February 22, 2023
LETTER OF APPROVAL
Express Option
Chick Fil-A, Inc.
Attn: R. Todd Williams, Director
5200 Buffington Road
Raleigh NC 27606
RE: Project Name: Lumberton CFA
Acres Approved: 1.2
Project ID: ROBES-2023-029
County: Robeson, City: Lumberton, Address: 3400 North Elm Street
River Basin: Lumber
Stream Classification: Other
Submitted By: Carter Engineering Consultants, Inc.
Date Received by LQS: February 22, 2023
Plan Type: Express
Dear Mr. Williams:
This office has reviewed the subject erosion and sedimentation control plan and hereby issues this Letter
of Approval. This plan approval shall expire three (3) years following the date of approval, if no land -
disturbing activity has been undertaken, as is required by Title 15A NCAC 4B .0129. Should the plan not
perform adequately, a revised plan will be required (G.S. 113A-54.1)(b).
As of April 1, 2019, all new construction activities are required to complete and submit an electronic Notice
of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the NCG010000 Construction
General Permit. After the form is reviewed and found to be complete, you will receive a link with payment
instructions for the $100 annual permit fee. After the fee is processed, you will receive the COC via
email. As the Financially Responsible Party shown on the FRO form submitted for this project, you MUST
obtain the COC prior to commencement of any land disturbing activity. The eNOI form may be
accessed atdeq.nc.gov/NCGOI. Please direct questions about the NOI form to Paul Clark at
Paul.clarkkncdenr.gov. After you submit a complete and correct NOI Form, a COC will be emailed to you
within three business days. A $100 fee will be charged annually until a Notice of Termination is issued.
This fee is to be sent to the DEMLR Stormwater Central Office staff in Raleigh. If the owner/operator of
this project changes in the future, the new responsible party must obtain a new COC.
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation be kept on
file at the job site:
D E Q�� North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
Fayetteville Regional Office 1225 Green Street, Suite 7141 Fayetteville, North Carolina 28301
NORTH CAROLINA -
DepoWnentetEnelronme'JQ.a" /`� 910.433.3300
Letter of Approval
Chick Fil-A, Inc.
February 22, 2023
Page 2 of 2
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Also, this letter gives the notice required by G.S. I I3A-61.1(a) of our right of periodic inspection to ensure
compliance with the approved plan.
Title 15A NCAC 4B .0118(a) requires that a copy of the approved erosion control plan be on file at the job
site. Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to
ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, it is
determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the
Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this
office may require revisions to the plan and implementation of the revisions to ensure compliance with the
Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply to
this land -disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the Financial
Responsibility Form, which you provided. You are requested to file an amended form if there is any change
in the information included on the form. This permit allows for a land -disturbance, as called for on the
application plan, not to exceed the approved acres. Exceeding the acreage will be a violation of this permit
and would require a revised plan and additional application fee. In addition, it would be helpful if you notify
this office of the proposed starting date for this project.
Your cooperation is appreciated.
Sincerely,
it�t.
odi Pace, EI
Regional Engineering Associate
DEMLR
Enclosures: Certificate of Approval
Modifications Required for Approval
NPDES NCGO1 Fact Sheet
cc: Mark Campbell, Carter Engineering Consultants, Inc. (electronic copy)
Jody Allen, Building Inspector (electronic copy)
DEMLR - Fayetteville Regional Office