SEDIMENTATION INSPECTION REPORT
Dear Sir or Madam:
Enclosed is a copy of the inspection report, which was prepared following an
onsite inspection of the referenced project. This report is intended to provide you
with infonnation concerning the status of the project as it relates to compliance with
the North Carolina Sedimentation Pollution Act of 1973.
Please review this report carefully, as it may contain corrective actions needed
or comments, which will assist you in meeting the required standards of the Act.
It is our desire that any and all possible problems be discussed and resolved at
the earliest possible time. To facilitate this effort, please contact me or the named
inspector at the address shown on the inspection report if you have any questions.
Sincerely,
Tamers plin, PE, CPESC
Regional Engineer
Land Quality Section
Enclosure: Sedimentation Inspection Report
Norlh Carolina Depadinonl of Envlrcmnenlal Quaiily ! fllvision of Energy. Minerals & [.and Rescuraos
Winston-&alenl Regional Office 1450 Wasl Hales Mil! Road, Suile 100 / Winslor-5alarn, North Carolina 27105
(336) 776-9800
North Carolina Department of Environmental Quality
Land Resources: 450 W. Hanes Mill Road, Suite 300, Winston-Salem, NC 27105
(336) 776-9800
County: Guilford Project: Peeler Community Recreation Parking Lot River basin: Cape Fear
Person financially responsible: City of Greensboro Project #: GUILF-2021-009
Address: PO Box 3136, Greensboro, NC 27402-3136
1. Project Location: Sykes Ave, Greensboro
Pictures: No
2. Weather and soil conditions: 50's, Clear, Workable
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes
5. Violations:
Initial inspection: No
if no, check violations below:
6. Is the site in compliance with NPDES Permit NCG010000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No IfYes, where? (check all that apply)
Degree of damage:
8. Contact made with (name):
Inspection report: Sent Report
9. Corrective action needed:
Title:
Date given/sent: February 13, 2023
10. Comments: Permanent ground cover sufficient to restrain erosion has been established. No additional
self -monitoring or self -inspections are required. Project is in compliance and released under
the SPCA. Termination of coverage under the NPDES General Stonmwater Permit for
Construction Activities (NCGO 1) must be requested by the pennittee via a Notice of
Termination (NOT). The NOT is available at:
https://edocs.deq.nc.gov/Forrns/NCG01-Termination. Please note that this correspondence
must be uploaded as part of completing the NOT process.
Reported by: Kimberly Tumey
Date of inspection: February 08, 2023 Time arriving on site: 2:00 PM Time leaving site: 2:30 PM