SEDIMEIkI'I'A'I ION INSPECTION REPORT
Dear Sir or Madam:
RECEIVED
FEB 21 2023
Public Service Dept.
Enclosed is a copy of the inspection report, which was prepared following an
onsite inspection of the referenced project. This report is intended to provide you
with information concerning the status of the project as it relates to compliance with
the North Carolina Sedimentation Pollution Act of 1973.
Please review this report carefully, as it may contain corrective actions needed
or comments, which will assist you in meeting the required standards of the Act.
It is our desire that any and all possible problems be discussed and resolved at
the earliest possible time. To facilitate this effort, please contact me or the named
inspector at the address shown on the inspection report if you have any questions.
Sincerely,
Tamera plin, PE, CPESC
Regional Engineer
Land Quality Section
Enclosure: Sedimentation Inspection Report
Norlh Carofina Dzpaftenl of En0mri nenlal 0uaiity / Division of Energy, Minerals L rand Resources
nslon•Sz[eno Regional Orrice! 450 West Hanes Mill Road, Suffe 300 / >Mnslon.Saforn, North Carotina V105
(336) 776-9800
North Carolina Department of Environmental Quality
Land Resources: 450 W. Hanes Mill Road, Suite 300, Winston-Salem, NC 27105
(336) 776-9800
County: Guilford Project: Riverdale Sewer Lift Station West Force Main
Person financially responsible: City of High Point
Address: P.O. Box 230, High Point, NC 27261
1. Pro_lect Location: 5899 Riverdale Dr., High Point
Pictures: No
2. Weather and soil conditions: 60's, Clear, Workable
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes
5. Violations:
River basin: Cape Fear
Project #: GUILF-2021-001
Initial inspection: No
If no, check violations below:
6. Is the site in compliance with NPDES Permit NCG010000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name):
Inspection report: Sent Report
9. Corrective action needed:
Title:
Date given/sent: February 17, 2023
10. Comments: Permanent ground cover sufficient to restrain erosion has been established. No additional
self -monitoring or self -inspections are required. Project is in compliance and released under
the SPCA, Termination of coverage under the NPDES General Stormwater Permit for
Construction Activities (NCGO1) must be requested by the permittee via a Notice of
Termination (NOT). The NOT is available at:
https://edocs.deq.nc.gov/Forms/NCGO 1-Termination. Please note that this correspondence
must be uploaded as part of completing the NOT process.
Reported by: Kimberly Turney
Date of inspection: February 14, 2023 Time arriving on site: 8:00ANI Time leaving site: 8:30 AM