HomeMy WebLinkAboutcertificateNorth Carolina Division of Water Resources I - 3 Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report – Revised June, 2001
ENVIRONMENTAL MANAGEMENT COMMISSION
Certificate Authorizing the Towns of Cary, Apex, and Morrisville and Wake County
to Increase Their Transfer of Water
from the Haw River basin to the Neuse River basin
under the Provisions of G.S. 143-215.22I
On September 13, 2000, the Towns of Cary, Apex, and Morrisville and Wake County (for RTP
South) petitioned the Environmental Management Commission (EMC) for an increase in the
existing Cary/Apex interbasin transfer certificate from 16.0 to 27.0 million gallons per day,
incidental to their proposed increased withdrawals from Jordan Lake and discharge of treated
wastewater to tributaries of the Neuse River. Public hearings on the proposed transfer increase
were held in Raleigh on March 5, 2001 and in Fayetteville on March 6, 2001 pursuant to G.S.
143-215.22I. The original hearing officer’s report was prepared in April of 2001 and mailed to
members of the EMC on May 2, 2001. A revised hearing officer’s report was prepared in June
of 2001 and mailed to members of the EMC on July 3, 2001.
The EMC considered the petitioner’s request at its regular meeting on July 12, 2001. According
to G.S. 143-215.22I (g), the EMC shall issue a transfer certificate only if the benefits of the
proposed transfer outweigh the detriments of the proposed transfer, and the detriments have been
or will be mitigated to a reasonable degree.
The EMC may grant the petition in whole or in part, or deny it, and may require mitigation
measures to minimize detrimental effects. In making this determination, the EMC shall
specifically consider:
1.The necessity, reasonableness, and beneficial effects of the transfer
2.Detrimental effects on the source river basin
2a.The cumulative effect on the source major river basin of any water transfer or
consumptive water use
3.Detrimental effects on the receiving basin
4.Reasonable alternatives to the proposed transfer
5.Use of impounded storage
6.Purposes and water storage allocations in a US Army Corps of Engineers multi-
purpose reservoir
7.Any other facts or circumstances necessary to carry out the law
In addition, the certificate may require a drought management plan. The plan will describe the
actions a certificate holder will take to protect the source basin during drought conditions.
The members of the EMC reviewed and considered the complete record which included the
hearing officer’s report, staff recommendations, the applicant’s petition, the Final Environmental
Impact Statement, the public comments relating to the proposed interbasin transfer, and all of the
criteria specified above. Based on that record, the Commission makes the following findings of
fact.
North Carolina Division of Water Resources I - 4 Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report – Revised June, 2001
Finding of Fact
THE COMMISSION FINDS:
(1)Necessity, Reasonableness, and Benefits of the Transfer
North Carolina has been enjoying significant population and job growth over the last
decade. Growth in the Triangle is centered on the Research Triangle Park and the
surrounding communities of Durham, Raleigh, Cary, Apex, and Morrisville. The
proposed transfer of water will provide water to three of these fast growing communities
in the Triangle. Their current combined population is about 122,900 with a maximum day
water use of 23.4 million gallons per day (mgd) and projected to grow to a population of
325,400 with maximum day water use of 53.6 mgd by 2030. This water will also support
economic development and job creation in the portion of RTP located in Wake County as
well as the workers who are attracted to the Triangle region to fill these jobs. Raleigh and
Durham each have dedicated sources of water that are adequate to meet current needs but
are inadequate in their current state of development to meet long term demands for these
communities. Raleigh and Durham do not have enough water to supply Cary, Apex, and
Morrisville to meet their long-term needs.
Cary and Apex are located on the eastern boundary of the Jordan Lake Project and have
invested in development of the only water supply intake on the lake, with approval of the
state, sized to allow the withdrawal of 50 mgd of water. The Cary-Apex water treatment
plant provides water to Cary, Apex, Morrisville, RTP, and Raleigh-Durham International
Airport. The Chatham County water system also receives raw water through this intake to
supply water to the eastern part of the county.
The state permitted the development of a raw water intake on the eastern shore of Jordan
Lake to supply surrounding communities from this regional water supply. Cary and Apex
received permission to use Jordan Lake water to meet their community needs and support
economic development in and around RTP. They received permission to transfer 16 mgd
of water from the Haw River Basin to the Neuse River Basin. This amount is no longer
adequate to meet the communities’ water demands. Durham and Raleigh have assisted
the communities receiving water from the Cary-Apex water system by providing water to
the system but can not continue because they need the water to meet demands within
their own service areas.
These petitioners have made a request to transfer enough water to meet their future needs.
The petitioners’ combined 2030 projected transfer amount is 24.1 mgd plus an additional
2.9 mgd contingency amount for a total requested amount of 27 mgd. The projected
2009 transfer amount is 27 mgd, which will drop to 17.9 mgd in 2010 when the regional
water reclamation facility becomes operational. The 24.1 mgd transfer amount assumes
that the Towns of Cary and Apex will construct a regional water reclamation facility that
would discharge to the Cape Fear River Basin by 2010, therefore limiting the need for
additional future transfers.
North Carolina Division of Water Resources I - 5 Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report – Revised June, 2001
The transfer of water will benefit the Research Triangle Region by guaranteeing water to
support the economic development and associated population growth that have been
encouraged by the establishment of the Research Triangle Park.
Based on the record the Commission finds the transfer is necessary to supply water to the
growing communities of this area. Water from the source basin is readily available and
within a short distance from the service area. The applicants have reasonably mitigated
this need by returning treated wastewater to the source basin by December 31, 2009, and
therefore the transfer is a reasonable allocation to these communities. The transfer will
greatly benefit these communities by providing raw water of high quality for residential
and industrial purposes.
The Commission finds that the appropriate transfer amount should not include a
contingency factor, therefore 24 mgd is the appropriate necessary and reasonable
transfer amount.
(2)Detrimental Effects on the Source Basin
In order to assess the direct impacts of the proposed transfer on the source basin,
the petitioners participated in the development of a Cape Fear River Basin
Hydrologic Model that was developed for water supply planning, using Moffat &
Nichol and the Danish Hydraulic Institute as contractors. The model considers all
major water withdrawals (water supply and irrigation) and discharges within the
Cape Fear River basin, including those into and out of Jordan Lake. As required
under G.S. 143-215.22I(f)(2), local water supply plans were considered in
developing the model. In addition, industrial and agricultural withdrawals were
model inputs. Model runs for seven alternatives were evaluated for present and
2030 water demands. Impacts were assessed for the Jordan Lake watershed and
downstream to Lock and Dam Number 1, including impacts at Fayetteville.
The source for all of the petitioners’ water is the water supply pool of Jordan
Lake. The water supply pool is operated entirely separate from the low flow
augmentation pool. The low flow augmentation pool, not the water supply pool, is
dedicated to maintaining flows in the Cape Fear River downstream of Jordan
Lake dam. Therefore, the petitioners’ water supply withdrawals will have no
significant impact on the downstream flows as demonstrated with the model. A
comparison of the alternatives showed that the proposed transfer will not have any
significant impact on Jordan Lake surface water elevation, minimum releases
from the dam, water quality pool levels, the target flows at Lillington, flows at
Fayetteville, and water quality pool levels compared to the other alternatives and
to present conditions (see Appendix B in the EIS). As shown in the following
figure (Figure 14 from the EIS) there are no significant differences in flows at
Fayetteville.
North Carolina Division of Water Resources I - 6 Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report – Revised June, 2001
Approximately two-thirds of Jordan Lake's conservation storage is dedicated to
maintaining minimum flows in the Cape Fear River, compared with the one-third
dedicated to water supply. Downstream users benefit from this low-flow
augmentation pool without requiring a Jordan Lake allocation and at no cost.
Upstream users do not benefit from the low flow augmentation pool. The historic
low flow of the Cape Fear River at Lillington was 75 cfs prior to regulation by
Jordan Dam. The target flow at Lillington is now 600 cfs, supported by the low
flow augmentation pool of Jordan Lake. This target flow is 8 times as great as the
historic low flow, and equivalent to 388 mgd. Even allowing for instream flow
requirements for habitat, an enormous amount of water is available to downstream
users. Based on the 1997 Local Water Supply Plans the projected water supply
demand for the middle Cape Fear River (Jordan Lake to Fayetteville) is 93.5 mgd.
The target flow of 388 mgd is over 4 times as great as the projected municipal
water supply demand.
Because wastewater assimilation is directly related to flows, no significant
changes in wastewater assimilation are expected from the proposed action.
Similarly, no impacts were identified for hydropower generation, navigation or
recreation.
Secondary effects from growth such as increased runoff, erosion, and loss of open
space are expected to have negative impacts on water quality and fish and wildlife
habitat. These impacts will be mitigated to a reasonable degree through existing
regulations and programs, as well as new initiatives. The most notable of these
initiatives are Cary’s Stream Buffer Ordinance and Open Space and Historic
Resources Plan
The Commission finds that it is reasonable to minimize the impacts of secondary
effects caused by growth in the Towns of Cary, Apex and Morrisville and Wake
County through the implementation of ordinances similar to the Neuse River
Buffer rules for the parts of their jurisdictions that are within the Jordan Lake
watershed for protection of the lake.
North Carolina Division of Water Resources I - 7 Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report – Revised June, 2001
(2a)Cumulative effect on Source Basin of any transfers or consumptive water use
projected in local water supply plans
Local water supply plan data, including current and projected water use and water
transfers, were used to develop the input data sets for the Cape Fear River Basin
Model. The model was used to evaluate current and future scenarios of basin
water use.
In a statement to the Commission, a representative of the Public Works
Commission of Fayetteville asserted that the Department of Environmental and
Natural Resources had established a limit on the amount of water PWC could
withdraw from the Cape Fear River. He was asked to provide the Commission a
copy of that document. The document was a memo from the North Carolina
Division of Environmental Management (now the Division of Water Quality),
dated December 9, 1996 from Jason Doll transmitted through Ruth Swanek to
Tom Fransen, Division of Water Resources.
The sentence in that memo that caused concern to representatives of Fayetteville
states: “...our analysis indicates the City of Fayetteville could withdraw up to 60
MGD from the Cape Fear River without causing substantial declines in predicted
instream DO (dissolved oxygen) levels.”
North Carolina Division of Water Resources I - 8 Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report – Revised June, 2001
That sentence does not limit how much water Fayetteville can withdraw from the
Cape Fear River. In fact, there is no existing regulation that explicitly limits the
amount of water Fayetteville can withdraw from the river. North Carolina does
not have a statewide permit system for water withdrawals. The only procedure
for issuing such permits is the Capacity Use Act of 1967. Under that authority,
the Environmental Management Commission must first declare a specific
geographical area to be a “capacity use area” based on findings that “aggregate
uses of groundwater or surface water, or both, in or affecting said area (i) have
developed or threatened to develop to a degree which requires coordination and
regulation, or (ii) exceed or threaten to exceed, or otherwise threaten or impair,
the renewal or replenishment of such waters or any part of them”. Only one area
of the state has ever been so designated, that being the area around the phosphate
mining operation near Aurora. Another area currently under consideration for
designation is a portion of the central coastal plain. No such designation has ever
been considered for surface water withdrawals from the Lower Cape Fear River,
and given the abundance of water in that area relative to current and foreseeable
use, it is highly unlikely that such an action would be contemplated for decades to
come. Given projected water use in the Lower Cape Fear River relative to
available supply, there is no foreseeable limit on withdrawals from the river.
The memo in question goes on to say that: “The Division (of Water Quality) does
not believe that our water quality predictions constitute a basis to impede
increases in withdrawal from the Cape Fear River by the City of Fayetteville.”
It does say that DWQ reserves the right to assign even more stringent effluent
limits in the future if the need arises. That statement would be true for all
dischargers in North Carolina. Details of the earlier analysis have been
challenged and are now under review. A consulting engineering firm, CH2MHill,
has been retained by the cities of Cary and Fayetteville to review and evaluate the
QUAL2E models used in that analysis. That review is expected to be completed
in August 2001 at the earliest.
Under no foreseeable circumstances, however, would Fayetteville’s withdrawal
be limited by water quality considerations. Durham and the Orange Water and
Sewer Authority (Chapel Hill/Carrboro) are permitted to discharge effluents from
their wastewater treatment plants into streams with low flows of less than 1.0
MGD. They are upstream of an arm of Jordan Lake that has a very long detention
time. When comparing those dischargers with Fayetteville, two factors are
important. First, effluent limits assigned to the Durham and Chapel Hill plants for
substances related to dissolved oxygen are very comparable to those for
Fayetteville plants. Current limits are given in the table below. Second, the Cape
Fear River at Fayetteville has critical low flows several hundred times those for
streams into which Chapel Hill and South Durham are discharging.
North Carolina Division of Water Resources I - 9 Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report – Revised June, 2001
Effluent Limits
BOD Ammonia
mg/l mg/l
Facility summer/winter summer/winter
OWASA 4/8 2/4
South Durham 5/7 1/2
Fayetteville Cross Creek 6.8/8 1/2
Fayetteville Rockfish Crk 5/10 1/2
Furthermore, any effect on water quality due to Fayetteville’s withdrawals would
be limited primarily to that section of the river between the point of withdrawal
and the points of discharge.
Based on the modeling discussed in Finding No. 2, the Commission finds the
cumulative effects of this and other future water transfers or consumptive uses as
described in G.S. §143-215.22I(f)(2a) will be insignificant. Also, the EMC
concludes that, despite the language in the December 9, 1996 memorandum, the
proposed transfer will not adversely affect or limit water supply availability in the
Fayetteville area.
(3)Detrimental Effects on the Receiving Basin
The proposed transfer will utilize existing permitted wastewater discharges to the Neuse
River basin; therefore no plant expansions will be required. Previous studies for the
existing plants indicated no significant direct impacts to water quality or wastewater
assimilation on the receiving streams. Because stream flows in the Neuse River basin are
not expected to change significantly due to the proposal, no impacts are likely to occur to
navigation, recreation, or flooding. According to 1998 Neuse River Basinwide Water
Quality Plan: “Over 80% of the freshwater streams in the basin that have been monitored
are either impaired or rated as fully supporting but threatened. …. A major cause of this
impairment, especially in the upper basin, is population growth and urbanization, and
every indication is that this strong growth will continue for decades to come. In addition
to the tremendous challenges ahead in balancing the growth in the basin with the
restoration of its waters, it is also clear that if we are to prevent more waters from
becoming impaired in the future, and if the nutrient-related problems in the lower basin
and lakes are to be solved, it can no longer be business as usual in the Neuse.”
North Carolina Division of Water Resources I - 10 Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report – Revised June, 2001
Based on the record the Commission finds the transfer will support continued population
growth and the attendant impacts of that growth. These impacts include effects on
wastewater assimilation, fish and wildlife habitat, and water quality similar to the
secondary growth effects described in Finding No. 2, above. However, these impacts will
be minimal. Reasonable mitigation is prohibiting additional wastewater treatment
facilities in the Neuse River basin as a result of this transfer and to limit the applicants’
existing Neuse River wastewater treatment facilities to their current permitted levels.
(4)Alternatives to Proposed Transfer
The petitioners evaluated six alternatives to the proposed transfer. The alternatives
considered include:
Alternative 1A: No IBT Increase and No Additional Jordan Lake Allocations
§ No increase in the existing 16-mgd (average day basis) Jordan Lake allocation
§ No increase in the existing IBT certificate (16 mgd on a maximum day basis)
§ No construction of a regional treatment and water reclamation facility
§ No other additional discharges to the source basin, in western Wake County
Alternative 1B: No IBT Increase with Additional Jordan Lake Allocations
§ Increases in Jordan Lake water supply allocations
§ No increase in existing IBT certificate (16 mgd on maximum day basis)
Alternative 2: Obtain Water From the Neuse River Basin
§ No increase in existing IBT certificate (16 mgd)
§ Regional Cape Fear WWTP
§ Purchase of finished water from the Neuse River basin
Alternative 3: Increase Wastewater Discharges to Cape Fear River Basin
§ No increase in existing IBT certificate (16 mgd)
§ Additional Jordan Lake water supply allocations
§ Relocation of existing Apex and Cary WWTP discharges to Cape Fear basin
§ Regional Cape Fear WWTP
Alternative 4:Merger of Water and Sewer Utility Operations of Town of Cary and City
of Durham
§ Institutional arrangement offsets existing Durham transfer (Neuse to Haw)
§ No increase in existing IBT certificate (16 mgd)
§ Additional Jordan Lake water supply allocations
§ Regional Cape Fear WWTP
North Carolina Division of Water Resources I - 11 Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report – Revised June, 2001
Alternative 5: No Regional Treatment and Water Reclamation Facility
§ Discharge through existing WWTPs in Neuse River basin
§ Additional Jordan Lake water supply allocations
§ 45 mgd IBT
The table on the following page compares the proposed transfer with the six alternatives.
Factors used in the comparison of alternatives include:
§ required increase in interbasin transfer
§ direct and indirect impacts
§ ability to meet future water needs
§ capital cost
§ construction of a regional water reclamation facility
§ outside water purchases
§ expansion of Cary/Apex water treatment plant
Except for Alternative 1A, which does not serve the projected water supply needs of the
petitioners, the alternatives will not substantially reduce the expected impacts of the
proposed transfer increase. The only significant impacts associated with the proposed
transfer are secondary impacts associated with growth. All of the alternatives will have
essentially the same growth related impacts due to high rates of regional growth.
Based on these comparisons, the Commission finds that the proposed alternative is the
most feasible means of meeting the petitioners’ long-term water supply needs while
minimizing overall impacts and cost.
North Carolina Division of Water Resources I - 12 Jordan Lake Water Supply Storage Allocations
Environmental Management Commission Round Two and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report – Revised June, 2001
Summary of Alternatives
Alternatives
Item
Proposed
Action
1A
No Action
1B
No Action
2
Water From
Neuse
3
Move WWTP
Discharges
4
Merger with
Durham
5
No Regional
WWTP
Increase in IBT (mgd)11 0 0 0 0 0 29
Significant Direct Impacts No No No Yes Yes No Yes
Significant Secondary Impacts Yes Yes Yes Yes Yes Yes Yes
Additional Jordan Lake Allocations Yes No Yes Yes Yes Yes Yes
2030 MDD Water Demands (mgd)53.6 19 43.8 53.6 53.6 53.6 53.6
Maximum IBT (mgd)251 16 16 16 16 19
(Neuse to Haw)
45
Total Capital Cost (million)$225.7 $11.1 $206.6 $206.9 $279 $248 $84.0
Water Reuse 3.8 mgd 3.8 mgd 3.8 mgd 3.8 mgd 3.8 mgd 3.8 mgd 3.8 mgd
Construct Regional WWTP
(2030 max month capacity)
18.0 mgd No 18.0 mgd 18.0 mgd 18.0 mgd 18.0 mgd No
Finished Water Purchases
(2030 max day demand)
No No No 9.2 mgd No No No
Expand Cary/Apex WTP (capacity
beyond 40 mgd, max day basis)
20.0 mgd No 9.0 mgd 9.0 mgd 20.0 mgd 20.0 mgd 20.0 mgd
Note: 1Projected IBT in 2030 is approximately 25 mgd. The requested amount of 27 mgd includes some contingency
North Carolina Division of Water Resources I - 13 Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report - Revised June, 2001
(5)Impoundment Storage
This criterion is not applicable, as the petitioners do not have an impoundment.
(6)Jordan Lake Purposes/Water Supply
The source of the water for this transfer is Jordan Lake, which is a multipurpose reservoir
constructed by the United States Army Corps of Engineers. One of the federally
authorized purposes of this reservoir is water supply. Water is allocated from this
reservoir intermittently. The applicants for this transfer plan to secure an allocation prior
to initiating this transfer.
The Commission finds that the transfer and allocations are consistent with the federally
authorized project purposes of Jordan Lake. Also, the Commission finds that to be
consistent with the use of Jordan Lake as a regional water supply Cary/Apex are
required to provide access through their intake with other Jordan Lake Water Allocation
Holders that need access to their allocation. The cost associated with getting any
necessary permits, engineering design, and associated construction costs are not the
responsibility of Cary/Apex.
(7)Other Considerations
The Commission finds that to protect the source basin during drought conditions, to
mitigate the future need for allocations of the limited resources of this basin, and as
authorized by G.S. § 143-215.22I(h), a drought management plan is appropriate. The
plan should describe the actions that the Towns of Cary, Apex, Morrisville and Wake
County (for RTP South) will take to protect the Cape Fear River Basin during drought
conditions.
The Commission notes that future developments may prove the projections and
predictions in the EIS to be incorrect and new information may become available that
shows that there are substantial environmental impacts associated with this transfer.
Therefore, to protect water quality and availability and associated benefits, modification
of the terms and conditions of the certificate may be necessary at a later date.
North Carolina Division of Water Resources I -Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report - Revised June, 2001
14
Decision
Based on the hearing record and the recommendation of the hearing officers, the Commission, on
July 12, 2001, by duly made motions concludes that by a preponderance of the evidence based
upon the Findings of Fact stated above that (1) the benefits of the proposed transfer outweigh the
detriments of the proposed transfer, and (2) the detriments of the proposed transfer will be
mitigated to a reasonable degree. Therefore, and by duly made motions, the Commission grants
the petition of the Towns of Cary, Apex, Morrisville, and Wake County (with modification) to
increase their transfer of water from the Haw River basin to the Neuse River basin. The
permitted transfer amount shall be 24 million gallons per day (mgd) on a maximum day basis
from the effective date. This certificate supercedes any other transfer certificates held by the
Towns of Cary and Apex under G.S. § 143-215.22I and any other laws. This certificate is
effective immediately. The certificate is subject to the following conditions, imposed under the
authority of G.S. § 143-215.22I:
1. The holders of this certificate, after 2010, shall return water supplied from the Haw River
basin used in the Neuse River Basin to either the Haw or Cape Fear River basins as described
below:
(a) Any water used in the Neuse Basin in excess of 16 million gallons per day
adjusted on an average daily basis shall be returned.
(b) Water used for consumptive purposes in the Neuse Basin will not be subject
to this condition.
Nothing in this certificate shall decrease the amount of any transfer that existed
prior to July 1, 1993 or that was approved pursuant to G.S. § 162A-7 (repealed by
1993 Laws, ch. 348, § 6), as provided in G.S. § 143-215.22I(i), including such
approved transfer of 16 million gallons per day.
For purposes of this condition the average annual daily return to the Haw River
and Cape Fear River basin will be calculated as follows:
All amounts are a calendar year average annual daily amount in million of gallons
per day (mgd).
Peaking Factor (PF) = Maximum Daily Demand (MDD) / Average Daily Demand
(ADD)
For the first year PF = 1.64. Thereafter, the certificate holders annual compliance and
monitor report will include the information needed by the Division of Water Resources to
determine if an adjustment is needed for PF. The Division of Water Resources shall have
the authority to make modifications to PF as necessary to accurately reflect local water
use practices.
Consumptive use = C% of Finished Water (X) (average annual basis)
Neuse Consumptive use (CN) = C% of Finished Water (X) times Neuse Finished
Water (XN)
North Carolina Division of Water Resources I -Jordan Lake Water Supply Storage Allocations Round Two
Environmental Management Commission and Proposed Increase in Interbasin Transfer
Hearing Officers’ Report - Revised June, 2001
15
For the first year C% = 20%. Thereafter, the certificate holders annual compliance
and monitor report will include the information needed by the Division of Water
Resources to determine if an adjustment is needed for C%. The Division of Water
Resources shall have the authority to make modifications to C% as necessary to
accurately reflect local water use practices.
Required Return (RR) = (Neuse Finished Water (XN) - 16 mgd adjusted to an
average annual basis (16 / Peaking Factor (PF)) – Neuse Consumptive use (CN)
RR = (XN – 16/ PF) – C% XN
If RR is less than Zero then RR = 0
2. The holders of this certificate shall manage the authorized transfer amount in such a way that
none of the individual petitioners (Towns of Cary, Apex, Morrisville, and Wake County (for
RTP South)) are prevented from fully using their respective Jordan Lake water supply
allocations.
3. If the holders of this certificate discontinue their cooperative service agreement with each
other, the maximum day permitted transfer will be adjusted by the Division of Water
Resources based on the 2030 projected transfer of each applicant at that time.
4. Prior to transferring water under this certificate, the holders of this certificate shall work with
the Division of Water Resources to develop compliance and monitoring plan subject to
approval by the Division. The plan shall include methodologies and reporting schedules for
reporting the following information: maximum daily transfer amounts, compliance with
permit conditions, progress on mitigation measures, drought management, and reporting. A
copy of the approved plan shall be kept on file with the Division for public inspection. The
Division of Water Resources shall have the authority to make modifications to the
compliance and monitoring plan as necessary to assess compliance with the certificate.
5. If either the EIS is found at a later date to be incorrect or new information becomes available
such that the environmental impacts associated with this transfer are substantially different
from those projected impacts that formed the basis for the above Findings of Fact and this
certificate, the Commission may reopen the certificate to adjust the existing conditions or
require new conditions to ensure that the detriments continue to be mitigated to a reasonable
degree.
6. The Towns of Cary and Apex shall be required to provide access at their existing intake site
to other Jordan Lake water allocation holders that need access to utilize their allocation to the
extent that this additional use is determined to be feasible by the Division of Water
Resources. The cost associated with getting any necessary permits, engineering design, and
associated construction costs are the responsibility of the allocation holder(s) requesting the
access and not Cary and Apex.