HomeMy WebLinkAboutB-5717 Bank StabilizationCarpenter, Kristi
From: Parker, Jerry A
Sent: Monday, February 13, 2023 12:53 PM
To: Conchilla, Ryan; Alsmeyer, Eric C SAW
Cc: Eason, Patty P; Paul.ingram@kci.com; dmoore@rkk.com
Subject: B-5717 Bank Stabilization
Attachments: B-5717 Bank Stabilization.pdf
Eric and Ryan,
Per our earlier phone conversations, I have attached the drawing showing
the proposed bank stabilization on project B-5717(Gate City Blvd, Guilford
County). The proposed riprap stabilization is considered necessary in order
to prevent slope failure during and after construction of the project. NCDOT
is requesting to utilize the non -reporting Nationwide 13 for installation of the
bank stabilization. There will be approximately 150 total linear feet of bank
stabilization. The project will not exceed an average of one cubic yard per
running foot placed along the bank below ordinary high water and will
involve no discharge into any special aquatic site. NCDOT will adhere to all
conditions of the Nationwide 13 and utilize Best Management Practices
throughout the entire construction phase of the project. Please let me know
if you have any questions or concerns. Thanks.
Jerry
Jerry Parker
Environmental Supervisor
Division 7
North Carolina Department of Transportation
336 256 2063 office
(parker ncdot.gov
1584 Yanceyville St.
P.O. Box 14996
Greensboro, NC. 27415-4996
1