HomeMy WebLinkAbout20140268_03_Pamlico Sound Bridge Corridor Cost Analysis (October 2012) - Appendix B_20150317Appendix B
NCDOT November 2011 Construction Cost Estimate
NC-DOT
Contract Standards and Development Unit
Preliminary Estimate Section
November 9, 2011 Updated Prices
Memo To: Victor Barbour, PE
Administrator of the Technical Services Division
From: Doug Lane
Preliminary Estimate Engineer
Subject: B-2500 (Long Bridge) Alternative Functional Design Construction Estimates, Dare County.
LONG BRIDGE
Description Alternate A Alternate C
(18.5 Miles) 18.1 Miles
Segment A $2,800,000
Segment C $1,900,000
Strs & Dredging $515,000,000 $513,000,000
Segment F $1,400,000 $1,400,000
B-2500 Long Bridge $519,200,000 $516,300,000
(Conventional)
B-2500 Long Bridge $601,000,000 $597,000,000
(Design Build)
Note: Design Build Cost shown is an Average of the High and Low Range.
:
NC-DOT
Contract Standards and Development Unit
Preliminary Estimate Section
January 26, 2012
Memo To: Victor Barbour, PE
Administrator of the Technical Services Division
From: Doug Lane
Preliminary Estimate Engineer
Subject: Design Build Construction Estimate for B-2500 Long Bridge, in Dare County.
B-2500 Lonq Bridqe IHiqh Ranqe)
( Alternate C )
DESCRIPTION CONSTR.COST
B-2500 Long Br (Conventional Construction Cost 10-31-11) , $516,30Q000
Inflate to Lett Date 0.00°/a $0
PE 10.00% $51,800,000
Sub-Total $568,100,000
Permits, R/W Acq.,Plans,1/2CT
Months 2%/Yr
Sub-Total $568,700,000
Risk 10.00% $56,900,000
Design Build Construction Cost (High Range) $625,000,000
Note: Permits, R/W Acquisition, and Plan Completion Months
One Half Contract Time (Contract Time = Months) Months
DB Construction Cost includes 15% E. & C.
cc:
C
NC-DOT
Contract Standards and Development Unit
Preliminary Estimate Section
January 26, 2012
Memo To: Victor Barbour, PE
Administrator of the Technical Services Division
From: Doug Lane
Preliminary Estimate Engineer
Subject: Design Build Construction Estimate for B-2500 Long Bridge, in Dare County.
B-2500 Lonq Bridqe (Low Ranqe)
� Alternate C )
DESCRIPTION CONSTR.COST
B-2500 Long Br (Conventional Construction Cost 110-31-11) $516,300,000 '
Inflate to Lett Date 0.00% $0
PE 5.00% $25,800,000
Sub-Total $542,100,000
Permits, R/W Acq.,Plans,1/2CT
Months 2°/a/Yr
Sub-Total $542,100,000
Risk 5.00% $26,900,000
Design Build Construction Cost (Low Range) $569,000,000
Note: Permits, R/W Acquisition, and Plan Completion Months
One Half Contract Time (Contract Time = Months) Months
DB Construction Cost includes 15% E. & C.
cc:
C
NC-DOT
Contract Standards and Development Unit
Preliminary Estimate Section
November 9, 2071
Memo To: Victor Barbour, PE
Administrator of the Technical Services Division
From: Doug Lane
Preliminary Estimate Engineer
Subject: Design Build Construction Estimate for B-2500 Long Bridge, in Dare County.
B-2500 Lonq Bridqe (Hiqh Ranqe)
( Alternate A �
DESCRIPTION CONSTR.COST
B-2500 Long Br (Conventional Construction Cost 10-31-11) $519,200,000
Inflate to Lett Date 0.00% $0
PE 10.00% $52,000,000
Sub-Total $577,200,000
Permits, R/W Acq.,Plans,1/2CT
Months 2%/Yr
Sub-Total $577,200,000
Rlsk 10.00% $57�800�000
Design Build Construction Cost (High Range) $629,000,000
Note: Permits, R/W Acquisition, and Plan Completion Months
One Half Contract Time (Contract Time = Months) Months
DB Construction Cost includes 15% E. & C.
cc:
. ,
NC-DOT
Contract Standards and Development Unit
Preliminary Estimate Section
November 9, 2071
Memo To: Victor Barbour, PE
Administrator of the Technical Services Division
From: Doug Lane
Preliminary Estimate Engineer
Subject: Design Build Construction Estimate for B-2500 Long Bridge, in Dare County.
B-2500 Lonq Bridqe (Low Ranqe)
( Alternate A )
DESCRIPTION CONSTR.COST
B-2500 Long Br (Conventional Construction Cost 110-31-11) $519,200,000 '
Inflate to Lett Date 0.00% $0
PE 5.00% $26,000,000
Sub-Total $545,200,000
Permits, R/W Acq.,Plans,1/2CT
Months 2%/Yr
Sub-Total $545,200,000
Risk 5.00% $27,800,000
Design Build Construction Cost (Low Range) $573,000,000
Note: Permits, R/W Acquisition, and Plan Completion Months
One Half Contract Time (Contract Time = Months) Months
DB Construction Cost includes 15% E. & C.
cc:
C
TIP No
Route
From
Typical Section
North Carolina Department of Transportation
Preliminary Estimate
B-2500 Seg A County:
NC 12
Oregon Inlet to Rodanthe - Curved Rodanthe Terminus (Segment A)
Approach Road
2 Lane Shoulder
Priced By: Doug Lane
Quantities By: Casey Woodall
Requested By: Victor Barbour, PE
10/31/11 Updated Prices Only
10/8/03
10/28/11
DARE
CONSTR. COST
$2,800,000
Line Sec
Item Des No. Descri tion Quantity Unit Price Amount
Clearin and Grubbin 1.5 Acre $ 30,000.00 $ 45,000.00
Earthwork 20,000 CY $ 15.00 $ 300,000.00
Pavement Removal 650 SY $ 5.00 $ 3,250.00
Draina e New Location 0.7 Miles $ 150,000.00 $ 105,000.00
Fine Gradin 12,600 SY $ 3.00 $ 37,800.00
Pavement Widenin 0 SY $ -
New Pa�ement 11,000 SY $ 80.00 $ 880,000.00
Pavement Resurfacin 0 SY $ -
5.0"Avera e As halt Wed in 3,600 SY $ 30.00 $ 108,000.00
Sub rade Stabilization 11,300 SY $ 7.00 $ 79,100.00
1'-6" Concrete Curb and Gutter 0 LF $ -
2'-6" Concrete Curb and Gutter 0 LF $ -
4" Concrete Sidewalk both sides 0 SY $ -
7" Monolithic Islands 0 SY $ -
Erosion Control 7 Acres $ 15,000.00 $ 105,000.00
New RR Si nal with Gates 0 Each $ -
Rubber Railroad Crossin 0 Each $ -
U rade Traffic Si nal 0 Each $ -
Traffic Control 0.7 Miles $ 25,000.00 $ 17,500,00
Thermo and Markers 0.7 Miles $ 20,000.00 $ 14,000.00
Utilitv Construction
Relocate Existin Water Line 0 LF $ -
Relocate Existin Sewer Line 0 LF $ -
Misc. & Mob (15% Strs&Util)
Misc. & Mob (45% Functional) $ 762,350.00
Lgtn u. i ivnies
t;ontract c;ost ... ... ... ..
E. & C. 15 % . . . . . . . . . . .
Construction Cost ... ... ... ..
:.
........................ $ 2,457,000.00
........................ $ 343,000.00
........................ � 2,800,000.00
TIP No.
Route
From
Typical Section
Priced By:
Quantities By:
Requested By:
North Carolina Department of Transportation
Preliminary Estimate
B-2500 Seg C County: Dare
NC 12
Oregon Inlet to Rodanthe - Intersection Rodanthe Terminus (Segment C) CONSTR. COST
Approach Road $1,900,000
2 Lane Shoulder
Doug Lane 10/31/11 Updated Unit Prices Only
Casey Woodall 10/8/03
Victor Barbour, PE 10/28/11
Line Sec
Item Des No. Descri tion Quantity Unit Price Amount
Clearin and Grubbin 0.5 Acre $ 30,000.00 $ 15,000.00
$ -
Earthwork 6,000 CY $ 20.00 $ 120,000.00
Pavement Removal 0 SY $ -
Draina e New Location 0.40 Miles $ 150,000.00 $ 60,000.00
Fine Gradin 8,600 SY $ 3.00 $ 25,800.00
Pavement Widenin 4,500 SY $ 90.00 $ 405,000.00
New Pavement 2,900 SY $ 80.00 $ 232,000.00
Pavement Resurfacin 3,200 SY $ 15.00 $ 48,000.00
."Avera e As halt Wed in 0 SY $ -
Sub rade Stabilization 8,100 SY $ 7.00 $ 56,700.00
1'-6" Concrete Curb and Gutter 0 LF $ -
2'-6" Concrete Curb and Gutter 0 LF $ -
4" Concrete Sidewalk both sides 0 SY $ -
7" Monolithic Islands 0 SY $ -
Erosion Control 4.2 Acres $ 15,000.00 $ 63,000.00
New RR Si nal with Gates 0 Each $ -
Rubber Railroad Crossin 0 Each $ -
New Traffic Signal (NC12 & Old NC12 1 Each $ 90,000.00 $ 90,000.00
Traffic Control 0.4 Miles $ 35,000.00 $ 14,000.00
Thermo and Markers 0.4 Miles $ 20,000.00 $ 8,000.00
Utilit Construction
Relocate Existin Water Line 0 LF $ -
Relocate Existin Sewer Line 0 LF $ -
Misc. & Mob (15% Strs&Util)
Misc. & Mob 45%Functional) $ 511,500.00
Lgth 0.4 Miles Contract Cost ... ... ... ..... ... ...... ... ........... $ 1,649,000.00
E. & C. 15% ....................... ... ........... $ 251,000.00
Construction Cost ... ... ... ..... ......... ... ........... � 1,900,000.00
:
North Carolina Department of Transportation
Preliminary Estimate
TIP No. B-2500 Seg F County: Dare
Route NC 12
From Oregon Inlet to Rodanthe - Bodie Island Terminus (Segment F) CONSTR COST
Typical Section 2 Lane Shoulder $1,400,000
Priced By: Doug Lane 10/31/11 Updated Unit Prices Only
QuanUUes By: Casey Woodall 10/8/03
Requested By: Victor Barbour, PE 10/28/11
Line Sec
Item Des No. Descri tion Quantit Unit Price Amount
Clearin and Grubbin 0.7 Acre $ 30,000.00 $ 21,000.00
Earthwork 17,000 CY $ 15.00 $ 255,000.00
Pavement Removal 2,000 SY $ 5.00 $ 10,000.00
Draina e New Location 0.30 Miles $ 150,000.00 $ 45,000.00
Fine Gradin 5,300 SY $ 3.00 $ 15,900.00
Pavement Widenin 0 SY $ -
New Pavement 4,300 SY $ 80.00 $ 344,000.00
Pavement Resurfacin 3,000 SY $ 12.00 $ 36,000.00
."Avera e As halt Wed in 0 SY $ -
Sub rade Stabilization 4,600 SY $ 7.00 $ 32,200.00
1'-6" Concrete Curb and Gutter 0 LF $ -
2'-6" Concrete Curb and Gutter 0 LF $ -
4" Concrete Sidewalk both sides 0 SY $ -
7" Monolithic Islands 0 SY $ -
Erosion Control 3.'7 Acres $ 15,000.00 $ 55,500.00
New RR Si nal with Gates 0 Each $ -
Rubber Railroad Crossin 0 Each $ -
U rade Traffic Si nal 0 Each $ -
Traffic Control 0.3 Miles $ 30,000.00 $ 9,000.00
Thermo and Markers 0.3 Miles $ 20,000.00 $ 6,000.00
Utilit Construction
Relocate Existin Water Line 0 LF $ -
Relocate Existin Sewer Line 0 LF $ -
Misc. & Mob (15% Strs&Util)
Misc. & Mob (45% Functional) $ 373,400.00
Lgth 0.3 Miles
Contract Cost
E.&C.15%
Construction Cost
..
.................................... $ 1,203,000.00
.................................... $ 197,000.00
.................................... $ 1,400,000.00
TIP No.
Route
From
Typical Section
Priced By:
Quantities By
Requested By
North Carolina Department of Transportation
Preliminary Estimate
B-2500 Long Deen Water Alternativ Alt A Strs County:
NC 12
Replacement of Bridge #11 (Herbert C. Bonner Bridge)
with Curved Rodanthe Ternunus (Segment A)
Long Deep Water AlternaUve
Doug Lane / Harry Lucas 10/31/11 Updated Unit Prices
Casey Woodall 10/14/03
Victor Barbour, PE 10/28/11
Dare
CONSTR COST
$515,000,000
Line Sec
Item Des No. Descri tion Quantity Unit Price Amount
Thermo and Markers 17.5 Miles $ 12,000.00 $ 210,000.00
1.3 Mi. Southern A roach 40' x 6,575' 263,000 SF $ 95.00 $ 24,985,000.00
(Const. From Work Brid e)
141 Mi. Southern A roach 40' Y 74,637' 2,985,480 SF $ 100.00 $ 298,548,000.00
(Constr. From Bar e)
0.3 Mi. Hi h Level & Channel 40' x 1,584' 63,360 SF $ 180.00 $ 11,404,800.00
Bum Outs (6Ea x 12,OOOSF) 72,000 SF $ 120.00 $ 8,640,000.00
1.8 Mi. Northern A roach 40' x 9,475' 379,000 SF $ 95.00 $ 36,005,000.00
(Constr. From Work Brid e
3.0 Mi. Work Brid e 45' x 16,050' 722,250 SF $ 25.00 $ 18,056,250.00
Dred in (39,875'x 100'x 3'AvDe th) 443,100 CY $ 20.00 $ 8,862,000.00
Misc. & Mob (10% Structure) 1 LS $ 40,671,950.00
Lgtn i i.� Niues
C:ontract (:ost .............. .......... .............. � 447,383,000.00
E. & C. 15% .............. .......... .............. $ 67,617,000.00
Construction Cost ......... ..... . ... ...... ... ........... $ 515,000,000.00
..
TIP No.
Route
From
Typical Section
Priced By:
Prepared By:
Requested By
North Carolina Department of Transportation
Preliminary Estimate
B-2500 Long Deen Water Alternativ Alt C Strs County:
NC 12
Replacement of Bridge #11 (Herbert C. Bonner Bridge)
with Intersection Rodanthe Terminus (Segment C)
Long Deep Water Alternative
Doug Lane / Harry Lucas 10/31/11 Updated Unit Prices
Casey Woodall 10/14/03
Victor Barbour, PE 10/28/11
Dare
CONSTR. COST
$513,000,000
Line Sec
Item Des No. Descri tion Quantit Unit Price Amount
Thermo and Markers 17.5 Miles $ 12,000.00 $ 210,000.00
1.2 Mi. Southern A roach 40' x 6,300' 252,000 SF $ 95.00 $ 23,940,000.00
(Const. From Work Brid e)
14.1 Mi. Southern A roach 40' x 74,589' 2,983,560 SF $ 100.00 $ 298,356,000.00
(Constr. From Bar e)
0.3 Mi. Hi h Level & Channel 40' x 1,584' 63,360 SF $ 180.00 $ 11,404,800.00
Bum Outs (6 Ea x 12,000 SF) 72,000 SF $ 120.00 $ 8,640,000.00
1.8 Mi. Northern A roach 40' x 9,475' 379,000 SF $ 95.00 $ 36,005,000.00
(Constr. From Work Brid e
3.0 Mi. Work Brid e 45' x 15,775' 709,875 SF $ 25.00 $ 17,746,875.00
Dred in (39,875'x 100'x 3'AvDe th) 443,100 CY $ 20.00 $ 8,862,000.00
Misc. & Mob (10% Structure) 1 LS $ 40,516,325.00
Lgtn i i.4 ivmes
(;ontract l;ost ... ........... .... ... ... ... ........... � 445,681,000.00
E. & C. 15 % . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . .. $ 67, 319,000.00
Construction Cost ... ... ... ..... . ... ... ... ... ...... ..... � 513,000,000.00
: 1
Begin Station
121 +75.00
137+50.00
138+75.00
186+50.00
478+25.00
480+75.00
493+00.00
760+00.00
7g2+50.00
805+50.00
854+00.00
B-2500 Herbert C. Bonner Bridge Replacement
Dare County, North Carolina
Dredging Requirements
End Station
134+00.00
138+25.00
186+00.00
187+25.00
480+25.00
492+25.00
742+50.00
773+75.00
7gg+50.00
850+50.00
863+00.00
Dredging - (All Alternatives)
Length in feet
1225
75
4725
75
200
1150
24950
1375
700
4500
900
Comments
Areas in Sound with depth less than 6' below MLLW
" Assumes no dredging in Submerged Aquatic Vegetation (SAV) areas. SAV work completed from workbridge
Total with Curved Rodanthe Terminus (Segment A)
Total with Intersection Rodanthe Terminus (Segment C)
E:\B-2500 Long Bridge
B-11
39875
39875
i6►Z:3ha
B-2500 Herbert C. Bonner Bridge Replacement
Dare County, North Carolina
Workbridge Requirements
Workbridge - Curved Rodanthe Terminus (Segment A)
Begin Station End Station Length Comments
29+75.00 95+50.00 6575 Begin workbridge at shoreline, end at SAV limits
Workbridge - Intersection Rodanthe Terminus (Segment C)
Begin Station End Station Length Comments
22+25.00 85+25.00 6300 Begin workbridge at shoreline, end at SAV limits
Workbridge - Bodie Island Terminus (Segement F-- Applies to All Alternatives)
Begin Station End Station Length Comments
7gg+50.00 805+50.00 1600 Begin workbridge at SAV limits end at SAV limits
863+00.00 941+75.00 7875 Begin workbridge at SAV limits end at shoreline
" Workbridge assumed to be needed only over Submerged Aquatic Vegetation (SAV)
Total with Curved Rodanthe Terminus (Segment A)
Total with Intersection Rodanthe Terminus (Segment C)
16050
15775
E:\B-2500 Long Bridge 1-26-12
B-12