HomeMy WebLinkAboutNCW_Pre-construction meeting summary_2023-04-18
April 18, 2023 Meeting Summary Business Confidential and Proprietary
1
TIMBERMILL WIND PROJECT - MEETING SUMMARY
Meeting Attendees:
Samir Dumpor – NCDEQ
Stephanie Goss - NCDEQ
Robert Tankard – NCDEQ
Maria Dunn – NCWRC
Anthony Scarbraugh – USACE
Kathy Matthews – USFWS
BriAnna Alcorn – Burns & McDonnell
Courtney Didier – Burns & McDonnell
Luke DuPont – Dominion Energy
Andrew Gliniak – Terracon
Lukas Geissbuehler – Timbermill Wind
Blake Greenhalgh – Timbermill Wind
Case Kittel – Timbermill Wind
Jimmy Merrick – Timbermill Wind
Nate Pedder – Timbermill Wind
Hank Seltzer – Timbermill Wind
Jeremy Spaeth – Timbermill Wind
Notes Prepared by: Timbermill Wind, LLC
Date: May 5, 2023
______________________________________________________________________________
On April 18, 2023, Timbermill Wind, LLC (Timbermill Wind) met with the North Carolina
Department of Environmental Quality (NCDEQ), the North Carolina Wildlife Resources
Commission (NCWRC), the U.S. Army Corps of Engineers (USACE), and the U.S. Fish and Wildlife
Service (USFWS) over a Microsoft Teams video call to discuss the Timbermill Wind project
(Project) in Chowan County, North Carolina. Representatives from entities involved in preliminary
construction activities for the Project also attended the meeting. The purpose of the meeting was
to discuss proposed pre-construction activities in 2Q 2023 and to satisfy a condition of the
Project’s Clean Water Act S404 Individual Permit regarding pre-construction meetings with state
and federal agencies. In the meeting, the Timbermill Wind team described the proposed pre-
construction activities and shared maps of their proposed locations.
The following is a summary of the topics discussed.
Phase I Pre-construction Activities
Representatives from Timbermill Wind described Phase I pre-construction activities, include tree
clearing in Waters of the United States (WOTUS) to facilitate geotechnical investigations at the
switchyard location and along the proposed gen-tie transmission line. Representatives from
Terracon, Dominion, and Burns & McDonnell described their respective roles in clearing and
additional geotechnical investigations at the switchyard location. Timbermill Wind estimated that
2-3 acres would be impacted during Phase I activities, based on total impacts within the Project’s
April 18, 2023 Meeting Summary Business Confidential and Proprietary
2
Limits of Disturbance. A smaller portion of the 2-3 acre total would occur within WOTUS.
Timbermill Wind representatives shared maps of the proposed Phase I work areas.
Phase II Pre-construction Activities
Representatives from Timbermill Wind, Dominion, Burns & McDonnell, and Terracon described
proposed Phase II pre-construction activities, which would include clearing, grading, and pad
preparation at the Dominion switchyard location. The switchyard area would be conveyed to
Dominion during Phase II, and Dominion would begin switchyard construction shortly thereafter.
Timbermill Wind estimated that approximately 20 acres would be impacted during Phase II
activities, based on total impacts within the Project’s Limits of Disturbance. A smaller portion of
the approx. 20-acre total would occur within WOTUS. Timbermill Wind representatives shared
maps of the proposed Phase II work areas.
Phase III – Full Notice to Proceed for Construction
Representatives from Timbermill Wind anticipated the start of construction to begin in mid-
August 2023 with tree clearing activities, with full notice to proceed (FNTP) for the balance of
plant contractor to begin road and wind turbine foundation work by October 2023.
Other
Attendees agreed to meet at the Project site in Chowan County on Wednesday, May 03, 2023,
prior to beginning Phase I activities. The objective of the on-site meeting would be to assess
proposed Phase I and Phase II work areas, discuss relevant conditions of the Individual Permit
(including the 401 Water Quality Certification and Biological Opinion), and agree on next steps.
Attendees also agreed a second on-site meeting is warranted later this summer at a time TBD, at
least 30 days prior to construction (currently proposed for mid-August, as noted above).
Action Items:
• Timbermill Wind to schedule on-site meeting for Wednesday, May 3rd, 2023
• Timbermill Wind to provide USACE and NCDEQ DWR details regarding impacts to WOTUS
from proposed Phase I and Phase II pre-construction activities
April 18, 2023 Meeting Summary Business Confidential and Proprietary
3
Attachment 1: Phase I and Phase II Exhibits Shared During Meeting
®CONFID ENT IAL
0 160 320 480 64080
Meters
0 840 1,680 2,520 3,360420
Feet
NC
VA
SC
Timbermill WindIndex Map Coordinate System: NAD 1983 StatePlane North Carolina FIPS 3200 Feet
Projection: Lambert Conformal Conic
Datum: North American 1983
False Easting: 2,000,000.0026
False Northing: 0.0000
Units: Foot US
Date: 4/27/2023
Author: JF
Docume
nt Pa
th
: Y:\GIS\_Projects\NCW_Timbermill\MXD\Setbacks\NCW_PhasedImpacts_Phase1_Index_20230418.mxd
NCW - Timberm ill
Phase 1 and Phase
2 LODs 2023-04-26
See In set Map 1
See In set Map 2
®CONFID ENT IAL
0 50 100 150 20025
Meters
0 300 600 900 1,200150
Feet
NC
VA
SC
Timbermill Wind Coordinate System: NAD 1983 StatePlane North Carolina FIPS 3200 Feet
Projection: Lambert Conformal Conic
Datum: North American 1983
False Easting: 2,000,000.0026
False Northing: 0.0000
Units: Foot US
Date: 4/27/2023
Author: JF
NCW - Timberm ill
Phase 1 and Phase
2 LODs 2023-04-26
N Broad St
R a m p
Peanut Dr
Paradise Rd
SR 1319
U S 1 7
£¤17
£¤17
®CONFID ENT IAL
0 80 160 240 32040
Meters
0 420 840 1,260 1,680210
Feet
NC
VA
SC
Timbermill Wind Coordinate System: NAD 1983 StatePlane North Carolina FIPS 3200 Feet
Projection: Lambert Conformal Conic
Datum: North American 1983
False Easting: 2,000,000.0026
False Northing: 0.0000
Units: Foot US
Date: 4/27/2023
Author: JF
NCW - Timberm ill
Phase 1 and Phase
2 LODs 2023-04-26
Sub Station Rd
U S 1 7
£¤17
®CONFID ENT IAL
0 30 60 90 12015
Meters
0 175 350 525 70087.5
Feet
NC
VA
SC
Timbermill Wind Coordinate System: NAD 1983 StatePlane North Carolina FIPS 3200 Feet
Projection: Lambert Conformal Conic
Datum: North American 1983
False Easting: 2,000,000.0026
False Northing: 0.0000
Units: Foot US
Date: 4/27/2023
Author: JF
NC W - Tim berm ill
Phase 1 and
Phase 2 LO Ds
2023-04-26