HomeMy WebLinkAboutSite Inspection 2.15.23 A9 Non-CompliantWetland Inspection Report
Project Num: 20201371 Version: I Status: Issued
Project Name: TPB NCDOT -Improvements to NC 129 and NC Project Type: New Road/Highway
County: Graham43 (A-0009C) Region: Asheville
Location: TPB NCDOT - Improvements to NC 129 and NC 143 (A-0009C)
Latitude: Longitude:
SW Plan Location:
Site Owner Name: NC DOT Division 14 - Sylva
Inspection Date: 2/15/2023
Reason for Inspection: Routine
Inspection Type: Site Inspection (DOT)
Inspection Contact Person: Title: Phone:
On -Site Representative(s):
Primary Inspector: Robert K Mitchell Phone:
Secondary Inspector(s):
Facility Compliance Status: ❑ Compliant 0 Not Compliant
Program Areas: 401 (includes isolated/non-404)
Question Areas:
Permit (401 WQC)
Inspection Summary:
Site inspection was conducted on February 15, 2023 by Kevin Mitchell with the Asheville Regional Office. Mark Davis.
Roland, Reid Whitehead, Crystal Amschler, and Dave McHenry were present during the inspection. The following are
items that require attention:
Station 47+00 - 51+00 Y2 (Site I I)- Condition 92 of the permit states, " In -stream work and land disturbance within the
25 foot buffer zone are prohibited during the trout spawning season of January 1 - April 15 to protect the egg and fry
stages of trout." The access road adjacent to the stream needs to be stabilized at 51+00 LT. The stream bank at station
47+00 RT needs to be stabilized.
page: 1
Site Number: 20201371 Owner: Blazer, Keith
Inspection Date: 2/15/2023 Inspection Type: Site Inspection (DOT) Reason for Visit: Routine
Permit (401 WOO Yes No NA NE
Does the impact(s) match what was approved in the 401 WQC or non 404 permit? ❑ ❑ 0 ❑
Are the culverts and/or filled areas installed properly? ❑ ❑0 ❑
Is the site compliant with additional conditions of the 401 WQC or non 404 permit? ❑ ❑ ❑
Comment: Station 47+00 - 51+00 Y2 (Site 11) -Condition #2 of the permit states," In -stream work and land
disturbance within the 25 foot buffer zone are prohibited during the trout spawning season of January 1 _
April 15 to protect the egg and fry stages of trout." The access road adjacent to the stream needs to be
stabilized at 51+00 LT. The stream bank at station 47+00 RT needs to be stabilized.