HomeMy WebLinkAboutSWA000195_Response To Comments_20230323 (3)C UU1 Civil
Design
Concepts, PA
November 22, 2022
Mr. Jim Farkas
Division of Energy, Mineral & Land Resources
Stormwater Program
512 North Salisbury Street, Office 640E
Raleigh, NC 27604
RE: Legacy at Mills River — Phase 1
CDC Project No.: 22160
NCDEQ Permit NO.: TBD
Dear Plan Reviewer,
On behalf of Blue Ridge Retirement Partners, LLC, we are pleased to submit the requested
additional information for your review and approval. The comments identified in the email from
Ms. Margie DeBerry, dated October 25, 2022 are summarized below along with the associated
responses (in blue).
1. Ix original, signed hard copies of the Application with the following corrections made (A
complete application is required per 15A NCAC 02H .1042(3)(a) and per Section F of the
Application). One hard copy of the Application was provided, but two original signed hard
copies are required. CDC — Two originals are provided.
2. Ix hard copy of a USGS map identifying the project location and GPS coordinates for the
project. This is required per 15A NCAC 02H .1043(3)(e) and per Section F of the
Application. One hard copy of a USGS map was provided (in the Hydrology and Erosion
Control Study), however two hard copies are required. CDC — Two copies of the USGS map
are provided.
3. Ix hard copy of the construction sequence discussing how any future development on the
project maybe phased. This is required per 15A NCAC 02H .1043(3)(g). One hard copy of
the construction sequence was provided (in the Hydrology and Erosion Control Study),
however two hard copies are required. CDC — The Construction Sequence provided on C931
has been provided as a separate signed/sealed page.
4. 2x hard copies of documentation from the NC Secretary of State or other official
documentation which supports the titles and positions held by the persons listed in Section
C.2 of the Application per 15A NCAC 2H. 1043(3)(b). This is required per Section F of the
Application. CDC — Two copies of the documentation have been provided.
Mailing Address: P.O. Box 5432, Asheville, NC 28813
168 Patton Avenue Asheville, NC 28801 52 Walnut Street — Suite 9, Waynesville, NC 28786
Phone 828-252-5388 Fax 828-252-5365 Phone: 828-452-4410 Fax: 828-456-5455
Legacy at Mills River — Phase 1
November 22, 2022
Page 2
5. Please indicate whether both phases of the project are being permitted with the submitted
application, or only Phase 1. The project name stated on the application is "Legacy at Mills
River — Ph. V' CDC — This plan set is for Phase 1 only.
6. Section E.5 of the application listed BUA associated with Existing Development. Please
note that "Existing development" as defined in 15A NCAC 02H .1002, means those projects
that are built or those projects that have established a vested right under North Carolina law
as of the effective date of the state stormwater program or applicable local government
ordinance to which the project is subject. If the existing BUA indicated on the application
was built after the post -construction stormwater rules went into effect (2006), and
cumulatively disturbed 1.0 acre or more, a stormwater permit was required, and the proposed
project is not eligible to be permitted under the Fast -Track ATC process. Please provide the
construction date and total area of the existing pavement, buildings, bridge, and gravel road
shown on the submitted plans. CDC — Based on discussions with the current owner, it is our
understanding that the site was previously permitted before 2006 by a now defunct
developer. Since 2006, the only improvements to the site have been the pavement associated
with the temporary sales center. These improvements disturbed less than 1 acre and this
impervious area will be removed once the project is complete. Based on this information it is
our understanding that Phase 1 can continue as a fast -track review.
Please find enclosed the following items for your review and approval:
• Two (2) State Stormwater Fast Track Process: "Authorization to Construct" (ATC) Permit
Application Forms [ORIGINALS]
• Two (2) USGS Maps
• Two (2) Construction Sequence excerpt from Sheet C931.
• Two (2) North Carolina Secretary of State documentation
If you should have any questions or need any additional information during your review, please
do not hesitate to call our office.
Sincerely,
W"'
Michael Ca' P.E.
Civil Design Concepts, P.A.
mcain@cdcgo.com