Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
SW3221001_Design Calculations_20230216 (2)
STORM CALCULATIONS FOR BRIGHTON PARK MOUNT PLEASANT, CABARRUS COUNTY, NC PREPARED BY: LATHAM-WALTERS ENGINEERING, INC. 16507-A NORTHCROSS DRIVE HUNTERSVILLE, N.C. 28078 Phone: 704-895-8484 Fax: 704-237-4362 N.C. Corporate License C-1815 FOR NIBLOCK HOMES, LLC 759 CONCORD PARKWAY NORTH SUITE 20 CONCORD, NC 28027 DATE: August 4, 2022 REVISED: 2/9/2023 Carlos L. Ruano P.E. Latham -Walters Engineer, Inc. 16507-A Northcross Drive Huntersville, NC 28078 Brighton Park Stormwater System Design Summary Stormwater system was designed in accordance with the latest version of the NCDOT's Guidelines for Drainage Studies & Hydraulic Design, NCDOT Subdivision Manual, & Concord's Technical Standards Manual. Roadway inlet locations, capacities, gutter spread, and storm drain pipe system was analyzed and designed using a ten-year discharge (Q10) with a minimum time of concentration of 5 minutes. An intensity of 4 inches/hour was used for calculating spread and determination of appropriate locations for inlet placement. Allowable gutter spread is limited to gutter width plus %travel lane (total of 7 feet with valley gutter) per the latest version of the NCDOT Subdivision Manual. Per Concord UDC, may flow may spread to crown of street for Local & Alley. Concord's Rainfall Intensity Table 2-2 was utilized for hydraulic analysis. Coefficient of 0.50 was determined by the average BUA per lot. Intensity storm of 7.26 in/hr was used for 10-year return period. Storm pipes were design by Rational method. Sediment basins & erosion control measures were based off NCDEQ's Erosion & Sediment Control Planning & Design Manual. 10 8 0 6 t 4 N L U 2 W 4 1 0.8 0.6 0.4 0.2 SECTION 2 STORMWATER RUNOFF R�ru� !'�\ pU ar�od yed rS ? �s 0.2 0.4 0.6 0.8 1 2 4 6 8 10 20 Duration -Hours Figure 2-2 Intensity -Duration -Frequency Curves for Concord, NC TABLE 2-3 ORDINATES OF THE IDF CURVES FOR CONCORD, NC Duration Return Period (years) Hours Minute s 1 2 5 10 25 50 100 0 5 4.80 5.66 6.60 7.26 8.00 8.52 8.98 10 3.83 4.54 5.29 5.81 6.38 6.78 7.13 15 3.19 1 3.80 4.46 4.90 5.39 5.72 6.01 30 2.19 2.62 3.17 3.55 3.99 4.31 4.60 1 1.36 1.65 2.03 2.31 2.66 2.92 3.17 2 0.79 0.96 1.19 1.36 1.58 1.75 1.92 3 0.56 0.68 0.85 0.98 1.15 1.29 1.42 6 0.34 0.41 0.51 0.59 0.70 0.79 0.87 12 0.20 0.24 0.31 0.35 0.42 0.48 0.53 24 0.12 0.14 0.18 0.21 0.25 0.28 0.31 Adopted January 10, 2008 2-5 Technical Standards Manual EXISTING STORM NETWORK ON HWY-73 Hydraflow Storm Sewers Extension for Autodesk® AutoCAD® Civil 3D® Plan EX.DI-1 EX. DI-2 Project File: 2020.17 - EX.STORM Hwy73.stm Outfall Number of lines: 2 1 Date: 8/4/2022 Storm Sewers v2018.30 TR55 Tc Worksheet Hydraflow Storm Sewers Extension for AUtodeskS AutoCADO Civil 3DO by Autodesk, Inc. v2018.30 Line No. 4 4 Description A B C Totals Sheet Flow Manning's n-value = 0.240 0.011 0.011 Flow length (ft) = 100.0 0.0 0.0 Two-year 24-hr precip. (in) = 3.12 0.00 0.00 Land slope (%) = 5.86 0.00 0.00 Travel Time (min) = 9.40 + 0.00 + 0.00 = 9.40 Shallow Concentrated Flow Flow length (ft) = 629.00 0.00 0.00 Watercourse slope (%) = 4.82 0.00 0.00 Surface description = UnPaved Paved Paved Average velocity (ft/s) =3.54 0.00 0.00 Travel Time (min) = 2.96 + 0.00 + 0.00 = 2.96 Channel Flow X sectional flow area (sqft) = 0.00 0.00 0.00 Wetted perimeter (ft) = 0.00 0.00 0.00 Channel slope (%) = 0.00 0.00 0.00 Manning's n-value = 0.015 0.015 0.015 Velocity (ft/s) =0.00 0.00 0.00 Flow length (ft) = 0.0 0.0 0.0 Travel Time (min) = 0.00 + 0.00 + 0.00 = 0.00 Total Travel Time, Tc.............................................................................. 12.36 min Dschedule Page 1 Line Inlet Gnd/Rim Drng Total Runoff i i Flow Invert Invert Capac Line Line Line Vol Line Cover No. ID El Up Area Area Coeff Inlet Sys Rate Up Dn Full Size Length Slope Dn ID Up (ft) (ac) (ac) (C) (in/hr) (in/hr) (cfs) (ft) (ft) (cfs) (in) (ft) M) (ft/s) (ft) 1 EX. DI-2 622.95 0.33 8.05 0.50 7.24 5.61 22.56 614.15 605.72 46.25 24 236.654 3.56 14.62 3 6.80 2 EX.DI-1 625.15 7.72 7.72 0.50 5.61 5.61 21.67 621.97 616.05 86.05 24 48.000 12.33 22.79 4 1.18 Project File: 2020.17 - EX.STORM Hwy73.stm Number of lines: 2 Date: 8/4/2022 NOTES: Intensity = 88.24 / (Inlet time + 15.50) ^ 0.83 -- Return period = 10 Yrs. ; ** Critical depth Storm Sewers PROPOPSED STORM NETWORK ON HWY-73 } CDk I i pB� t I{ T V p ar- I l } I AWHALTWDENW9 hew a- ,..1>. -a+--- 06EPLAY UP TO a � l j. � F �o' !.; i i :I Poe. ME � p4F r Pae '�•- RELOCATE LNY€SJPPLES (►1 39d S y 4 y k - f 1 I ___ I C- �, b In 4 y 9 • i h y� 6 i OLEANDER STRLL'T- I ' WP4)PtK'R1w Hydraflow Storm Sewers Extension for Autodesk® AutoCAD® Civil 3D® Plan SDMH-2 CB-3 DGI-4 DGI-8 Project File: 2020.17 - Prop.STORM Hwy73.stm Riser-2 Number of lines: 8 1 Date: 2/9/2023 Storm Sewers v2018.30 Dschedule Page 1 Line Inlet Gnd/Rim Drng Total Runoff i i Flow Invert Invert Capac Line Line Line Vel Line Depth Depth Cover No. ID El Up Area Area Coeff Inlet Sys Rate Up Dn Full Size Length Slope Dn ID Dn Up Up (ft) (ac) (ac) (C) (in/hr) (in/hr) (cfs) (ft) (ft) (cfs) (in) (ft) M) (ft/s) (ft) (ft) (ft) 1 EX.DI-2 622.95 0.38 1.57 0.50 7.26 6.48 8.20 614.15 605.72 46.25 24 236.654 3.56 11.10 3 0.57 1.02** 6.80 2 DI-5 627.92 0.57 1.18 0.50 7.26 6.72 4.37 620.99 616.41 21.16 18 132.430 3.46 9.43 4 0.46 0.80** 5.43 3 DGI-8 635.53 0.61 0.61 0.60 7.26 7.26 2.66 632.00 621.24 15.13 15 229.890 4.68 5.10 0.55 0.65** 2.28 4 Riser-2 638.00 0.01 0.01 0.01 7.26 7.26 2.75 630.39 617.77 35.98 18 126.170 10.00 12.01 0.28 0.63** 6.11 5 SDMH-2 631.55 0.01 1.39 0.01 7.26 7.01 4.84 627.10 627.00 8.48 18 18.000 0.56 4.95 0.81 0.85** 2.95 6 CB-2 632.87 0.21 1.38 0.50 7.26 7.06 4.87 627.44 627.30 8.51 18 25.000 0.56 4.98 0.81 0.85** 3.93 7 CB-3 632.87 0.11 1.17 0.50 7.26 7.14 4.18 627.84 627.64 8.48 18 36.000 0.56 4.78 0.74 0.78** 3.53 8 DGI-4 0.00 1.06 1.06 0.50 7.26 7.26 3.85 628.53 628.09 5.67 15 67.000 0.66 4.96 0.76 0.79** n/a --[Project File: 2020.17 - Prop.STORM Hwy73.stm Number of lines: 8 Date: 2/10/2023 NOTES: Intensity = 71.97 / (Inlet time + 12.40) ^ 0.80 -- Return period = 10 Yrs. ; ** Critical depth Storm Sewers SAND FILTER-2 Mt. Pleasant, NC Sand Filter Calculation 1. Calculate Runoff Coeff, (Rv) Drainage area to filter, Ad = Impervious area to filter forebay= Impervious percentage = Rv = 0.05 + 0.9(la) _ 2. Calculate req'd water quality volume (WQV) Brighton Park 2 10.33 ac 4.43 ac. 42.86% 0.43569888 Storage: Cum Elev. Area Vol. Vol 632.5 15777 0 0 634 18796 25929.75 25929.75 636 22040 40836 66765.75 638 25511 47551 114316.75 Calculate Depth for WQ Volume: 632.5 0 633.45 16338 634 25929.75 Elevation of WQ Volume = 3. Discount WQv: 0.75 x WQv 4. Site Hydrologic Input Parameters: 633.45 12253.34 cuft WQV = (Rv/1 x Ad/1 x 43560 sf/1 ac x Rd/1 x ft/12 in) WQV = 16338 cf (used to size Af) WQV= 0.3751 ac-ft. Cn Pre = 68.0 Cn Post = 81.0 to pond Tnhla 4 R Raciiltc of Hvrlrnlnnir. ('alriilatinnc frnm Hvrlm('Prl Condition Q 1- ear Q 10- r. Q 25- r Q 50 yr Runoff Pre Dev. 6.28 25.11 34.11 42.44 Post. Dev. 23.81 57.82 72.24 85.12 Routed 0.46 2.75 10.34 25.88 Peak Stage 634.32 636.11 636.41 636.81 Disch. Time 1140 hours 1 1 11.2' IFreeboardl 5. Minimum Surface Area for Sand Media 2042 SA (ft2) 2 FS 12253 DV (FT3) 2 K (in/hr) 72 T (hours) 6. Sediment Sand Sizing 12253 Design Volume (ft3) 6127 Sediment Chamber (ft3) 6127 Sand Chamber (ft3) 7. Sand Filter Drawdown Calculation Equation 2u Minimum Surface area f r a,r Mrntrafm. Syatem *12 SA = FS * DV K'T where: SA = required minimum surface area of infiltration system (W) FS = factor of safety (minlm um of 2 is r—mmended) DV = design volume (ft3) K = hydraulic conductivdy of soil (in/hr) T = maximum dewatering Ume (72 hours) Coeff. Of Permeability of filter media =2 in/hr 0.166667 ft/hr Volume of water drained in one hour = 0.167 ft/hr x SA ft2 = 340.3707 cf/hour 0.095 cfs Drawdown Time = WQV/Drawdown Rate = 48.00 hrs 2 days 8. Underdrain Calculations: 78 I.f of underdrain shown; provide 6" perforated pvc pipe with 3/8" perforations spaces 3" o.c. - 4 longitudinal rows spaced 90 degrees apart. 150 I.f. of pipe I.f. x 4 rows/ft x 4 holes/ft = 2400 holes 50% of perforations = 1200 holes Capacity of one hole = 0.0083 cfs based upon CA(2gh)A0.5 Total Capacity = 9.96 cfs which is 105.3 times the capacity of the sand filter. Total Capacityof 6" PVC @ 0.50% is 0.40 cfs (0.20 cfs assuming 50% clogged) from Mannings and BMP Manual. 9. Antiflotation Calculation 7.5 Height of Riser, ft. 6 Area of Riser, s.f. 45 Volume of Riser, c.f. 2808 Weight of Water @ 62.4 pcf 3088.8 Weight of water with safety factor of 1.1 82.6 Buoyant Wt. of Concrete = (145-62.4) pcf 1.38 Volume of Concrete Req'd in c.y. 37.39 Volume of Concrete Req'd in c.f. 45 Volume of Concrete in Structure (cf) -7.61 Volume of Concrete Required (cf) 0.5 ft thick 2.8 Length/Width (If negative, additional concrete weight not required) Brighton Park Mt. Pleasant, NC 10. Infiltration Rate Q = Af(k)(h+df)/(df) Latham -Walters Engineering, Inc. 16507-A Northcross Drive Huntersville, NC 28078 where Af = surface area of filter bed = 2042 sf df = filter bed depth, ft. = 1.5 ft. k = coefficient of permeability of filter media (ft/day) = ft/day h = average height of water above filter bed (ft) 12, etc. h Q cf/day Q cfs 1 13614.83 0.158 2 19060.76 0.221 3 24506.69 0.284 4 29952.62 0.347 5 35398.55 0.410 6 40844.48 0.473 7 46290.41 0.536 8 51736.34 0.599 9 57182.28 0.662 10 62628.21 0.725 Inlet Report Hydraflow Express Extension for AUtodeskS AutoCADS Civil 3DO by Autodesk, Inc. Thursday, Jan 12 2023 PROP. DI-5 DA:.61 ac 1:7.26 C:.6 Drop Curb Inlet Calculations Location = Sag Compute by: Known Q Curb Length (ft) = 12.00 Q (cfs) = 2.66 Throat Height (in) = 5.00 Grate Area (sqft) _ -0- Highlighted Grate Width (ft) _ -0- Q Total (cfs) = 2.66 Grate Length (ft) _ -0- Q Capt (cfs) = 2.66 Q Bypass (cfs) _ -0- Gutter Depth at Inlet (in) = 2.11 Slope, Sw (ft/ft) = 0.300 Efficiency (%) = 100 Slope, Sx (ft/ft) = 0.300 Gutter Spread (ft) = 0.59 Local Depr (in) _ -0- Gutter Vel (ft/s) _ -0- Gutter Width (ft) _ -0- Bypass Spread (ft) _ -0- Gutter Slope (%) _ -0- Bypass Depth (in) _ -0- Gutter n-value = -0- Inlet Report Hydraflow Express Extension for AUtodeskS AutoCADO Civil 31DO by Autodesk, Inc. Thursday, Jan 12 2023 EX. DI-2 DA:.38 ac 1:7.26 C:.6 Drop Curb Inlet Calculations Location = Sag Compute by: Known Q Curb Length (ft) = 12.00 Q (cfs) = 1.68 Throat Height (in) = 5.00 Grate Area (sqft) = -0- Highlighted Grate Width (ft) = -0- Q Total (cfs) = 1.68 Grate Length (ft) = -0- Q Capt (cfs) = 1.68 Q Bypass (cfs) = -0- Gutter Depth at Inlet (in) = 1.55 Slope, Sw (ft/ft) = 0.300 Efficiency (%) = 100 Slope, Sx (ft/ft) = 0.300 Gutter Spread (ft) = 0.43 Local Depr (in) = -0- Gutter Vel (ft/s) = -0- Gutter Width (ft) = -0- Bypass Spread (ft) = -0- Gutter Slope (%) = -0- Bypass Depth (in) = -0- Gutter n-value = -0- Channel Report Hydraflow Express Extension for AUtodeskS AutoCADO Civil 31DO by Autodesk, Inc. VCD-1 DA: 2.68 ac C:0.6 I: 7.261N/HR Trapezoidal Bottom Width (ft) = 2.00 Side Slopes (z:1) = 3.00, 2.00 Total Depth (ft) = 2.00 Invert Elev (ft) = 600.00 Slope (%) = 2.00 N-Value = 0.150 Calculations Compute by: Known Q Known Q (cfs) = 11.67 Highlighted Depth (ft) Q (cfs) Area (sqft) Velocity (ft/s) Wetted Perim (ft) Crit Depth, Yc (ft) Top Width (ft) EGL (ft) Thursday, Jan 12 2023 = 1.55 = 11.67 = 9.11 = 1.28 = 10.37 = 0.75 = 9.75 = 1.58 Elev (ft) Section Depth (ft) 603.00 3.00 602.50 2.50 602.00 2.00 601.50 1.50 601.00 1.00 600.50 600.00 tiaa tin 0.50 0.00 -0 50 Ot 2 4 6 8 Reach (ft) 10 12 14 16 Channel Report Hydraflow Express Extension for AUtodeskS AutoCADO Civil 31DO by Autodesk, Inc. VCD-2 DA: 1.06 ac C:0.6 I: 7.261N/HR Trapezoidal Bottom Width (ft) = 2.00 Side Slopes (z:1) = 3.00, 2.00 Total Depth (ft) = 2.00 Invert Elev (ft) = 600.00 Slope (%) = 2.00 N-Value = 0.150 Calculations Compute by: Known Q Known Q (cfs) = 4.62 Highlighted Depth (ft) Q (cfs) Area (sqft) Velocity (ft/s) Wetted Perim (ft) Crit Depth, Yc (ft) Top Width (ft) EGL (ft) Thursday, Jan 12 2023 = 1.01 = 4.620 = 4.57 = 1.01 = 7.45 = 0.46 = 7.05 = 1.03 Elev (ft) Section Depth (ft) 603.00 3.00 602.50 2.50 602.00 2.00 601.50 601.00 1.50 1.00 Ot 600.50 600.00 tiaa tin 0.50 0.00 -0 50 Ot 2 4 6 8 Reach (ft) 10 12 14 16 Channel Report Hydraflow Express Extension for AUtodeskS AutoCADO Civil 31DO by Autodesk, Inc. VCD-3 DA: 0.61 ac C:0.6 I: 7.261N/HR Trapezoidal Bottom Width (ft) = 2.00 Side Slopes (z:1) = 3.00, 2.00 Total Depth (ft) = 2.00 Invert Elev (ft) = 600.00 Slope (%) = 2.00 N-Value = 0.150 Calculations Compute by: Known Q Known Q (cfs) = 2.66 Highlighted Depth (ft) Q (cfs) Area (sqft) Velocity (ft/s) Wetted Perim (ft) Crit Depth, Yc (ft) Top Width (ft) EGL (ft) Thursday, Jan 12 2023 = 0.78 = 2.660 = 3.08 = 0.86 = 6.21 = 0.33 = 5.90 = 0.79 Elev (ft) Section Depth (ft) 603.00 3.00 602.50 2.50 602.00 2.00 601.50 1.50 601.00 1.00 600.50 600.00 tiaa tin 0.50 0.00 -0 50 Ot 2 4 6 8 Reach (ft) 10 12 14 16 Channel Report Hydraflow Express Extension for AUtodeskS AutoCADO Civil 31DO by Autodesk, Inc. VCD-4 DA: 0.57 ac C:0.6 I: 7.261N/HR Trapezoidal Bottom Width (ft) = 2.00 Side Slopes (z:1) = 3.00, 2.00 Total Depth (ft) = 2.00 Invert Elev (ft) = 600.00 Slope (%) = 2.00 N-Value = 0.150 Calculations Compute by: Known Q Known Q (cfs) = 2.48 Highlighted Depth (ft) Q (cfs) Area (sqft) Velocity (ft/s) Wetted Perim (ft) Crit Depth, Yc (ft) Top Width (ft) EGL (ft) Thursday, Jan 12 2023 = 0.75 = 2.480 = 2.91 = 0.85 = 6.05 = 0.32 = 5.75 = 0.76 Elev (ft) Section Depth (ft) 603.00 3.00 602.50 2.50 602.00 2.00 601.50 1.50 601.00 1.00 MUF 600.50 600.00 tiaa tin 0.50 0.00 -0 50 Ot 2 4 6 8 Reach (ft) 10 12 14 16 Channel Report Hydraflow Express Extension for AUtodeskS AutoCADO Civil 31DO by Autodesk, Inc. VCD-5 DA: 0.38 ac C:0.6 I: 7.261N/HR Trapezoidal Bottom Width (ft) = 2.00 Side Slopes (z:1) = 3.00, 2.00 Total Depth (ft) = 2.00 Invert Elev (ft) = 600.00 Slope (%) = 2.00 N-Value = 0.150 Calculations Compute by: Known Q Known Q (cfs) = 1.66 Highlighted Depth (ft) Q (cfs) Area (sqft) Velocity (ft/s) Wetted Perim (ft) Crit Depth, Yc (ft) Top Width (ft) EGL (ft) Thursday, Jan 12 2023 = 0.62 = 1.660 = 2.20 = 0.75 = 5.35 = 0.25 = 5.10 = 0.63 Elev (ft) Section Depth (ft) 603.00 3.00 602.50 2.50 602.00 2.00 601.50 1.50 601.00 1.00 — 600.50 600.00 tiaa tin 0.50 0.00 -0 50 Ot 2 4 6 8 Reach (ft) 10 12 14 16