HomeMy WebLinkAbout20130918 Ver 5_USACE Correspondence_20150327Wanucha, Dave
From: Bailey, David E SAW <David.E.Bailey2@usace.army.mil>
Sent: Friday, March 27, 2015 1:26 PM
To: Wanucha, Dave
Subject: RE: [EXTERNAL] U-2525B Mitigation Site 2(UNCLASSIFIED)
Classification: UNCLASSIFIED
Caveats: NONE
Dave,
Thanks for the email and itemized thoughts. I agree with all of them and I certainly agree that they are reasonable
"conditions" prior to releasing water. I spoke with others in my office and they confirmed that the Corps has, on a case-
by-case basis, allowed water release into mitigation channels prior to full veg cover. However, they also agreed that the
issues you mentioned should be addressed/corrected prior to doing so. My only suggestion is that, once they have
fulfilled the "conditions" below, that they request a field visit and/or send documentation pictures prior to getting our
explicit approval. Thanks for your efforts, and please let me know if you have any questions or concerns.
-Dave Bailey
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Phone: (919) 554-4884, Ext. 30.
Fax: (919) 562-0421
Email: David.E.Bailey2@usace.army.mil
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we
continue to do so, please complete the Customer Satisfaction Survey located at http://re�ulatory.usacesurvey.com/.
-----Original Message-----
From: Wanucha, Dave [mailto:dave.wanucha@ncdenr.�ov]
Sent: Friday, March 27, 2015 12:20 PM
To: Bailey, David E SAW
Subject: [EXTERNAL] U-2525B Mitigation Site 2
H i Dave,
Some thoughts on what we observed yesterday morning regarding Mitigation Site 2 on U-2525B-
DWR is ok with returning the stream to its new channel but I think a couple of items need to be addressed by DOT first.
They obviously need to dewater the most downstream portion or the mitigation site and reseed matted area;
* The channel structure you pointed out needs to be leveled so that flow is maintained within the center of the
structure; and,
* Upstream erosion and sediment erosion control measures need to be improved to reduce downstream turbidity
and potential sediment discharges. I will coordinate with Barry and Jerry, but drainage ditches and slopes near the
Huffine Mill Road area (hill slopes, drainage channels, V-ditch, etc) all need to be shored up in some way (core fiber
matted, mulched, permanently seeded).
Let me know what else you might add to improve the situation. I think it is within reason to request the above work
prior to returning the stream to its new channel. Let me know your thoughts and I will touch base with Byron after I
hear from you. Thanks.
Dave W
Dave Wanucha
NC DENR Winston Salem Region Office
NC Division of Water Resources
Transportation Permitting Unit
450 W. Hanes Mill Rd, Suite 300
Winston-Salem, NC 27105
Cell (336) 403-5655
Office (336) 776-9703
Dave.Wanucha@ncdenr.�ov <mailto:Dave.Wanucha@ncdenr
E-mail correspondence to and from this address may be subject
to the North Carolina Public Records Law and may be disclosed to third parties.
Classification: UNCLASSIFIED
Caveats: NONE
�