HomeMy WebLinkAboutNCC215149_NOT Closeout Documents_20230213Q,PE
7873
CN
Lennar Carolinas (Troy George)
Troy George
1100 Perimeter Park Drive, Ste. 112
Morrisville, NC 27560
Re: Certificate of Completion
Project Name:
Project Location
Project Number
Submitted By:
Submitted Date:
Completion Date
Depot 499 Sewer 0utfaII
0 Apex Barbeque Road
20-007
McAdams Company
December 1, 2020
February 7, 2023
WATER RESOURCES
February 7, 2023
THIS IS TO CERTIFY that on the above referenced project the grading has been completed,
temporary S&E measures have been removed, and permanent ground cover sufficient to
restrain erosion has been established as outlined on the approved S&E Plan and in accordance
with the Town of Apex S&E ordinance.
Permanent ground cover sufficient to restrain erosion has been established. No additional self -
monitoring or self -inspections are required. Project is in compliance and released under the
SPCA. Termination of coverage under the NPDES General Stormwater Permit for Construction
Activities (NCG01) must be requested by the permittee via a Notice of Termination (NOT). The
NOT is available at: https://edocs.deq.nc.gov/Forms/NCG01-Termination. Please note that this
correspondence must be uploaded as part of completing the NOT process.
The owner of the site will be responsible for regular erosion control maintenance after this
release to the developer.
James Misciagno, CES, CPESC
Stormwater Field Services Supervisor
Town of Apex Stormwater Engineering
TOWN OF APEX
The Peak of Good Living
PO Box 25o Apex, NC 27502 1 (919) 362-8166 1 www.apexnc.org