HomeMy WebLinkAboutSWA000187_Construction Sequence_20230306Circle K — HSD Addition 2723997 Stedman NC
Construction Sequence:
Phase I:
1. OWNER/DEVELOPER/CONTRACTOR SHALL OBTAIN A COPY OF THE APPROVED EROSION
CONTROL PLAN AND MAINTAIN A COPY OF THE PLAN ON SITE THROUGHOUT
DURATION OF CONSTRUCTION. OBTAIN CERTIFICATE OF COVERAGE BEFORE INITIATING
LAND DISTURBANCE.
2. OWNER/CONTRACTOR SHALL NOTIFY NCDEQ DEMLR (FAYETTEVILLE, NC) AT (910) 433-
3300 A MINIMUM OF 72 HOURS BEFORE START OF CONSTRUCTION ON EACH PHASE.
3. ONLY CLEAR/GRADE ENOUGH TO INSTALL SEDIMENT CONTROL DEVICES AS SHOWN IN
PHASE I.
4. INSTALL PERMANENT DRIVEWAY PIPE AND CONSTRUCTION ENTRANCE AS INDICATED
ON PLAN. INSTALL SILT FENCE AND SILT FENCE OUTLETS AROUND THE PERIMETER OF
THE SITE. DISTURB ONLY THE AREAS NECESSARY FOR INSTALLATION.
5. ADJUST EROSION AND SEDIMENT CONTROL MEASURES AS NECESSARY FOR PROPER
OPERATION. INSTALL ADDITIONAL EROSION CONTROL MEASURES IF DETERMINED
NECESSARY BY INSPECTOR.
6. INSPECT ALL EROSION CONTROL DEVICES AFTER EVERY RAINFALL EVENT AND AT LEAST
ONCE PER WEEK. REPAIR AND CLEAN OUT AS REQUIRED.
7. NOTIFY NCDEQ DEMLR (FAYETTEVILLE, NC) AT (910) 433-3300 FOR AN INSPECTION
AFTER THIS IS COMPLETED.
8. PROCEED TO PHASE 2 OF THE EROSION CONTROL SEQUENCE WHEN PHASE 1
MEASURES HAVE BEEN COMPLETED, INSPECTED, AND APPROVED.
Phase II:
1. MAINTAIN ALL EXISTING EROSION CONTROL FEATURES PREVIOUSLY CONSTRUCTED
AND ASSOCIATED WITH PHASE 2 EROSION CONTROL.
2. CONTINUE BRINGING FILL INTO THE SITE. IMPORTED MATERIAL WILL REQUIRE A
PERMITTED SITE APPROVAL BEFORE THIS PROCESS BEGINS. ALL FILL SHALL BE BROUGHT
INTO THE SITE AND EVENLY SPREAD OUT THROUGH THE SITE AS SHOWN IN LIFTS OF NO
MORE THAT 1.0' AT A TIME. FILL SHALL BE ROLL COMPACTED BY A DOZER OR
EQUIVALENT AS IT IS PLACED.
3. INSTALL SITE IMPROVEMENTS, UTILITY SERVICES, SIDEWALKS AND DRIVES AS SHOWN
ON THE APPROVED PLANS. ALL OPEN TRENCHES FOR UTILITY AND STORMWATER
INSTALLATION SHALL BE PROTECTED FROM SEDIMENTATION BY PILING EXCAVATED
MATERIAL ON THE UPHILL SIDE OF EXCAVATION.
4. INSTALL ADEQUATE EROSION AND SEDIMENT CONTROL MEASURES AND/OR INCREASE
MAINTENANCE FREQUENCY WHERE APPROVED MEASURES FAIL TO PREVENT
ACCELERATED EROSION, OFF -SITE SEDIMENTATION, OR REPETITIVE NON-COMPLIANCE
ISSUES. ALL MEASURES MUST BE INSTALLED PER PLAN DETAIL. ENSURE CONSTRUCTION
TRAFFIC IS LIMITED TO THE CONSTRUCTION ENTRANCE ONLY.
L11115c]0i111►1oxciIT/II'Al 00Fil102aa'kTi1T/1971107_Viti]Iti]yiym
• FOR ALL AREAS OF MODERATE AND/OR STEEP SLOPES, PROVIDE TEMPORARY
GROUND COVER IF THE SLOPE HAS NOT BEEN DISTURBED FOR A PERIOD OF
FOURTEEN (14) DAYS. SLOPES GREATER THAN 3:1 REQUIRE GROUND COVER IN 7
DAYS.
• PROVIDE GROUND COVER SUFFICIENT TO RESTRAIN EROSION ON ANY PORTION
OF THE SITE UPON WHICH FURTHER LAND -DISTURBING ACTIVITY IS NOT BEING
UNDERTAKEN WITHIN FOURTEEN (14) CALENDAR DAYS OF TEMPORARILY OR
PERMANETLY SUSPENDING LAND DISTURBING ACTIVITY.
• ESTABLISH PERMANENT GROUND COVER SUFFICIENT TO RESTRAIN EROSION
WITHIN FOURTEEN (14) CALENDAR DAYS FOLLOWING COMPLETION OF
CONSTRUCTION OR DEVELOPMENT AND/OR PRIOR TO FINAL INSPECTION.
8. INSTALL CURB & GUTTER AND GRAVEL BASE.
9. MODIFICATIONS TO THE APPROVED AND PERMITTED PLANS SHALL BE APPROVED BY
EROSION CONTROL INSPECTIONS PRIOR TO REMOVAL OR INSTALLATION. CONTACT THE
EROSION CONTROL INSPECTOR TO OBTAIN SIGN -OFF ON THE PLANS.
10. MAINTAIN ALL EROSION AND SEDIMENT CONTROL MEASURES IN GOOD WORKING
ORDER. SILT FENCE, INLET PROTECTION, AND OTHER SIMILAR MEASURES MUST BE
CLEANED OUT BEFORE THEY ARE HALF FULL. CLOGGED STONE FILTERS MUST BE
REFRESHED/REPLACED. SILT FENCE CANNOT HAVE HOLES OR TEARS.
11. AT A MINIMUM OF SEVEN (7) DAYS PRIOR TO SCHEDULING THE STORMWATER FINAL
INSPECTION, SUBMIT ANY REQUIRED PAPERWORK TO THE EROSION CONTROL
INSPECTORS FOR APPROVAL. FAILURE TO DO SO WILL PREVENT A CERTIFICATE OF
OCCUPANCY FROM BEING ISSUED.
12. ONCE THE STORMWATER FINAL INSPECTION IS APPROVED, CLOSE THE GRADING
PERMIT AND OBTAIN A NOTICE OF TERMINATION.
13. NO FUTURE DEVELOPMENT IS PLANNED FOR THE PROJECT AT THIS TIME.