HomeMy WebLinkAboutHB-0001_CP4B_MergerMeetingSummary_finalMeeting from the Interagency 4B Hydraulic Design Review Meeting
State Project 49475.1.1 (1113-0001) in Dare/Tyrrell County
F.A. Project: NHPB-0001(156)
Meeting Date: April 20, 2022
Minutes Date: June 10, 2022
Team Members:
Seth Wilcher, FHWA
Kyle Barnes, Corps of Engineers
Fritz Rohde, NOAA — NMF
Travis Wilson, Wildlife Resource Commission
Cathy Brittingham, Division of Coastal Management
Johnathan Howell, Division of Coastal Management
James Harrison, DEQ - Marine Fisheries
Greg Daisey, NCDEQ — DCM
Robert Patterson, NCDEQ-DWR
Support Staff/Other Attendees:
Chris Rivenbark, NCDOT ECAP
Gordon Cashin, NCDOT ECAP
Paul Williams, NCDOT Division 1
Barry Hobbs, NCDOT Division 1
John Conforti, NCDOT PMU
Paul Atkinson, NCDOT Hydraulics
Brian Lipscomb, NCDOT Hydraulics
David Hering, NCDOT Geotech
Jennifer Evans, NCDOT PMU
Marissa Cox, NCDOT Biological Surveys
Larry James, NCDOT Utilities
John Jamison, NCDOT EPU
Douglass Kretchman, NCDOT Roadway
Mark Staley, NCDOT Roadside Environmental
James Harrison, NCDOT Roadside Environmental
Tanga Sampson, NCDOT Eastern Regional Utility
Craig Young, Three Oaks Engineering
James Mason, Three Oaks Engineering
Joanna Salvucci, Three Oaks Engineering
Jason Patskoski, Three Oaks Engineering
Bryan Loflin, Modjeski & Masters
Jason Doughty, Modjeski & Masters
Bon -Hsiang Lien, Wood
Michael Lear, Wood
Chien -Ting Tang, Wood
Faith Jahnke, Summit Design & Engineering
Brandon Johnson, Summit Design & Engineering
Patrick Hartnett, Summit Design & Engineering
Jerry Lindsey, Wetherill Engineering
Kathy Herring, RK&K
Jeff Sheldon, Moffat & Nichol
Project Description:
HB-0001 is located across Tyrrell and Dare Counties and consists of replacing bridge #7 on US
64 over Alligator River. The project is approximately 4.2 miles long with approximately 0.9
miles of roadway on new location and approximately 3.3 miles of new structures.
Minutes:
The "413" Meeting for HB-0001 was held on April 20, 2022 from 10:00 AM to 10:45 AM via a
Microsoft Teams meeting. Patrick Hartnett provided a brief project description and proceeded
through the 413 Hydraulic Redline Plans dated March 2022.
General:
- It was noted that the current Wetland Boundaries needed further identification between
CAMA and 404 wetlands.
- The begin and end stations for the bridge deck drains are to be added to the Stormwater
Management Plan.
- There may be Public Trust AEC labels missing from the current redline drainage plans.
- A USCG permit will be required.
- The proposed drainage design currently shown on the 4B plans is preliminary and subject
to change as the design progresses.
- It was noted that the minimum 36" equalizer pipe size was not utilized throughout the
project. This will be revised in the final design.
Sheet 4:
- Impacts include project fill in wetlands and potential excavation in wetlands.
- Fill in wetlands will be due to new alignment as well as proposed wildlife fence along
proposed ROW.
- Potential excavation in wetlands may occur as a result of excavating through the existing
alignment in order to provide access to the proposed wildlife crossing at -L- Sta. 24+25
Sheet 5:
- Impacts include project fill in wetlands.
- 36" RCP equalizer pipe to be installed at -L- Sta. 33+00 +/- within the footprint of
proposed fill slopes to provide wetland connectivity.
- 24" RCP equalizer pipe to be installed at -Y1- Sta. 11+50 +/- within the footprint of
proposed fill slopes to provide wetland connectivity. This will be upsized to a 36" RCP in
the final design.
- The necessity of an RCP equalizer pipe was questioned. It was assumed the wetland area
located south of the proposed -L- alignment, east of the proposed -Y1- alignment and
north of the existing alignment will expand to fill in the remaining non -wetland area
enclosed by the proposed and existing alignments.
Sheet 6:
Impacts include project fill in wetlands and permanent stream impacts in a jurisdictional
stream.
The drainage networks at the begin bridge approach slab will both require riprap outlet
pads in the wetland areas at the fill slope toe.
It was noted that the shoreline stabilization shown beneath the proposed bridge may not
be required as there is existing riprap along the shoreline at this location.
It was noted the closed drainage system at the gas station along the existing alignment
will most likely require a tail ditch that outlets to the wetland area near the coastline. The
redline drainage plans showed a riprap outlet pad in the wetlands at this outlet point but
will be revised to move the outlet pad outside of the wetland area to minimize impacts.
Sheet 7-18:
- Project impacts include permanent stream impacts in a jurisdictional stream.
Sheet 19:
- Impacts include project fill in wetlands and permanent stream impacts in a jurisdictional
stream.
- The drainage networks at the end bridge approach slab will both require riprap outlet
pads in the wetland areas at the fill slope toe.
- It was noted that the redline drainage plans did not show the updated abutment location
as the end bridge location had moved. The abutment will be revised to extend to the new
end bridge location.
- It was noted that the shoreline stabilization shown beneath the proposed bridge may not
be required as the end bent setback is large enough to avoid shoreline stabilization issues.
Sheet 20:
- Impacts include project fill in wetlands and permanent stream impacts in a jurisdictional
stream.
- Fill in wetlands will be due to new alignment as well as proposed wildlife fence along
proposed ROW.
- Proposed wildlife crossing at -L- Sta. 228+60 +/- will also serve as an equalizer pipe to
provide wetland connectivity.
- 24" RCP equalizer pipe to be installed at -Y2- Sta. 14+60 +/- within the footprint of
proposed fill slopes to provide wetland connectivity. This will be upsized to a 36" RCP in
the final design.
- The location of the RCP equalizer pipe was questioned as the current location is closer to
the intersection with -L- than desirable. Placement is limited by proposed turn -around on
-Y2- that provides school bus access to residents on Old Ferry Landing Road.
- Endwalls were recommended for the 48" RCP equalizer pipe located in the channel along
-Y2- for additional stabilization.
- Proposed tail ditch along existing alignment will replace an existing 24" RCP that was
observed to be completely submerged during the field investigation. The proposed tail
ditch will connect the existing channels.
- ECAP inquired whether the bus turnaround could be retained at its existing location on
US 64. The proposed location was selected to provide access to residents on Old Ferry
Landing Road while minimizing foot traffic along US 64.
Sheet 21:
Impacts include project fill in wetlands and permanent stream impacts in a jurisdictional
stream.
Endwalls were recommended for the 48" RCP equalizer pipe located in the channel along
the existing alignment for additional stabilization.
Profile Sheets:
- It was determined that the horizontal and vertical clearances for the proposed bridge will
be labeled.
No further comments.
Meeting adjourned.