HomeMy WebLinkAboutRE_ [External] RE_ U-5878 Commerce Rd Ext. additional riprap at outlet Site 1 culvertFrom:Sprinkle, Hannah H
To:Steffens, Thomas A CIV USARMY CESAW (USA); Westphal, Anneliese
Subject:RE: [External] RE: U-5878 Commerce Rd Ext. additional riprap at outlet Site 1 culvert
Date:Monday, February 6, 2023 7:55:00 AM
Attachments:image001.png
Anneliese,
DWR has reviewed the adjustment to extend riprap along the stream bank -11 linear feet at the
outlet of Culvert 1 (-L- Sta. 22+11) and to convert the existing mechanized clearing (wetland) impacts
to fill impacts (0.0015 ac). DWR agrees we can handle this via a field adjustment, please consider
this correspondence as the official approval. I will add the supporting documentation to the project
file.
Thank you,
Hannah
From: Steffens, Thomas A CIV USARMY CESAW (USA) <Thomas.A.Steffens@usace.army.mil>
Sent: Friday, February 3, 2023 4:09 PM
To: Westphal, Anneliese <awestphal@ncdot.gov>; Sprinkle, Hannah H
<hannah.sprinkle@ncdenr.gov>
Subject: [External] RE: U-5878 Commerce Rd Ext. additional riprap at outlet Site 1 culvert
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to Report Spam.
Annelise,
The Corps has reviewed the proposal to extend the riprap along the stream
bank 11 linear feet at the outlet of Culvert 1 (-L- Sta. 22+11) and convert
existing mechanized clearing (wetland) impacts to fill impacts (0.0015ac). You
may consider this as official approval of the proposed work and will note this in
the project file.
Thomas A Steffens
Regulatory Project Manager
USACE CESAW-RG-W
O(910)-251-4615
C(252)-955-0739
From: Westphal, Anneliese <awestphal@ncdot.gov>
Sent: Friday, February 3, 2023 3:54 PM
To: Steffens, Thomas A CIV USARMY CESAW (USA) <Thomas.A.Steffens@usace.army.mil>; Sprinkle,
Hannah H <hannah.sprinkle@ncdenr.gov>
Subject: [Non-DoD Source] U-5878 Commerce Rd Ext. additional riprap at outlet Site 1 culvert
Hi Hannah and Tom,
I wanted to follow-up about the subject project’s proposed field adjustment for additional impacts.
As discussed on site on 2/1/2023, NCDOT would like to extend the riprap along the stream bank 11
linear feet at the outlet of Culvert 1 (-L- Sta. 22+11). The existing rock extending from the culvert’s
wing wall in this vicinity (see attached photo) was permitted as fill in wetlands. Therefore, by
extending the rock, we will be changing existing mechanized clearing (wetland) impacts to fill
impacts. Please see the attached permit drawing showing the approximate location of the additional
riprap along the stream. The additional rock will be within the permanent drainage easement. I
calculate the additional fill to be 66 square feet or 0.0015 acre.
We intend to construct this as a field adjustment. Please let me know if you have any questions or if
you need additional information.
Thank you,
Anneliese
Anneliese Westphal
Environmental Senior Specialist
Division 3
NCDOT- Division of Highways
910 341 2000 office
910 604 1330 mobile
910 675 0143 fax
awestphal@ncdot.gov
5501 Barbados Blvd
Castle Hayne, NC 28429-5647
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.