irons (or 2:1), and 4 hydrogens to 2 irons (or 2:1). Therefore, pyrite oxidation is not considered the primary reaction controlling pH at any of the sites. all ■H+1 Sulfate ■Particulate ■Filtered IRON Iran 10.0000 1.0000 m m 0 E 0.1000 0 m 0.0100 C: as ci 0 U 0.0010 0.0001 ILI. -P , *__ .. ■ ■ ILI 1 1 1 I .I I I 1 .1 Or Figure 26. Molar Concentrations of Hydrogen Ions, Sulfate, and Iron Fractions from all Cedar Cliff Sampling Sites 1 E+05 1. E+04 1. E+43 0 1. E+02 tr 1. E+41 0 1. E+00 1-E-01 1.E-02 1E-03 Particulate Fe ■ Filtered Fe+3 Pyrite Oxidation Ratio SO4-2 - Fe SO4-2 : Fe+3 e Figure 27. Molar Ratios of Sulfate to Iron Fractions from all Cedar Cliff Sampling Sites 31 ■ SO4-2 - H+1 ■ Filtered Fe+3 ■ Particulate Fe H+1 : Fe H+1 Fe 1-E+45 1. E+4i 1.E+43 O 1-E+42 tu 1. E+41 `m a � 1.E+pp 1.E-01 1.E-02 1. E-03 #: Q Pyrite Oxidation Ratio-- SO4-2: H+1 Pyrite Oxidation Ratio - H+1 : Fe Figure 28. Molar Ratios of Sulfate and Iron Fractions to Hydrogen Ions from all Cedar Cliff Sampling Sites 32 Summary Duke Energy submitted a water quality monitoring plan to the North Carolina Department of Environmental Quality (NCDEQ), Division of Water Quality, on May 19, 2019. to evaluate the extent and influence of pyrite oxidation on the pH in the waters of Cedar Cliff reservoir and the East Fork Tuckasegee River downstream of Cedar Cliff Hydro before and after the Auxiliary Spillway Upgrade Project. Therefore, the purpose of the monitoring plan is to identify the various processes controlling the pH in the project waters, in particular pyrite oxidation as it influences ph. This report covers the data collection from the baseline period (2018-2020) through the excavation period (2021-2023). The methods and sampling sites during the excavation period were the same as during the baseline period, with the following exceptions: • Samples for most parameters consisted of a whole water sample and a filtered sample • Alkalinity titration curves were performed where alkalinity was determined from the inflection point • A laboratory experiment was performed measuring the direct effect of spoiled rock Rock barging consisted of spoiling rocks greater than 1'/2 inches into the lake. The fines were removed with a mobile screen. Material less than 1'/2 inches (fines) were temporarily stored in the auxiliary spill channel until trucked to other locations, both off -site and on -site. Barging material into the lake commenced on May 14, 2021 and ended April 14, 2023 with approximately 164,000 yds3 spoiled. A total of approximately 130,000 yds3 of screened fines were trucked from the auxiliary spill channel to off -site and on -site locations. The lake level was lowered to approximately 50-60% of its total capacity on September 4, 2019, and was managed at this level through most of the excavation period to accommodate barging and other construction activities. Since this lower lake level was below the tainter gate sill, lake water only flowed down the principal spillway when lake levels rose above the tainter gate sill during heavy rains or outages. During these heavy rains, the chemistry at the upper and lower bypassed reach sites resembled that of lake water. During the remainder of time, the principal spill way only received water from the auxiliary spill channel via the sediment basin and, above the lower bypassed reach site, accretion water entered the spillway. The average flow from the bypassed reach into the East Fork Tuckasegee River was calculated to be 7-8 cfs. Due to the temporary storage of the screened rock fines, the auxiliary spill channel had higher conductivity values (dissolved solids) during the excavation period than the baseline period. Primarily sulfate and sodium ions contributed to the increased conductivity values. The sediment basin water collected in the single stage samplers and the upper bypassed reach samples were reflective of these higher values. By the time the water slowly moved down the bypassed reach and accretion water entered the channel, the values were only slightly greater than the East Fork levels. Cedar Cliff Reservoir water quality during the excavation period resembled that during the baseline period. Conductivity and turbidity levels were very low throughout the entire 5 years of sampling turbidity values only approximated the state standard of 10 NTU during the 2019 Bear Creek maintenance. Since retention times of the water was significantly shorter during the lake drawdown period, the influence of biological reactions (photosynthesis and respiration) was reduced during this period. pH values varied little in the lake, median of 6.9 standard units at the surface and 6.1 standard units at the bottom. A laboratory experiment adding rocks greater than 33 1'/2 inches from the rock separator, illustrated that the rock dust had no influence on pH or conductivity. Detailed analyses of alkalinity, and subsequent pH values, revealed that the pH's from the lower bypassed reach location, the East Fork River, and all of the lake samples were controlled by the carbon dioxide -bicarbonate buffering system. Even though sulfate was high in the auxiliary spill channel, sediment basin, and upper bypassed reach locations, molar ratios of hydrogen ions, sulfate, and iron fractions did not support the pyrite oxidation mechanism of controlling pH. The auxiliary spill channel and upper bypassed reach were heavily influence by the temporary storage of the screened rock fines. This influence should be diminished as material is removed. Overall conclusion is that there was no evidence of pyrite oxidation which impacted the pH of Cedar Cliff waters. In addition, the increase of ionic concentrations during the excavation period originating from the auxiliary spill channel due to the temporary storage of screened fines should return to baseline conditions once the auxiliary spill channel returns to exposed bedrock. 34 References American Public Health Association (APHA). 1998. Standard Methods for the Examination of Water Duke Energy Carolinas, LLC. 2018. East Fork Hydroelectric Project (FERC No. 2698) Cedar Cliff Hydroelectric Development Auxiliary Spillway Upgrade Environmental Report and Request for Approval for Temporary Variance from License Article 401 (Reservoir Level Management) pp. E-3. Hach Company. 2005. Hydrolab DSSX, DS5, and MS5 Water Quality Multiprobes, User Manual, Catalog Number 003078HY. HDR. 2017. Geological and Geotechnical Subsurface Investigation, East Fork Hydroelectric Project and Cedar Cliff Development (FERC No. 2698). Tuckasegee, North Carolina, Report for Duke Energy of the Carolinas, LLC. 2018a. Cedar Cliff Rock Spoil Evaluation. East Fork Hydroelectric Project and Cedar Cliff Development (FERC No. 2698) Tuckasegee, North Carolina. 2018b. Cedar Cliff Hydroelectric Development Auxiliary Spillway Upgrade Project Status Update and Permitting Process. Power Point Presentation for Agency Briefing January 18, 2018. Hutchinson, G.E. 1957. A Treatise on Limnology, Vol 1, Part 2 — Chemistry of Lakes Pp.1015. John Wiley and Sons, Inc. New York, NY Knight, JC. and JR Quinn, 2020. Cedar Cliff Hydroelectric Development, Auxiliary Spillway Upgrade Project Baseline (Pre -Auxiliary Spillway Excavation) Monitoring Results. Duke Energy Carolinas, LLC Millar, C.E., L.M. Turk, and H.D. Foth. 1966. Fundamentals of Soil Science, Fourth Edition. John Wiley and Sons, Inc. New York, NY. Pugh, C.E., L.R. Hossner, and J.B. Dixon. 1984. Oxidation rate of iron sulfides as affected by surface area, morphology, oxygen concentration, and autotrophic bacteria. Soil Science. 137:5, pp. 309-314. Stumm, W. and J.J. Morgan. 1981. Aquatic Chemistry. John Wiley & Sons, Inc., New York, NY, 780p. 35