20210364 Ver1_20230330 - PNG Line 142 Bi-Weekly Permit Report_20230330
Project Name: PNG Line 142 Date: 03/30/2023 Feature ID Start Date Completion Date Notes Stream S1 3-1-2023 Matted crossing removed Stream S2 3-1-2023 Matted crossing removed Stream S3 3-1-2023 Matted crossing removed Stream S4 1-9-2023 1-10-2023 Pipe installation complete Stream S5 11-18-2022 11-18-2022 Pipe installation complete Stream S6 12-18-2022 12-19-2022 Pipe installation complete Stream S7 11-25-2022 11-25-2022 Pipe installation complete (HDD) Stream S8 8-25-2022 Clearing complete Stream S9 9-3-2022 Clearing complete Stream S10 9-3-2022 Clearing complete Stream S11 9-3-2022 Clearing complete Stream S12 11-29-2022 11-29-2022 Pipe installation complete Stream S13 8-26-2022 False ROW for HDD Clearing complete Stream S14 8-26-2022 False ROW for HDD Clearing complete Stream S15 3-1-2023 Matted crossing removed Stream S16 3-1-2023 Matted crossing removed Stream S17 3-8-2023 Matted crossing removed Stream S18 9-19-2022 12-10-2022 Pipe installation complete (HDD) Stream S19 1-17-2023 1-18-2023 Pipe installation complete Stream S20 1-17-2023 1-18-2023 Pipe installation complete Stream S21 1-20-2023 1-21-2023 Pipe installation complete Stream S22 9-19-2022 Clearing complete Stream S23 3-20-2023 Matted crossing removed Stream S24 3-22-2023 Matted crossing removed Stream S25 3-22-2023 Matted crossing removed Stream S26 3-23-2023 Matted crossing removed Stream S27 3-20-2023 Matted crossing removed Stream S28 1-6-2023 1-7-2023 Pipe installation complete Stream S29 12-15-2022 12-16-2022 Pipe installation complete Stream S30 12-15-2022 12-16-2022 Pipe installation complete Stream S31 12-19-2022 12-20-2022 Pipe installation complete Stream S32 12-20-2022 12-21-2022 Pipe installation complete Stream S33/34 3-16-2023 Matted crossing removed Stream S35 3-16-2023 Matted crossing removed Stream S36 3-21-2023 Matted crossing removed Stream S37/38 2-8-2023 2-9-2023 Pipe installation complete Project Name: PNG Line 142 Date: 03/30/2023 Feature ID Start Date Completion Date Notes Wetland W1 3-28-2023 Matted crossing removed Wetland W1A 9-19-2022 False ROW for HDD Clearing complete Wetland W1B 03-01-2023 Matted crossing removed Wetland W2 11-30-2022 11-30-2022 Pipe installation complete (HDD) Wetland W3 03-01-2023 Matted crossing removed Wetland W4A-A 9-15-2022 Clearing complete Wetland W4A-B 9-15-2022 Clearing complete Wetland W41) 9-18-2022 Clearing complete Wetland W4C 9-15-2022 Clearing complete Wetland W4E 9-3-2022 Clearing complete Wetland W4F 11-29-2022 11-29-2022 Pipe installation complete Wetland W5-A 11-29-2022 11-29-2022 Pipe installation complete Wetland W5-B 11-29-2022 11-29-2022 Pipe installation complete Wetland W6-A 9-19-2022 12-10-2022 Pipe installation complete (HDD) Wetland W513-A 1-11-2023 1-11-2023 Pipe installation complete Wetland W513-13 1-11-2023 1-11-2023 Pipe installation complete Wetland W6-A1 11-29-2022 11-29-2022 Pipe installation complete Wetland W6-B1 11-29-2022 11-29-2022 Pipe installation complete Wetland W7-A 3-15-2023 Matted crossing removed Wetland W7-13 3-15-2023 Matted crossing removed Wetland W7C-A 3-22-2023 Matted crossing removed Wetland W7C-B 3-22-2023 Matted crossing removed Wetland W7D-A 3-22-2023 Matted crossing removed Wetland W7D-B 3-22-2023 Matted crossing removed Wetland W7E-A 3-24-2023 Matted crossing removed Wetland W7E-B 3-24-2023 Matted crossing removed Wetland W8-A 3-23-2023 Matted crossing removed Wetland W8-13 3-23-2023 Matted crossing removed Wetland W9-A 3-21-2023 Matted crossing removed Wetland W9-13 3-21-2023 Matted crossing removed Wetland W9C-A 12-15-2022 12-16-2022 Pipe installation complete Wetland W9C-B 12-15-2022 12-16-2022 Pipe installation complete Wetland W9D-A 12-17-2022 12-18-2022 Pipe installation complete Wetland W9D-B 12-17-2022 12-18-2022 Pipe installation complete Wetland W9E-A 12-20-2022 12-21-2022 Pipe installation complete Wetland W9E-B 12-20-2022 12-21-2022 Pipe installation complete Project Name: PNG Line 142 Date: 03/30/2023 0136°SE (T) w 35.704249,-78.409356 ► 22 m Wetland W9-A ® 80°E (T) ® 35.705905,-78,418704 A 25 m Wetland W7E-A Project Name: PNG Line 142 Date: 03/30/2023 Ctranm C_71; Stream S-24. Wetland W7A