Loading...
HomeMy WebLinkAboutWQ0013419_Sludge Landfill Sink Hole Status Report_202302274 Blanchard Road, P.O. Box 85A Cumberland, ME 04021 Tel: 207.829.5016  Fax: 207.829.5692 info@sme-engineers.com sme-engineers.com 220568.01 20230227_letter for NCDEQ.docx ENVIRONMENTAL  CIVIL  GEOTECHNICAL  WATER  COMPLIANCE February 27, 2023 G. Landon Davidson, P.G. Regional Supervisor, Water Quality Operations Section North Carolina Department of Environmental Quality Asheville Regional Office 2090 U.S. 70 Highway Swannanoa, NC 28778-8211 Subject: Sinkhole at Sludge Landfill Dear Mr. Davidson, At request of Glatfelter, this letter was prepared by Sevee & Maher Engineers, Inc (SME) to provide the North Carolina Department of Environmental Quality (NCDEQ) with a status update for the sinkhole at Glatfelter’s Sludge Landfill in Pisgah Forest. The sinkhole was first noticed in July 2022. BACKGROUND The sinkhole is believed to be associated with leachate drainage piping installed as part of the original dam (henceforth referred to as “the dam”). The dam forms the downslope end of the Sludge Landfill. As sludge was placed in the landfill, the height of the dam was first increased about 3 feet (i.e., soil was added to the dam crest). After the crest increase, the dam height was further increased by construction of two soil dikes, one on top of the other. The two dikes increased the overall dam height (before settlement) by approximately 20 feet; the increased height allowed additional sludge to be placed in the landfill. Both dikes were constructed on soft sludge that was already in-place behind the dam and, subsequently, both dikes have undergone settlement. Figure 1 shows an aerial view of the exposed portions of the dam and dikes. Dike #1 is estimated to have been underlain by sludge in the range of 5 to 30 feet thick at the time of construction. Dike #2 is estimated to have been underlain by 30 to 60 feet of sludge at the time of construction. Both dikes continue to settle into the sludge at a slow, but relatively constant rate. The sinkhole is located between the crests for Dike #1 and Dike #2 as shown on Figure 1. Figure 1 also shows the estimated alignment of the two leachate drainage pipes constructed as part of the dam. The 30-inch pipe (at the base of the dam) was installed to drain leachate from the landfill during and after operation. The 30-inch pipe is a corrugated metal pipe that was encased in concrete as part of construction. The 48-inch pipe was installed as a decant pipe to remove leachate from the surface of the relatively impervious sludge after precipitation. The 48-inch pipe is a reinforced concrete pipe (RCP) that was installed in sections as the sludge filling in the landfill progressed. The 48-inch pipe was terminated at the crest of the dam (see Figure 1). The 48-inch and 30-inch pipes connect in a concrete junction box located at the toe of the dam, on the landfill side. Leachate from the 30-inch pipe flows into an existing wastewater aeration stabilization basin (ASB). Figure 1 includes a cross-section of the dam and dikes and includes the approximate locations of the two pipes and the sinkhole. Since the sinkhole was noticed, the flow from the 30-inch pipe has been estimated to be less than 5 gallons per minute (gpm). 220568.01 20230227_letter for NCDEQ.docx February 27, 2023 Page 2 of 4 For safety reasons, no personnel or equipment have been allowed within approximately 5 feet of the sinkhole. Photographs of the sinkhole were taken on July 20, 2022, September 8, 2022, and February 19, 2023. Shortly after the sinkhole was noticed, a pipeline cleaning/inspection contractor attempted to clean the full length of the 30-inch pipe using water jetting methods. The pipeline cleaning contractor stopped work after several days, indicating the equipment available was not large enough to remove a concrete-like obstruction encountered approximately 135 feet into the pipe (as measured from the discharge end). The pipeline cleaning contractor performed a visual inspection of the cleaned portion of the 30-inch pipe using closed-circuit television (CCTV) techniques. In general, the cleaned portion of the pipe appeared in good condition. In January 2023, a second pipeline cleaning/inspection contractor attempted to clean and inspect the 30-inch pipe. The second contractor provided larger equipment that included very high-pressure jetting tools capable of reducing obstructions (like concrete) into small pieces for removal. When the second contractor started work, it was apparent that the 30-inch pipe had essentially become refilled with material from the sinkhole. Materials similar to those observed near the top of the sinkhole (e.g., drainage stone and geogrid, see Figure 2) were present in the material removed from the 30-inch pipe during the second cleaning. Stone riprap was also encountered in the 30-inch pipe during the second cleaning and became more frequent as the cleaning progressed inward. The second cleaning extended approximately 170 feet into the 30-inch pipe before the cleaning contractor indicated it would likely take several weeks to complete due to the size and amount of riprap encountered. The cleaning contractor also expressed concern for further sinkhole collapse if the cleaning continued, and the possible loss of the specially-made cleaning equipment. A CCTV inspection of the second cleaning showed the 30-inch pipe to be in generally good condition, considering it had been in service since approximately 1977. No attempt was made to clean the 48-inch pipe. Visual inspection of the 48-inch pipe (from the open end of the pipe at the crest of the dam) showed the pipe to be damaged and partially filled with soil-like material. DRAINAGE PIPE STATUS SME believes the 48-inch pipe and 30-inch drainage pipes are not necessary for continued stability of the dam, the dikes, and/or the landfill. Previous slope stability analyses did not identify either of the pipes as necessary structural elements relative to dam integrity. Rather, the 48-inch pipe was intended to serve as a decant pipe for the landfill surface before the dikes were added; as result of the dikes, the 48-inch pipe no longer receives runoff from the landfill surface. The 30-inch pipe, owing to its size, is thought to have been designed to handle large leachate flows from the landfill during operation as well as handle some groundwater discharge occurring within the landfill area. A technical document prepared by Law Engineering in the late 1970s concluded that considerable leachate (i.e., water) from the landfill must be draining from the sludge into and through the underlying soil and bedrock, given the low leachate flows observed coming from the 30-inch pipe at that time. 220568.01 20230227_letter for NCDEQ.docx February 27, 2023 Page 3 of 4 SINKHOLE MITIGATION ACTIVITIES The following activities are planned to mitigate the sinkhole. Re-photograph the sinkhole interior. The purpose of the photography will be to evaluate any changed conditions apparent in the sinkhole, evaluate how those conditions could affect the planned mitigation, and to allow an estimate of the sinkhole volume to be made. Drill several borings in the vicinity of the sinkhole and along a portion of the alignment for the 48-inch pipe. The purpose of the borings will be to evaluate if the sinkhole has a larger below-ground component that could hinder mitigation of the sinkhole, and to evaluate if other sinkholes might be present along the alignment for the 48-inch pipe. Backfill and monitor the sinkhole with clean washed gravel having a size consistent with the gravel already visibly present in the sinkhole (i.e., estimated No. 78 size washed aggregate). Effort will be made to drop the gravel into the sinkhole (with an excavator) rather than to push the gravel into the sinkhole. Dropping the gravel into the sinkhole is expected to result in the gravel being some of the first material to reach the 30-inch pipe in the event more material is accepted by the 30-inch pipe. The gravel will be less likely to plug the 30-inch pipe as compared to if the sidewall of the sinkhole collapsed, potentially causing loose sludge and soil to preferentially enter the 30-inch. The sinkhole will be filled to within 2 to 3 feet of the surrounding ground surface with gravel and then be capped with impermeable soil similar to that used to cover the Sludge Landfill. The surface of the filled sinkhole will be visually monitored to determine if settlement is occurring. Monitor flow from the 30-inch pipe. Flow from the 30-inch pipe will be measured two times per week. The flow measurements will be used to form an opinion of if conditions are changing in the 30-inch pipe. Monitor water levels in seven existing piezometers on the dam crest. Water level piezometers were installed in the dam in 2005 to evaluate dam stability as part of closing the landfill. To date, the piezometers have showed water levels consistent with those measured prior to the sinkhole. The water levels will be measured two times per week and then compared to the piezometer level history for the dam. In the event the water levels suggest changed (i.e., adverse) piezometric conditions within the dam, then corrective action will be taken to return the piezometric levels in the dam to pre-sinkhole conditions. 220568.01 20230227_letter for NCDEQ.docx February 27, 2023 Page 4 of 4 Glatfelter and SME look forward to discussing the sinkhole mitigation with NCDEQ and answering any questions NCDEQ might have regarding the planned mitigation. Respectfully, SEVEE & MAHER ENGINEERS, INC. Matthew W. Muzzy, P.E. Principal/Senior Geo-Environmental Engineer Attachments: Figures Photos cc: Brett Laverty (NCDEQ) Jill Urey (Glatfelter) Mike Cody (Consultant to Glatfelter) Jack Garren (Consultant to Glatfelter) FIGURE 0+00 0+20 0+40 0+60 0+80 1+00 1+20 1+40 1+60 1+80 2+00 2+20 2+40 2+60 2+80 3+00 3+20 3+40 3+60 3+80 4+00 4+20 4+40 4+60 4+80 5+00 5+20 5+40 5+60 5+80 6+00 2100 2120 2140 2160 2180 2200 2220 2100 2120 2140 2160 2180 2200 2220 X 2 1 9 5 2 1 9 4 21 9 3 2 1 9 6 2199 21 9 8 21 9 7 21 9 6 219 5 21 9 5 21 9 4 21 9 3 21 9 2 2 1 9 1 21 9 0 2 1 8 9 2 1 8 8 2 1 8 7 2 1 8 6 21 9 6 21 9 5 21 9 5 21 9 4 21 9 3 21 9 2 21 9 1 21 9 0 21 8 9 21 8 8 21 8 7 21 9 4 219 4 21 8 7 21 8 6 21 8 7 21 8 6 21 8 5 21 8 0 21 7 5 21 7 0 21 6 5 21 6 0 21 5 5 21 5 0 21 4 5 21 4 0 21 3 5 21 3 0 21 2 5 21 2 0 21 1 5 21 1 2 2 1 9 4 2195 2 1 9 7 21 9 6 2 1 9 9 2 1 9 8 2 1 9 7 2 1 9 6 2195 2194 2193 2199 2198 2197 2196 2195 220 6220 5 22 0 4 22 0 3 22 0 2 22 0 1 22 0 0 21 9 5 21 8 8 0+00 1+00 2+00 3+00 4+00 5+00 6+00 DWG:REV:LMN:CTB: SME SEVEE & MAHER ENGINEERS ENVIRONMENTAL CIVIL GEOTECHNICAL WATER COMPLIANCE 4 Blanchard Road, PO Box 85A, Cumberland, Maine 04021 Phone 207.829.5016 Fax 207.829.5692 smemaine.com SME SEVEE & MAHER ENGINEERS ENVIRONMENTAL CIVIL GEOTECHNICAL WATER COMPLIANCE 4 Blanchard Road, PO Box 85A, Cumberland, Maine 04021 Phone 207.829.5016 Fax 207.829.5692 smemaine.com2/16/202320220720-UAV-SME-BASE PLAN-PROF SME-STD FIGURE 1 DAM AND SINKHOLE PLAN AND CROSS-SECTION GLATFELTER SLUDGE LANDFILL PISGAH FOREST, NORTH CAROLINA 48" DIA DECANT PIPE 30" DIA PIPE JUNCTION BOX 010 20 40 FEET PLAN PROFILE 010 20 40 FEET 48" DIA DECANT PIPE 30" DIA OUTLET PIPE 12" DIA DRAINAGE PIPE FROM LANDFILL JUNCTION BOX EXISTING SLOPE SINKHOLE SINKHOLE PIPE LENGTH UNKNOWN PIPE LENGTH UNKNOWN NOTES: EXISTING AERIAL IMAGE FROM LOW ALTITUDE AERIAL PHOTOGRAMMETRIC MAPPING PERFORMED BY SEVEE & MAHER ENGINEERS, INC. (SME) OF CUMBERLAND, MAINE, DATED JULY 20, 2022. GROUND CONTROL ESTABLISHED USING AEROPOINTS. N GRI D 15' WIDE CREST OF ORIGINAL DAM 12" DIA PIPE FOR GROUNDWATER DRAINAGE CREST OF DIKE #2 AFTER SETTLEMENT RIPRAP DITCH ESTIMATED LOCATION OF DIKE #1 CREST AFTER SETTLEMENT PIPE CLEANING STOPPED HERE 1 2 1 3 SLUDGE \\ N S E R V E R \ c f s \ P h g \ S l u d g e L a n d f i l l \ A c a d \ 2 0 2 2 0 7 2 0 - U A V - S M E - B A S E . d w g , F I G U R E 1 X S E C , 2 / 1 6 / 2 0 2 3 2 : 1 8 : 4 6 P M , j r l PHOTOGRAPHS 20230227 photos for letter to NCDEQ.docx Sevee & Maher Engineers, Inc. 1 February 2023 1. View of sinkhole on July 20, 2022 2. View of Sinkhole taken on September 8, 2022 20230227 photos for letter to NCDEQ.docx Sevee & Maher Engineers, Inc. 2 February 2023 3. View of Sinkhole taken on February 19, 2023