HomeMy WebLinkAboutGamewell 0.2 General Project Notes & Specifications. Revised Feb 27 2023REVISIONS:
7
S
A
M
U
E
L
A
S
H
E
D
R
I
V
E
AS
H
E
V
I
L
L
E
,
N
C
2
8
8
0
5
91
9
-
6
0
0
-
4
7
9
0
NC
F
I
R
M
L
I
C
E
N
S
E
N
O
.
:
P
-
1
9
3
2
AB
I
N
G
D
O
N
C
R
E
E
K
S
T
R
E
A
M
R
E
S
T
O
R
A
T
I
O
N
GA
M
E
W
E
L
L
P
A
R
K
GA
M
E
W
E
L
L
,
CA
L
D
W
E
L
L
C
O
U
N
T
Y
,
NO
R
T
H
C
A
R
O
L
I
N
A
SHEET NUMBER
DATE:
DRAWN BY:
CHECKED BY:
APPROVED BY:
JE PIN:
OF
SCALE:
PROGRESS DRAWING
DO NOT USE FOR
CONSTRUCTION
1113
---
MJH
MJH
02/27/2023
240.2
NOT TO SCALE
GE
N
E
R
A
L
P
R
O
J
E
C
T
N
O
T
E
S
&
S
P
E
C
I
F
I
C
A
T
I
O
N
S
GENERAL PROJECT NOTES AND SPECIFICATIONS
1.DEFINITIONS:
1.1.CONSTRUCTION DOCUMENTS: THE CONTRACT AND APPLICABLE DRAWINGS, DETAILS, SPECIFICATIONS,
PERMIT(S), AND/OR ANY OTHER DOCUMENTS (MEETING MINUTES, PUNCH LISTS, BID TABS, ETC.) FOR
COMPLETE INFORMATION ABOUT THE REQUIRED WORK. ANY ONE OF THESE PARTS OF THE MAY NOT
CONTAIN ALL OF THE INFORMATION REQUIRED TO COMPLETE THE PROJECT WORK.
1.2.LANDOWNER: TOWN OF GAMEWELL
1.3.PROJECT MANAGER: PROJECT MANAGER
1.4.ENGINEER: JENNINGS ENVIRONMENTAL PLLC
1.5.SURVEYOR: PILOT SE, INC
2.THE WORK ON THIS PROJECT SHALL ADHERE TO THE FOLLOWING SPECIFICATIONS, STANDARDS AND/OR
REGULATIONS:
2.1.NC DEMLR'S "EROSION AND SEDIMENT CONTROL PLANNING AND DESIGN MANUAL" (2013)
2.2.NC DEMLR'S CONSTRUCTION GENERAL PERMIT NUMBER NCG01000
2.3.GENERAL, REGIONAL AND SPECIAL CONDITIONS OF USACE'S 404 NATIONWIDE PERMIT NUMBER 27
2.4.GENERAL AND SPECIAL CONDITIONS OF NCDWR'S 401 WATER QUALITY CERTIFICATION 4134
2.5.THE CONSTRUCTION DOCUMENTS
3.NOT ALL EXISTING UTILITIES ARE SHOWN. SOME LOCATIONS MAY BE APPROXIMATE. THE CONTRACTOR IS
RESPONSIBLE FOR ALL UTILITY LOCATION AND COORDINATION. ANY UTILITIES SHOWN ON THE
CONSTRUCTION DOCUMENTS ARE FOR INFORMATIONAL PURPOSES ONLY AND IN NO WAY RELIEVES THE
CONTRACTOR FROM COORDINATING, VERIFYING AND PROTECTING EXISTING UTILITIES.
4.ALL UTILITIES SHALL BE PROTECTED AND REMAIN ACTIVE UNLESS OTHERWISE NOTED.
5.THE CONTRACTOR IS RESPONSIBLE FOR THE PROJECT AREA UNTIL COMPLETION AND FINAL ACCEPTANCE BY
THE ENGINEER AND PROJECT OWNER. THE CONTRACTOR SHALL CONFINE ALL ACTIVITIES, INCLUDING
EQUIPMENT STORAGE, TO THE LIMITS OF DISTURBANCE, STAGING AREAS, AND DESIGNATED CONSTRUCTION
ACCESS POINTS.
6.THE MANNER IN WHICH THE CONTRACTOR DEALS WITH PEOPLE AND THEIR PROPERTIES WHILE PERFORMING
THIS WORK IS EXTREMELY IMPORTANT. THEREFORE, THE CONTRACTOR AND THE CONTRACTOR'S
REPRESENTATIVES SHALL MANIFEST A SPIRIT OF FRIENDLINESS AND COOPERATION WHEN DEALING WITH
PROPERTY OWNERS AND THE GENERAL PUBLIC WHILE PERFORMING WORK ON THE SITE.
7.EXTREME CARE AND DILIGENCE SHALL BE EXERCISED BY THE CONTRACTOR TO ASSURE THE SAFETY OF
PERSONS, ANIMALS, AND PROPERTY. IF AT ANY TIME THE OWNER OR ENGINEER DETERMINES THAT THE
CONTRACTOR'S METHODS OR EQUIPMENT ARE INADEQUATE FOR SECURING THE SAFETY OF THE
CONTRACTOR'S EMPLOYEES OR THE PUBLIC, THE DESIGNATED REPRESENTATIVE MAY DIRECT THE
CONTRACTOR TO TAKE SPECIFIC ACTIONS TO ENSURE SAFETY. THE CONTRACTOR SHALL IMPROVE METHODS
AS DEEMED APPROPRIATE BY THE DESIGNATED REPRESENTATIVE WITHOUT ADDITIONAL COST TO THE
PROJECT OWNER, SO AS TO ASSURE COMPLIANCE WITH SAFETY CONCERNS. FAILURE OF THE DESIGNATED
REPRESENTATIVE TO MAKE THIS DEMAND SHALL NOT RELIEVE THE CONTRACTOR OF ANY OBLIGATION TO
ENSURE THE SAFE CONDUCT OF ITS WORK.
8.THE CONTRACTOR SHALL MAINTAIN ALL LIGHTS, GUARDS, SIGNS, TEMPORARY PASSAGES, OR OTHER
PRECAUTIONS NECESSARY FOR THE SAFETY OF ALL PERSONS. THE CONTRACTOR SHALL ABIDE BY ALL SAFETY
RULES AND CONSTRUCTION CONDITIONS REQUIRED BY GOVERNMENTAL AUTHORITIES AND OTHER ENTITIES,
INCLUDING RAILROADS, SO THE PUBLIC IS SAFEGUARDED FROM ACCIDENTS AND DELAYS. GUARDS AND FLAGS
REQUIRED BY GOVERNMENTAL OR RAILROAD AUTHORITIES SHALL BE PROVIDED AT THE CONTRACTOR'S
EXPENSE, UNLESS DIRECTED OTHERWISE BY THE DESIGNATED REPRESENTATIVE. CONTRACTOR SHALL AT NO
TIME COMPROMISE EITHER SAFETY OR ENVIRONMENTAL REQUIREMENTS.
9.THE CONTRACTOR SHALL ONLY USE ACCESS PATHS AND STAGING AREAS SHOWN ON THE DRAWINGS. ANY
ALTERNATE ACCESS PLANNED BY THE CONTRACTOR SHALL BE APPROVED BY THE ENGINEER AND PROJECT
OWNER PRIOR TO USE.
10.NO NON-PERMITTED FILL IN WETLANDS MAY OCCUR. ALL EXCESS SOILS FROM STABILIZATION AND GRADING
WORK SHALL BE PLACED IN DESIGNATED AREAS ON THE SITE.
11.SITE SHOULD BE “STORM READY” AT THE END OF EACH WORK DAY AND WORK WEEK.
TOPOGRAPHIC NOTES AND SPECIFICATIONS
12.HORIZONTAL DATUM IS NAD83(2011) & VERTICAL DATUM IS NAVD88. ALL COORDINATES ARE BASED ON
NAD83(2011) AND ALL ELEVATIONS ARE BASED ON NAVD88.
13.A DETAILED TOPOGRAPHIC AND TREE SURVEY OF THE WORK AREA WAS COMPLETED BY PILOT SE INC. IN
MARCH 2022.
14.THE DESIGN ELEVATIONS AND GRADES SHOWN IN THE DRAWINGS ARE BASED ON THE EXISTING GROUND
SURFACE FROM THE MARCH 2022 SURVEY FROM WHICH ALL COMPUTATIONS OF CUT AND FILL ARE BASED.
DISCREPANCIES BETWEEN THE SURVEYED EXITING GROUND SURFACE AND FIELD CONDITIONS AT THE TIME OF
CONSTRUCTION CAN RESULT IN VARIATIONS OF TOTAL EXCAVATED QUANTITIES. THESE VARIATIONS SHALL BE
CONSIDERED INCIDENTAL TO CONSTRUCTION.
STREAM RESTORATION NOTES AND SPECIFICATIONS
15.FIELD CONDITIONS MAY REQUIRE ADAPTATION OF THE DESIGN AND/OR DETAILS PROVIDED IN THE
DRAWINGS. MINOR VARIATION(S) OR ADAPTATION(S) OF THE PROPOSED WORK SHOWN IN THE DRAWINGS
AND DETAILS ARE CONSIDERED INCIDENTAL TO THE WORK. THE ENGINEER WILL WORK WITH THE
CONTRACTOR TO ADDRESS ANY FIELD CHANGES.
16.IN-STREAM ROCK STRUCTURES MAY BE SUBSTITUTED WITH WOOD STRUCTURES WITH WRITTEN APPROVAL
FROM THE ENGINEER.
17.THE CONTRACTOR SHALL MARK THE LOCATIONS OF BANK STABILIZATION STRUCTURES USING SURVEY GRADE
GPS EQUIPMENT FOR REVIEW BY THE ENGINEER BEFORE BEGINNING EXCAVATION AND GRADING.
18.CONTRACTOR SHALL MINIMIZE, TO THE MAXIMUM EXTENT POSSIBLE, IMPACTS TO ADJACENT SIGNIFICANT
TREES.
19.CONTRACTOR SHALL USE AN EXCAVATOR WITH A HYDRAULIC THUMB TO INSTALL BANK STABILIZATION
STRUCTURES.
20.DESIGN ELEVATIONS SHALL BE CONSTRUCTED WITHIN 0.1' (VERTICAL). WIDTHS AND DEPTHS MUST FALL
WITHIN RANGES SHOWN IN THE DRAWINGS AND DETAILS.
21.IF THE EXISTING GROUND IS LESS THAN 0.2' HIGHER THAN THE PROPOSED BANKFULL ELEVATION, IT IS NOT
NECESSARY TO EXCAVATE TO THE PROPOSED ELEVATIONS AND GRADES IN THE CONSTRUCTION DOCUMENTS.
22.BANK STABILIZATION STRUCTURES SHALL BE INSTALLED AS SHOWN IN THE DRAWINGS AND DETAILS. ALL
STRUCTURES SHALL BE FINISHED TO A SMOOTH SURFACE IN ACCORDANCE WITH THE LINES, GRADES AND
ELEVATIONS SHOWN IN THE DRAWINGS AND DETAILS. THE FINISHED STRUCTURE SLOPES AND GRADES SHALL
BE WITHIN 0.1' OF DESIGN ELEVATIONS.
23.AFTER THE STRUCTURE IS COMPLETE AND NORMAL FLOW IS RESTORED TO THE CHANNEL, SOME
ADJUSTMENT TO THE STRUCTURE OR ADDITIONAL STABILIZATION MEASURE MAY BE NECESSARY TO ACHIEVE
THE DESIRED FUNCTION.
24.THE GRADED RIVER BANKS SHALL BE STABILIZED AS SOON AS POSSIBLE BY TEMPORARY AND PERMANENT
SEEDING, ADDING STRAW MULCH TO BARE SOIL AND INSTALLING EROSION CONTROL MATTING AS SHOWN IN
THE DRAWINGS AND DETAILS. PRIOR TO INSTALLING THE EROSION CONTROL MATTING, PREPARE THE SOIL
SURFACE BY LOOSENING 3 - 6” OF SOIL OR APPLYING 3 - 6” OF TOPSOIL TO THE DESIGN ELEVATIONS AND
APPLY TEMPORARY AND PERMANENT SEED AND THEN STRAW MULCH. SEED SHALL BE BROADCAST EVENLY
OVER THE AREA USING A BROADCAST SPREADER PRIOR TO COVERING WITH THE EROSION CONTROL
MATTING. THE MATTING SHALL BE ROLLED OUT IN THE DIRECTION OF ANTICIPATED RUNOFF. INSTALL
MATTING IN ACCORDANCE WITH THE DETAIL INCLUDED IN THE DRAWINGS. MATTING USED FOR
STREAMBANK STABILIZATION MUST BE CERTIFIED WEED-FREE STRAW OR OTHER NATURAL WEED-FREE /
NON-PROPAGATING VEGETATIVE MATERIALS. REWORKING OF AREAS THAT DO NOT ESTABLISH VEGETATION
OR BECOME UNSTABLE SHALL BE NECESSARY IN THE MATTING SEPARATES FROM THE SOIL.
25.TOPSOIL SHALL BE REMOVED FROM EXCAVATION AND FILL AREAS PRIOR TO EXCAVATION AND GRADING AND
RE-APPLIED TO AREAS AFTER ROUGH GRADING IS COMPLETE. 2 - 4” OF TOPSOIL SHALL BE PLACED ON
DISTURBED AREAS TO THE ELEVATIONS AND GRADES INCLUDED IN THE DRAWINGS. EROSION AND
SEDIMENTATION CONTROL NOTES AND SPECIFICATIONS.
26.ALL CONSTRUCTION ACTIVITIES SHALL ADHERE TO THE CONDITIONS AND REQUIREMENTS OF NCDEML'S NG01
CONSTRUCTION GENERAL PERMIT.
27.ALL TREES, UTILITIES AND OTHER SITE FEATURES SHALL BE PROTECTED UNLESS MARKED FOR REMOVAL OR
RELOCATION.
28.ALL WETLANDS AND STREAMS LOCATED WITHIN 50 FEET OF THE CONSTRUCTION AREA ON THE PROJECT SITE
SHALL BE CLEARLY MARKED (EXAMPLE- ORANGE FABRIC FENCING) PRIOR TO ANY LAND DISTURBING
ACTIVITIES AND MUST BE MAINTAINED ON THE PROPERTY UNTIL THE PROJECT PHASE IS COMPLETED [15A
NCAC 02H .0506 (B)(2)].
29.THE CONTRACTOR SHALL USED A STANDARD CONSTRUCTION ENTRANCE AT ALL SITE ACCESS POINTS TO
PREVENT SEDIMENT FROM BEING TRACKED ONTO PUBLIC ROADS.
30.THE CONTRACTOR SHALL USED TEMPORARY SILT FENCE ALONG THE DOWNSLOPE SIDE OF ALL STAGING
AREAS AND TEMPORARY STOCK PILE AREAS.
31.THE TURBIDITY STANDARD OF 50 NTUS (NEPHELOMETRIC TURBIDITY UNITS) SHALL NOT BE EXCEEDED AS
DESCRIBED IN 15A NCAC 02B .0200. APPROPRIATE SEDIMENT AND EROSION CONTROL PRACTICES MUST BE
USED TO MEET THIS STANDARD. [15A NCAC 02B .0211 (21)].
32.EQUIPMENT SHALL BE WELL-MAINTAINED, CLEANED PRIOR TO MOBILIZATION, AND CHECKED DAILY FOR
LEAKS OF PETROLEUM PRODUCTS. FUELING, LUBRICATION AND GENERAL EQUIPMENT MAINTENANCE
SHOULD NOT TAKE PLACE WITHIN 50 FEET OF A WATERBODY OR WETLANDS TO PREVENT CONTAMINATION
BY FUEL AND OILS. [15A NCAC 02H .0506 (B)(3) AND 15A NCAC 02B.0211(12)].
33.CONSTRUCTION SHALL BE TIMED TO OCCUR DURING TIMES OF LOW FLOW.
34.THE DESIGNER OR HIS DESIGNEE SHALL SUPERVISE THE INSTALLATION OF IN-STREAM STRUCTURES. [15A NCAC
02H .0506(B)(1) AND (2)].
35.A TEMPORARY PUMP AROUND SYSTEM SHALL BE USED TO DURING ALL STREAM RESTORATION AND
STABILIZATION WORK AS SHOWN IN THE DETAILS. TEMPORARY PUMP AROUND SYSTEM SHALL BE USED AT
PROJECT SITES WHERE THE WATERSHED SIZE IS LESS THAN 5 SQUARE MILES.
36.A TEMPORARY DIVERSION SHALL BE USED TO DURING ALL STREAM RESTORATION AND STABILIZATION WORK
AS SHOWN IN THE DETAILS.
37.THE STREAM BANKS, IN-STREAM STRUCTURES AND WORK AREA MUST BE STABILIZED AT THE END OF EACH
DAY BEFORE THE TEMPORARY IN-STREAM DIVERSIONS AND PUMP AROUNDS ARE REMOVED AND FLOW IS
RETURNED THE FULL CHANNEL.
38.EROSION CONTROL MATTING THAT INCORPORATES PLASTIC MESH AND/OR PLASTIC TWINE SHALL NOT BE
USED ALONG STREAMBANKS OR WITHIN WETLANDS. DISTURBED AREAS SHOULD BE SEEDED, MULCHED,
AND/OR MATTED AS SOON AS POSSIBLE, PREFERABLY AT THE END OF EACH WORKDAY. [15A NCAC 02B .0201]
39.IF BORROW OR WASTE MATERIAL IS REQUIRED OR GENERATED DURING GRADING OPERATIONS, AN
APPROVED EROSION AND SEDIMENT CONTROL PERMIT MUST BE SECURED FOR THE BORROW OR WASTE
MATERIAL SITE PRIOR TO INITIATION OF ANY LAND DISTURBING ACTIVITY. [15A NCAC 04B .0110].
QUANTITIES AND MATERIALS NOTES AND SPECIFICATIONS
40.THE CONTRACTOR SHALL FURNISH ALL MATERIALS NECESSARY TO COMPLETE THE PROPOSED WORK UNLESS
OTHER PROVISIONS HAVE BEEN AGREED UPON PRIOR TO CONSTRUCTION. THE CONTRACTOR SHALL DELIVER
ALL MATERIALS TO THE DESIGNATED ACCESS POINTS AND STAGING AREAS. MATERIAL QUANTITIES,
DIMENSIONS AND SIZES SHALL CONFORM TO THE NOTES AND SPECIFICATIONS PROVIDED IN THE
CONSTRUCTION DOCUMENTS. THE ENGINEER MAY INSPECT AND APPROVE ALL MATERIALS PRIOR TO
CONSTRUCTION. IF MATERIALS DO NOT MEET THE MINIMUM REQUIREMENTS SPECIFIED IN THE
CONSTRUCTION DOCUMENTS, THE ENGINEER SHALL REJECT THE MATERIALS.
41.COSTS INCURRED DUE TO PROJECT DELAYS RESULTING FROM FAILURE OF THE CONTRACTOR TO MEET THE
REQUIREMENTS OF THE CONSTRUCTION DOCUMENTS SHALL BE THE EXPENSE OF THE CONTRACTOR.
QUANTITIES LISTED ARE ESTIMATES ONLY AND SHALL BE CONFIRMED BY THE CONTRACTOR.
42.THE EROSION CONTROL MEASURES DEPICTED ON THE DRAWINGS SHALL BE INSTALLED AS NEEDED TO KEEP
ALL SEDIMENT ON SITE AND OUT OF STREAMS AND WETLANDS. ADDITIONAL EROSION CONTROL MEASURES
(ABOVE THOSE SHOWN ON THE DRAWINGS) MAY BE REQUIRED IN ORDER TO KEEP ALL SEDIMENT ON SITE
AND OUT OF STREAMS AND WETLANDS. THE CONTRACTOR SHALL OBTAIN APPROVAL FROM THE PROJECT
OWNER AND ENGINEER PRIOR TO INSTALLATION OF ADDITIONAL EROSION CONTROL MEASURES.
43.ANY ADDITIONAL GRADING OTHER THAN WHAT IS SHOWN ON THE PLANS SHALL REQUIRE PRIOR APPROVAL
FROM THE PROJECT OWNER AND ENGINEER.
44.THE USE OF ANY BRAND NAMES/MANUFACTURERS OR MODELS IS INTENDED SOLELY TO DENOTE THE
QUALITY STANDARD OF THE DESIRED PRODUCT. ANY USE OF BRAND NAMES IS NOT INTENDED TO RESTRICT
BIDDERS TO A SPECIFIC BRAND, MAKE, MANUFACTURER, OR NAME. THE BRAND NAMES / MANUFACTURERS
OF MODELS ARE INTENDED TO CONVEY THE GENERAL STYLE, TYPE, CHARACTER, AND QUALITY OF PRODUCT.
EQUIVALENT PRODUCTS WILL BE ACCEPTABLE IF THE PROJECT OWNER OR ENGINEER HAS GIVEN APPROVAL
OF THE SPECIFIC PRODUCT IN WRITING.
45.THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING AND PROVIDING STORAGE AREAS FOR
CONSTRUCTION MATERIALS AND EQUIPMENT. THE MATERIAL AND EQUIPMENT STORAGE SHALL COMPLY
WITH THE CONSTRUCTION DOCUMENTS AND ALL LOCAL, STATE AND FEDERAL REGULATIONS THROUGHOUT
THE CONSTRUCTION PERIOD. THE CONTRACTOR SHALL RESTORE THE STORAGE AREA TO ITS ORIGINAL (OR
BETTER) CONDITION UPON COMPLETION OF THE PROJECT OR UPON SUCH TIME AS DIRECTED BY THE PROJECT
OWNER AND ENGINEER. SUCH RESTORATION SHALL BE AT NO ADDITIONAL COST TO THE PROJECT OWNER.
THE CONTRACTOR SHALL WARRANTY ALL MATERIALS AND WORKMANSHIP FOR A PERIOD OF ONE (1) YEAR
FROM THE DATE OF ACCEPTANCE OF BY THE PROJECT OWNER AND SHALL REPLACE ANY PORTIONS THAT FAIL
DUE TO FAULTY MATERIALS OR WORKMANSHIP, AT NO ADDITIONAL COST TO THE PROJECT OWNER. A SIX (6)
MONTH AND ELEVEN (11) MONTH INSPECTION WILL BE PERFORMED DURING THE WARRANTY PERIOD. THE
CONTRACTOR SHALL IMMEDIATELY REPAIR ALL ITEMS DETERMINED BY THE PROJECT OWNER OR AUTHORIZED
REPRESENTATIVE TO BE DEFECTIVE UPON NOTIFICATION. THE CONTRACTOR SHALL IMMEDIATELY REPAIR OR
REPLACE FAILED ITEMS UPON NOTIFICATION BY THE PROJECT OWNER. SEASONALLY INSTALLED ITEMS SHALL
BE REPAIRED OR REPLACED DURING THE NEXT AVAILABLE INSTALLATION PERIOD. ITEMS REPAIRED OR
REPLACED UNDER THIS PROVISION SHALL HAVE AN ADDITIONAL ONE (1) YEAR WARRANTY PERIOD FROM THE
NEW DATE OF ACCEPTANCE. AREAS AND/OR OTHER WORK DISTURBED WHILE ACCESSING AND/OR
REPAIRING/REPLACING WARRANTY COVERED ITEMS SHALL BE STABILIZED.