LETTER OF APPROVAL
RE: Project Name: City of Laurinburg Type 1 Solid Waste Compost Facility
Acres Approved: 8.9
Project ID: SCOTL-2022-012
County: Scotland, City: Laurinburg
Address: Hall Street
River Basin: Lumber
Stream Classification: Other
Submitted by: Michael Brinchek
Date Received by LQS: April 13, 2023
Plan Type: Industrial
Dear Mr. Nichols:
The subject erosion and sedimentation control plan has been approved by default. The
Sedimentation Pollution Control Act (hereinafter "Act") states that this plan must be filed a
minimum of 30 days (15 days for revised plans) prior to the activity and the approving authority
must approve or disapprove the submitted plan within 30 days (15 days for revised plans) of
receipt of G.S. 113A-54.1. The Act further states that if the approving authority fails to approve
or disapprove the submitted plan within the 30-day (15 days for revised plans) period, the plan
will be deemed approved. The enclosed Certificate of Approval must be posted at the job site.
This plan approval shall expire three (3) years following the date of approval, if no land -
disturbing activity has been undertaken, as is required by Title 15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit
an electronic Notice of Intent (NOI) form requesting a Certificate of Coverage (COC)
under the NCGO10000 Construction Stormwater General Permit. This form MUST be
submitted, and COC issued prior to the commencement of any land disturbing activity
on the above -named project. The NOI form may be accessed at dea.nc.gov/NCG0I.
Please direct questions about the NOT form to Brooklyn Broussard at
Brooklyn.broussard(c�r�nedenr. ov or Paul Clark at Paul.clark{a�ncdenr.- ov. After you
submit a complete and correct NOT Form, a COC will be emailed to you within three
business days. Initially, DEMLR will not charge a fee for coverage under the NCGO I
North. Carolina Department of EnvironmentM Quality ! Division of Energy. Mineral and Land Resources
D,E*✓ Fayetteville Regional Office 1 225 Green Street, Suite 714 1 Fayetteville, North Carolina 28301
F Q
W.F.-_UI rw 11 910,4.'3'i300
permit. However, on or after June 1, 2019, a $100 fee will be charged annually. This fee
is to be sent to the DEMLR Stormwater Central Office staff in Raleigh. Title 15A
NCAC 4B .0118(a) and the NCG01 permit require that the following documentation be
kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also, this letter gives the notice required by G.S. I I3A-61.1(a) of our right of periodic
inspection to ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, the erosion and sedimentation control plan is inadequate
to meet the requirements of the Sedimentation Pollution Control Act of 1973 (North
Carolina General Statute 113A-51 through 66), this office may require revisions to the
plan and implementation of the revisions to ensure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal
and State water quality laws, regulations, and rules. In addition, local city or county
ordinances or rules may also apply to this land -disturbing activity. This approval does
not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the
information provided in the Financial Responsibility Form, which you provided. You
are requested to file an amended form if there is any change in the information
included on the form. This permit allows for land disturbance, as called for on the
application plan, not to exceed the approved acres. Exceeding the acreage will be a
violation of this permit and would require a revised plan and additional application
fee. Any addition in impervious surface, over that already noted on the approved
plan, would also require a revised plan to verify the appropriateness of the erosion
control measures and the stormwater retention measures. (GS 113A-54.I(b)). In
addition, it would be helpful if you notify this office of the proposed starting date for
this project. Please notify us if you plan to have a preconstruction conference.
Your cooperation is appreciated.
Sincerely,
Chris Baker
Assistant Regional Engineer
DEMLR - Fayetteville Regional Office
Enclosures: Certificate of Approval
cc: Michael Brinchek, P. E., Smith Gardner, Inc. — email copy
Thomas Milligan, Scotland County Inspection Office — email copy
Fayetteville Regional Office