HomeMy WebLinkAbout20181249 Ver 11_990-087 SmithRowe C204197 Bridge 87 DEMOPLAN Rev 3_20230210 TELEPHONE: (336)789-8221 SMITH-ROWE, LLC FAX: (336)789-6807 639 OLD HIGHWAY 52 SOUTH Mount Airy,NC 27030 DEMOLITION PLAN FOR STRUCTURE 087 Project: C204197 (Wake County, NC) Location: Bridge 87(Loop B Bridge on US-70 over 1-40 EB/WB) This plan is based on available plan information and site visits at the existing structure. Modifications of the plan may be needed during the demolition operation to ensure the safety of the demolition personnel, the traveling public and to complete the demolition project in a timely manner. *Attached Sheet shows locations of spans relative to 1-40 and jurisdictional stream/wetland. Step 1/Shifts 1 (Night): Beginning at end bent 1 and working west the existing deck of span A over the slope and westbound 1-40 will be demolished with excavators and hydraulic hammers (see notes 1 and 2). Traffic Control Required: Detour of 1-40WB Step 2/Shift 2 (Night): Beginning at the break line, demolition of span A deck will continue with excavators and hydraulic hammers. Traffic Control Required: Detour of 1-40WB Step 3/Shift 3 (Night): Beginning at the break line, demolition of span A deck will continue with excavators and hydraulic hammers. Traffic Control Required: Detour of 1-40WB Step 4/Shift 4(Night): Beginning at the break line, demolition of span B deck will begin. Traffic Control Required: Detour of 1-40EB Step 5/Shift 5(Night): Beginning at the break line, demolition of span B deck will continue. Traffic Control Required: Detour of 1-40EB Step 6/Shift 6(Night): Beginning at the break line, demolition of span C deck will be performed. Traffic Control Required: Outside lane closure(s)of 1-40EB Step 7/Shift 7 (Night or Day): Beginning at the break line, demolition of span C deck will continue. Traffic Control Required: None—working away from traffic Step 8/Shift 8 (Night or Day): Beginning at the break line, demolition of span C deck will be completed. Traffic Control Required: None—working away from traffic. Page 1 of 4 C204197(Wake County) Bridge 87 Demolition Plan Step 9/Shift 9 (Night or Day): (protection of wetland under Span D and demolition of Span D) The demolition process will consist of using a hydraulic hammer attached to an excavator to remove the deck from the bridge while the machine is located on the bridge deck. Rubbalized concrete will fall from the deck to the ground below. To protect the impacted areas,first any trees in the area under the bridge will be cleared but not grubbed. Non-Traditional BMP measures will be installed to protect the highly sensitive areas associated with the Swift Creek Watershed. Protection will be installed such that no demolition material enters the stream/buffers. First a layer of geotextile fabric will in placed at the width of the bridge plus 10'outside of drip edge and between the buffer limits;with the fabric spanning the stream bank to bank and not impacting stream flow in any way. Then crane mats will be installed over the entire area of the previously installed fabric. At stream crossing itself, mats will be installed perpendicular to flow spanning from bank to bank. Finally straw bales will be placed on the mats to inhibit material from rolling off the mats once debris has fallen onto the mats. Beginning at the break line, demolition of span D will begin. Traffic Control Required: None—working away from traffic. Step 10/Shift 10 (Night or Day): Beginning at the break line, demolition of span D will be completed. Traffic Control Required: None—working away from traffic. Step 111Shift 11 (Night): Girders of span A will be removed with cranes. Traffic Control Required: Detour of 1-40WB, inside lane closures of 1-40EB Step 121Shift 12 (Night): Remaining girders of span A will be removed with crane(s). Traffic Control Required: Detour of I-40WB, inside lane closures of 1-40EB Step 131Shift 13 (Night): Girders of span B will be removed with cranes. Traffic Control Required: Detour of 1-40EB, inside lane closure of 1-40WB. Step 141Shift 14(Night): Remaining girders of span B will be removed with crane. Traffic Control Required: Detour of 1-40EB, inside lane closure of 1-40WB Step 151Shift 15(Night): Interior bent 1, end bent 1 and slope protection will be demolished with excavators and hydraulic hammers. Traffic Control Required: Detour of I-40WB, inside lane closure of 1-40EB Step 161Shift 16(Night): Interior bent 1, end bent 1 and slope protection demolition will be completed. Traffic Control Required: Detour of I-40WB, inside lane closure of 1-40EB Step 171Shift 17 (Day): Beams of span C will be removed with cranes Traffic Control Required: None—working away from traffic Step 181Shift 18 (Day): Beams of span C will be removed with cranes Traffic Control Required: None—working away from traffic Step 191Shift 19 (Day): Beams of span D will be removed with cranes Traffic Control Required: None—working away from traffic Page 2 of 4 C204197(Wake County) Bridge 87 Demolition Plan Step 201Shift 20 (Day): Interior bents 2 and 3 will be demolished with excavators and hydraulic hammers. Traffic Control Required: None—working away from traffic Step 211Shift 21 (Day): Interior bents 2 and 3 will be demolished with excavators and hydraulic hammers. Traffic Control Required: None—working away from traffic Steps 22-301Shifts 22-30(Day): End bent 2 and slope protection will be demolished with excavators and hydraulic hammers. Debris will be processed (rebar removed)and transported off-site for recycling. Beam removal summary (spans A and B): During the removal of the existing beams two cranes will be utilized to remove the beams. Beam 4 will be rigged to two cranes and the diaphragms cut. The beam will be cut over the cap leaving the bolts attached to the cap. The beam will be lifted and removed. Cranes will be rigged to beam 3 and diaphragms will be cut, and the beam will be separated over the cap leaving the bolts and the remaining beam. On night two, beam 2 will be rigged and two additional cranes will be rigged to beam 1 to maintain stability. Diaphragms between beam 1 and 2 will be cut and the beams will be cut above the cap leaving the bolts intact, both beams will be removed. During beam removal on spans C and D two cranes will be utilized and the cutting pattern will be repeated.To expedite the project, excavators may be utilized to remove the beams on spans C and D away from traffic. Concrete debris will be removed to one or more of these locations for recycling: 1. Wise Recycling at 440 S. Tech Park Lane, Clayton, NC 2. ST Wooten Concrete Plant at Uzzle Industrial Drive, Clayton, NC 3. Godwin Recycling at 1409 S. Clinton Ave., Dunn, NC Rebar and steel debris will be removed to: 1. Wise Recycling at 440 S.Tech Park Lane, Clayton NC Note 1: Prior to demolition over an active roadway, roadway protection (screenings/sand)will be installed. Note 2: Prior to demolition of the deck a saw cut line will be made to provide a clean break/stopping line for each night of demolition. Note 3: The plan/sequence is our guide, multiple steps may be performed concurrently provided the steps can be performed safely for all workers and the traveling public. Note 4: Bent stems/piles will be demolished two feet below finished grade or as needed for new construction. Note 5: In the event of inclement weather, NCDOT and/or the contractor shall make a determination of installing traffic control. Note 6: Starting location/direction of demolition may be reversed to accommodate the contractors needs to continue work on the project. Note 7: The traffic control requirements supplied are a guide. Smith-Rowe and the contractor will coordinate the exact needs of traffic control to ensure the safety of the traveling public and all workers. Note 8: The sequence of Steps/Shifts does not imply continuous work. Our schedule will consist of a 5-day week with an option for a 6t"day if required to recover lost time due to weather or other issues. Page 3 of 4 C204197(Wake County) Bridge 87 Demolition Plan Note 9: Prior to demolition of the deck, girder locations will be identified and marked so operators are aware of the top flange locations. Supervisor(s)will monitor the operation to ensure minimal or no damage occurs to the beams. Note 10:After each shift,girders will be inspected and cleaned by hand and with blowers to remove any loose debris prior to opening the roadway to traffic. Note 11:Concrete slurry from the sawing operations shall be collected and disposed of at one of the area S.T. Wooten Concrete Plants for recycling. Note 12: Prior to demolition over any jurisdictional feature, all applicable requirements of the permit will be adhered to in order to protect these jurisdictional features. Note 13:At anytime during the demolition process, if debris enters the jurisdictional stream/wetland a proper recovery method will be discussed/reviewed prior to retrieval. Submitted by Jonathan Randall, Smith-Rowe, LLC Revised 11/9/22 to add Note 12 Revised 2/6/23 to add protective measures to step 9, add map of Deck Spans, and add Note 13 Page 4 of 4 .'r..¢serr-r Bridge 87 ilia -Spans c;,,f s ii rr,. M