SUBJECT: Authorization to Construct
A to C No. 025071 A02
City of Eden
Mebane Bridge Road WWTP
Biosolids Dewatering Facility
Phase 1 — Site Work & Foundations Package
Rockingham County
Dear Mr. Corcoran:
A letter of request for Authorization to Construct was received August 5, 2008, by the
Division, and final plans and specifications for the subject project have been reviewed and found
to be satisfactory. Authorization is hereby granted for the Phase 1 (Site Work and Foundation
Package) construction of the Biosolids Dewatering Facility at the existing 13.5 MGD
Wastewater Treatment Plant, with discharge of treated wastewater into the Dan River in the
Roanoke Basin. With the completion of Phase 1 and the future Phase 2 Biosolids Dewatering
Facility construction projects, the Biosolids Dewatering Facility will be operational.
This authorization results in no increase in design or permitted capacity and is awarded
for the construction of the following:
Concrete foundations for the (approximately) 28-foot by 46-foot dewatering
building, the 80-foot by 185-foot sludge storage shelter, and the 50,000 gallon
sludge storage tank, and associated site work and yard piping, in conformity with
the project plans, specifications, and other supporting data subsequently filed and
approved by the Department of Environment and Natural Resources.
The issuance of this Phase 1 Authorization to Construct (ATC) for the Site Work &
Foundation Package of the Mebane Bridge Road WWTP Biosolids Dewatering Facility in no
way implies that issuance of the authorization for the Phase 2 construction of this facility will be
granted. The Phase 2 ATC for the Biosolids Dewatering Facility may be issued after a complete
review of the plans and specifications for this portion of this project. Construction of facilities
other than those approved in this ATC shall not take place until the Phase 2 ATC is issued.
This Authorization to Construct is issued in accordance with Part III, Paragraph A of
NPDES Permit No. NCO025071 issued August 9, 2002, and shall be subject to revocation unless
IVoi�iih C arol i n a
)VII& AY
North Carolina Division of Water Quality 1617 Mail Service Center Raleigh, NC 27699-1617 Phone (919) 733-7015 Customer Service
Intemet: www.ncwaterauafitv.orq 512 N. Salisbury St. Raleigh, NC 27604 FAX (919) 733-2496 1-877-623-6748
An Equal opportunity/Affirmative Action Employer — 50°% Recycled110% Post Consumer Paper
Mr. Stephen B. Corcoran
October 13, 2008
Page 2
the wastewater treatment facilities are constructed in accordance with the conditions and
limitations specified in Permit No. NC0025701.
The sludge generated from these treatment facilities must be disposed of in accordance
with G.S. 143-215.1 and in a manner approved by the North Carolina Division of Water Quality.
In the event that the facilities fail to perform satisfactorily, including the creation of
nuisance conditions, the Permittee shall take immediate corrective action, including those as may
be required by this Division, such as the construction of additional or replacement wastewater
treatment or disposal facilities.
The Winston-Salem Regional Office, telephone number (336) 771-5000, shall be notified
at least forty-eight (48) hours in advance of operation of the installed facilities so that an on site
inspection can be made. Such notification to the regional supervisor shall be made during the
normal office hours from 8:00 a.m. until 5:00 p.m. on Monday through Friday, excluding State
Holidays.
Upon completion of construction and prior to operation of this permitted facility, a
certification must be received from a professional engineer certifying that the permitted facility
has been installed in accordance with the NPDES Permit, this Authorization to Construct and the
approved plans and specifications. Mail the Certification to: Construction Grants & Loans,
DWQ/DENR, 1633 Mail Service Center, Raleigh, NC 27699-1633.
Upon classification of the facility by the Certification Commission, the Permittee shall
employ a certified wastewater treatment plant operator to be in responsible charge (ORC) of the
wastewater treatment facilities. The operator must hold a certificate of the type and grade at
least equivalent to or greater than the classification assigned to the wastewater treatment
facilities by the Certification Commission.
The Permittee must also employ a certified back-up operator of the appropriate type and
grade to comply with the conditions of T15A:8G.0202. The ORC of the facility must visit each
Class I facility at least weekly and each Class II, III and IV facility at least daily, excluding
weekends and holidays, must properly manage the facility, must document daily operation and
maintenance of the facility, and must comply with all other conditions of T I 5A: 8G.0202.
A copy of the approved plans and specifications shall be maintained on file by the
Permittee for the life of the facility.
During the construction of the proposed additions/modifications, the permittee shall
continue to properly maintain and operate the existing wastewater treatment facilities at all times,
and in such a manner, as necessary to comply with the effluent limits specified in the NPDES
Permit.
You are reminded that it is mandatory for the project to be constructed in accordance
with the North Carolina Sedimentation Pollution Control Act, and when applicable, the North
Mr. Stephen B. Corcoran
October 13, 2008
Page 3
Carolina Dam Safety Act. In addition, the specifications must clearly state what the contractor's
responsibilities shall be in complying with these Acts.
Prior to entering into any contract(s) for construction, the recipient must have obtained all
applicable permits from the State.
Failure to abide by the requirements contained in this Authorization to Construct may
subject the Permittee to an enforcement action by the Division of Water Quality in accordance
with North Carolina General Statute 143-215.6A to 143-215.6C.
The issuance of this Authorization to Construct does not preclude the Permittee from
complying with any and all statutes, rules, regulations, or ordinances which may be imposed by
other government agencies (local, state, and federal) which have jurisdiction.
One (1) set of approved plans and specifications is being forwarded to you. If you have
any questions or need additional information, please contact Seth Robertson, P.E. at telephone
number (919) 715-6206.
Sincerely,
1014- Coleen H. Sullins
kp: sr
cc: Tyler Highfill, P.E. — Highfill Infrastructure Engineering, P.C., 1150 SE Maynard Rd,
Suite 250, Cary, NC 27511
Rockingham County Health Department
DWQ Winston-Salem Regional Office, Surface Water Protection
DWQ, Technical Assistance and Certification Unit
DWQ, Point Source Branch, NPDES Program
Daniel Blaisdell, P.E.
Seth Robertson, P.E.
Ken Pohlig, P.E.
ATC File