Ward, Garcy
From:Wheeler, Tracey L SAW <Tracey.L.Wheeler@usace.army.mil>
Sent:Wednesday, May 06, 2015 9:45 AM
To:Williams, Paul C; Ward, Garcy
Cc:Willis, Thomas C
Subject:RE: Permit modification request for Pasquotank #55 (UNCLASSIFIED)
Classification: UNCLASSIFIED
Caveats: NONE
Paul,
The project as described does not require authorization from the US Army Corps of Engineers. I have included a
copy of your email in the project file. Please notify this office of any changes to the project, as authorization may be
required.
Tracey L. Wheeler
Regulatory Project Manager
U.S. Army Corps of Engineers
Washington Regulatory Field Office
2407 West 5th Street
Washington, North Carolina 27889
(910) 251-4627
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we
continue to do so, please complete the Customer Satisfaction Survey located at http://regulatory.usacesurvey.com/.
-----Original Message-----
From: Williams, Paul C \[mailto:pcwilliams2@ncdot.gov\]
Sent: Tuesday, May 05, 2015 8:50 AM
To: Wheeler, Tracey L SAW; Ward, Garcy
Cc: Willis, Thomas C
Subject: \[EXTERNAL\] Permit modification request for Pasquotank #55
Tracey and Garcy,
Albemarle Electric has recently notified NCDOT that the power line would need to be relocated at the Pasquotank Bridge
#55 project site. Two temporary poles would need to be installed, and each pole will require a guy wire. The installation
of the guy wires will impact wetlands, resulting in a total of 300 sq. ft. of temporary hand clearing.
Each guy wire will require hand clearing an area 6' wide by 25' long in the understory of the wetlands. The areas are
shown in the attached photos. The guy wires will be placed in a manner that will not impact any mature trees in the
wetlands, only impacting the understory of the flooded swamp. Mats will be used in the wetland area of the maintained
utility corridor to move the auger truck into position for pole and guy wire installation. The auger arm of the truck will
reach into the hand cleared areas from the maintained corridor to install the anchors for the guy wires. After bridge
1
construction, the power line will be relocated to its original alignment and the temporary poles and guy wires will be
removed. The hand cleared areas for the guy wires will not be maintained.
The attached revised permit drawing includes the 300 sq. ft. of temporary hand clearing for the guy wires and the
temporary poles.
Please let me know if there is any additional information you need, or any questions you may have about the request.
USACE SAW-2014-00392
NCDWR Project #20140045
Thanks,
Paul C. Williams, Jr.
Environmental Specialist
NCDOT Division One
113 Airport Dr., Suite 100
Edenton, NC 27932
252-482-1861 office
252-482-8722 fax
252-333-9812 mobile
________________________________
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third
parties.