HomeMy WebLinkAboutNCC222584_MODIFICATION Supporting Documents_20230202February 2"d, 2023
Matt Cochrane
CH-M SELC Peeler, LLC
4064 Colony Rd. Suite 405
Charlotte, NC 28211
RE: APPROVAL LETTER W/ CONDITIONS — EROSION CONTROL PLAN
PROJECT NAME: Innovation Logistics Center Mass Grading - EC22.020
LOCATION: 331 Pietryk Dr.
TOTAL DISTURBED ACRES: 59.0 acres
LATITUDE: 35° 36' 20.26"
LONGITUDE: -80" 31' 03.05"
Dear Mr. Matt Cochrane:
This office has reviewed the subject erosion and sedimentation control plan. We find the plans
submitted on January 25', 2023, containing an additional 4 acres along Peeler Rd. and Lane Parkway, to
be acceptable with the following conditions:
1. No land disturbing activities can begin prior to submitting signed grading easement
agreements from all property owners within the new LODs containing property not owned by
CH-M SELC Peeler, LLC.
We hereby issue this Letter of Approval w/Conditions and the following comments:
I. A pre -construction conference is required for this project. Contact this office at least 48
hours in advance.
2. This approval does not authorize off -site land -disturbing activity (borrow or spoil)
associated with this project.
3. This approval does not supercede nor negate the need for any applicable development
permits or approvals (ie: planning, subdivision, floodplain, DOT, etc.).
Please be advised that Section 18-52 b. of the Rowan County Soil Erosion & Sedimentation
Ordinance (RCSESO) states that a copy of the approved Erosion Control Plan be on file at the job site.
Also, you should consider this letter as giving the Notice required by G.S. I I3A-61(d) & Section 18.53 a.
of that same ordinance specifying our right of periodic inspection to insure compliance with the approved
plan. This plan approval shall expire three (3) years following the date of approval if no land -disturbing
activity has been undertaken, as is required by Title 15A NCAC 4B.0129.
Letter of Approval
Mr. Matt Cochrane
February 2nd, 2023
Page 2
Based on rules established by the North Carolina Department of Environmental Management
Land Resources (DEMLR) as of April 1, 2019, all new construction activities are required to complete
and submit an electronic Notice of Intent (NOI) form requesting a Certificate of Coverage (COC) under
the NCG010000 Construction Stormwater General Permit. This form MUST be submitted prior to the
commencement of any land disturbing activity on the above mentioned project. The NOI form may be
accessed at d_eq.nc.gov/NCGOI. Please direct questions about the NOI form to Paul Clark at
Paul.clark@,nedenngov. After you submit a complete and correct NOI form, a COC will be emailed to
you within three business days. A $ 100 fee will be charged annually. This fee is to be sent to the
DEMLR Stormwater Central Office staff in Raleigh.
Rowan County's Sedimentation Pollution Control Program is performance oriented, requiring
protection of the natural resources and adjoining properties. If, following the commencement of this
project, it is determined that the erosion and sedimentation control plan is inadequate to meet the
requirements of the Sedimentation Pollution Act of 1973 (North Carolina General Statute 113A-51 thru
66), which are set forth in the local ordinance, this office may require revisions to the plan and
implementation of the revisions to insure compliance with the Act.
PIease note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form which you have provided. You are requested to file an amended form if
there is any change in the information included on the form.
Your cooperation is appreciated, and we look forward to working with you on this project.
Sincerely,
Josh Canup, CPESC
Environmental Compliance Specialist
ec: Salisbury 1 Stop, David Starkel — PE, Chris Urquhart