Has this project met the requirements for acceptance in to the review process? *
Yes
No
Is this project a public transportation project?*
Yes No
Change only If needed.
Pre -Filing Meeting Date Request was submitted on:
1/3/2023
BIMS # Assigned * Version#*
20230319 1
Is a payment required for this project? *
No payment required
Fee received
Fee needed - send electronic notification
Select Project Reviewer*
Andrew Pitner:andrew.pitner@ncdenr.gov
Information for Initial Review
la. Name of project:
COURTESY COPY King Canary Brewery
la. Who is the Primary Contact?*
Wade Brown
Reviewing Office*
Mooresville Regional Office - (704) 663-1699
1b. Primary Contact Email: * lc. Primary Contact Phone: *
Hgserviceswb@gmail.com (704)402-2656
Date Submitted
3/1/2023
Nearest Body of Water
Lake Norman
Basin
Catawba
Water Classification
B
Site Coordinates
Latitude:
35.57270940000001
Longitude:
-80.86894819999999
A. Processing Information O
Is this project connected with ARPA funding?
Yes No
County (or Counties) where the project is located:
Iredell
Is this a NCDMS Project
Yes No
Is this project a public transportation project?*
Yes No
la. Type(s) of approval sought from the Corps:
Section 404 Permit (wetlands, streams and waters, Clean Water Act)
Section 10 Permit (navigable waters, tidal waters, Rivers and Harbors Act)
Has this PCN previously been submitted?*
Yes
No
1b. What type(s) of permit(s) do you wish to seek authorization?
Nationwide Permit (NWP)
Regional General Permit (RGP)
Standard (IP)
lc. Has the NWP or GP number been verified by the Corps?
Yes No
Are you a federal applicant? *
Yes No
If yes, please provide a statement concerning compliance with the Coastal Zone Management Act. *
NA
Nationwide Permit (NWP) Number:
NWP Numbers (for multiple NWPS):
ld. Type(s) of approval sought from the DWR:
401 Water Quality Certification - Regular
Non-404 Jurisdictional General Permit
Individual 401 Water Quality Certification
le. Is this notification solely for the record because written approval is not required?
For the record only for DWR 401 Certification:
For the record only for Corps Permit:
1f. Is this an after -the -fact permit application?*
Yes No
lg. Is payment into a mitigation bank or in -lieu fee program proposed for mitigation of impacts?
Yes No
lg. Is payment into a mitigation bank or in -lieu fee program proposed for mitigation of impacts?
Yes No
lh. Is the project located in any of NC's twenty coastal counties?
Yes No
1j. Is the project located in a designated trout watershed?
Yes No
B. Applicant Information
ld. Who is applying for the permit?
Owner Applicant (other than owner)
le. Is there an Agent/Consultant for this project? *
Yes No
2. Owner Information
2a. Name(s) on recorded deed:
Goose+Loon Holdings LLC
2b. Deed book and page no.:
2476/1224
2c. Contact Person:
Andrea Gravina
401 Water Quality Certification - Express
Riparian Buffer Authorization
Yes No
Yes No
2d. Address
Street Address
562 Williamson rd.
Address Line 2
City State / Province / Region
Mooresville NC
Postal / Zip Code Country
28117 USA
2e. Telephone Number: 2f. Fax Number:
(954)464-5212
2g. Email Address:*
Andreamgravina@gmail.com
3. Applicant Information (if different from owner)
3a. Name:
Wade Brown
3b. Business Name:
HomeGrown Services L.L.C.
3c. Address
Street Address
938 Hampton pl.
Address Line 2
City State / Province / Region
Mooresville NC
Postal / Zip Code Country
28115 USA
3d. Telephone Number: 3e. Fax Number:
(704)402-2656
3f. Email Address: *
Hgserviceswb@gmail.com
C. Project Information and Prior Project History
1. Project Information
1b. Subdivision name:
(if appropriate)
Idlewood harbour
lc. Nearest municipality / town:
Mooresville
2. Project Identification
2a. Property Identification Number:
4646475818.000
2b. Property size:
0.9
2c. Project Address
Street Address
562 Williamson rd.
Address Line 2
City State / Province / Region
Mooresville NC
Postal / Zip Code Country
28117
3. Surface Waters
3a. Name of the nearest body of water to proposed project: *
Lake Norman
3b. Water Resources Classification of nearest receiving water: *
B
3c. What river basin(s) is your project located in?*
Catawba
3d. Please provide the 12-digit HUC in which the project is located.
030501011203
4. Project Description and History
4a. Describe the existing conditions on the site and the general land use in the vicinity of the project at the time of this application: *
Shoreline declining due to run off and no shoreline vegetation. Access to dock is being jeopardized.
4b. Have Corps permits or DWR certifications been obtained for this project (including all prior phases) in the past? *
Yes No Unknown
4b(2). Is Any Portion of the Work Already Complete?*
Yes No
If yes, describe the completed work.
4c. List of Other Certificates or Approvals/Denials received from other Federal, State, or Local Agencies for Work Described in This Application. not related to the 404 or 401.
4f. List the total estimated acreage of all existing wetlands on the property:
4g. List the total estimated linear feet of all existing streams on the property:
4h. Explain the purpose of the proposed project:*
shoreline deterioration is making for difficult access to dock abutment.
4i. Describe the overall project in detail, including indirect impacts and the type of equipment to be used: *
Silt fence along shore line above water ,Rip rap class 1-2 will be installed on woven geotextile fabric along shoreline. Skid steer for moving rock and excavator for placing rock. Sheets will
be placed under machines for low impact.
4k. Will this activity involve dredging in wetlands or waters? *
Yes No
If yes, Describe the type of dredging, the composition of the dredged material and the location of disposal area.
5. Jurisdictional Determinations
5a. Have the wetlands or streams been delineated on the property or proposed impact areas? *
Yes No
Comments:
5b. If the Corps made a jurisdictional determination, what type of determination was made?*
Preliminary Approved Not Verified Unknown N/A
Corps AID Number:
5c. If 5a is yes, who delineated the jurisdictional areas?
Name (if known):
Agency/Consultant Company:
Other:
6. Future Project Plans
6a. Is this a phased project? *
Yes No
Unknown
Are any other NWP(s), regional general permit(s), or individual permits(s) used, or intended to be used, to authorize any part of the proposed project or related activity?
7. Addresses of Adjoining Property Owners, Lessees, Etc., Whose Property Adjoins the Waterbody (if more than can be entered here, please attach a supplemental list)
8. Scheduling of Activity:
D. Proposed Impacts Inventory
1. Impacts Summary
la. Where are the impacts associated with your project? (check all that apply):
Wetlands
4 Open Waters
Streams -tributaries
Pond Construction
2h.Type(s) of Material Being Discharged and the Amount of Each Type in Cubic Yards:
Rip rap 30cu.yds
3i. Total cubic yard stream impacts: *
4. Open Water Impacts
4 Buffers
4a. Site #
NA
4a1. Impact Reason
Shoreline stabilization
4b. Impact type
P
4c. Name of waterbody
Catawba
4d. Activity type
Dock & Pier
4e. Waterbody type
Lake
4f. Impact area
0.00
4g. Total temporary open water Impacts:
0.00
4g. Total open water impacts:
0.00
4g. Total cubic yard open water impacts: *
4h. Comments:
6. Buffer Impacts (for DWR)
6a. Project is in which protect basin(s)?
Check all that apply.
Neuse
Catawba
Goose Creek
Other
4g. Total permanent open water impacts:
0.00
Tar -Pamlico
Randleman
Jordan Lake
6b. Impact Type
6c. Per or Temp
6d. Stream name
6e. Buffer mitigation required?
6f. Zone 1 impact
6g. Zone 2 impact
Shoreline stabilization
P
Catawba
No
300
0
6h. Total buffer impacts:
Zone 1
Total Temporary impacts: 0 00
Zone 1
Total Permanent impacts: 300.00 0.00
Zone 2
0.00
Zone 2
Zone 1 Zone 2
Total combined buffer impacts: 300.00 0.00
6i. Comments:
E. Impact Justification and Mitigation
1. Avoidance and Minimization
la. Specifically describe measures taken to avoid or minimize the proposed impacts in designing the project:
Silt fence installed from bank edge out to water back to bank edge
1b. Specifically describe measures taken to avoid or minimize the proposed impacts through construction techniques:
Geotextile fabric layed then rip rap classl-2 will be installed on top fabric
2. Compensatory Mitigation for Impacts to Waters of the U.S. or Waters of the State
2a. Does the project require Compensatory Mitigation for impacts to Waters of the U.S. or Waters of the State?
Yes No
2b. If this project DOES NOT require Compensatory Mitigation, explain why:
Will not be disturbing area around that is in shoreline area
F. Stormwater Management and Diffuse Flow Plan (required by DWR)
1. Diffuse Flow Plan
la. Does the project include or is it adjacent to protected riparian buffers identified within one of the NC Riparian Buffer Protection Rules?
Yes No
What type of SCM are you providing?
Level Spreader
Vegetated Conveyance (lower SHWT)
Wetland Swale (higher SHWT)
Other SCM that removes minimum 30% nitrogen
Proposed project will not create concentrated stormwater flow through the buffer
2. Stormwater Management Plan
2a. Is this a NCDOT project subject to compliance with NCDOT's Individual NPDES permit NCS000250? *
Yes No
2b. Does this project meet the requirements for low density projects as defined in 15A NCAC 02H .1003(2)?
Yes No
Comments:
G. Supplementary Information
1. Environmental Documentation
la. Does the project involve an expenditure of public (federal/state/local) funds or the use of public (federal/state) land? *
Yes No
2. Violations (DWR Requirement)
2a. Is the site in violation of DWR Water Quality Certification Rules (15A NCAC 2H .0500), Isolated Wetland Rules (15A NCAC 2H .1300), or DWR Surface Water or Wetland Standards or
Riparian Buffer Rules (15A NCAC 2B .0200)?*
Yes No
3. Cumulative Impacts (DWR Requirement)
3a. Will this project result in additional development, which could impact nearby downstream water quality? *
Yes No
3b. If you answered "no," provide a short narrative description.
4. Sewage Disposal (DWR Requirement)
4a. Is sewage disposal required by DWR for this project? *
Yes No N/A
5. Endangered Species and Designated Critical Habitat (Corps Requirement)
5a. Will this project occur in or near an area with federally protected species or habitat?*
Yes No
5b. Have you checked with the USFWS concerning Endangered Species Act impacts?*
Yes No
5d. Is another Federal agency involved?*
Yes
5e. Is this a DOT project located within Division's 1-8?
Yes No
No Unknown
5f. Will you cut any trees in order to conduct the work in waters of the U.S.?
Yes No
5g. Does this project involve bridge maintenance or removal?
Yes No
5h. Does this project involve the construction/installation of a wind turbine(s)?*
Yes No
5i. Does this project involve (1) blasting, and/or (2) other percussive activities that will be conducted by machines, such as jackhammers, mechanized pile drivers, etc.?
Yes No
5j. What data sources did you use to determine whether your site would impact Endangered Species or Designated Critical Habitat?
The area which is intended to be worked upon is empty no vegetation
6. Essential Fish Habitat (Corps Requirement)
6a. Will this project occur in or near an area designated as an Essential Fish Habitat?*
Yes No
6b. What data sources did you use to determine whether your site would impact an Essential Fish Habitat? *
Soil exsposed and no structure
7. Historic or Prehistoric Cultural Resources (Corps Requirement)
7a. Will this project occur in or near an area that the state, federal or tribal governments have designated as having historic or cultural preservation status? *
Yes No
7b. What data sources did you use to determine whether your site would impact historic or archeological resources? *
Location pre established
8. Flood Zone Designation (Corps Requirement)
8a. Will this project occur in a FEMA-designated 100-year floodplain? *
Yes No
8c. What source(s) did you use to make the floodplain determination? *
Map provided
Miscellaneous
Please use the space below to attach all required documentation or any additional information you feel is helpful for application review. Documents should be combined into one file when
possible, with a Cover Letter, Table of Contents, and a Cover Sheet for each Section preferred.
Click the upload button or drag and drop files here to attach document
File must be PDF or KMZ
Comments
Signature O
By checking the box and signing below, I certify that:
• The project proponent hereby certifies that all information contained herein is true, accurate, and complete to the best of my knowledge and belief'; and
• The project proponent hereby requests that the certifying authority review and take action on this CWA 401 certification request within the applicable reasonable period of time.
• I have given true, accurate, and complete information on this form;
I agree that submission of this PCN form is a "transaction" subject to Chapter 66, Article 40 of the NC General Statutes (the "Uniform Electronic Transactions Act");
I agree to conduct this transaction by electronic means pursuant to Chapter 66, Article 40 of the NC General Statutes (the "Uniform Electronic Transactions Act");
I understand that an electronic signature has the same legal effect and can be enforced in the same way as a written signature; AND
I intend to electronically sign and submit the PCN form.
Full Name:
Wade P Brown
Signature
Date
3/1/2023