January 24, 2023
Robert Tankard
Assistant Regional Supervisor
Water Quality Regional Operation Section
NC Division of Water Resources, NCDEQ
Washington Regional Office
943 Washington Square Mall
Washington, NC 27889
Re: The Lane's Major Permit Application for their Shoreline
Development Project along the Albemarle Sound, at 150 Osprey
Lane, near Harvey's Point in Perquimans County; your letter dated
01/12/2023 requesting additional information; DWR 4 20221424,
Perquimans County
Dear Mr. Tankard:
Many thanks for taking the time on 17 January 2023 to discuss with me the possible ways forward for the
Lane's proposed development.
At that time, we discussed meeting onsite to further evaluate the nature of the area in which the Fish Pond
had been proposed, or alternately relocating the proposed Fish Pond to the northwest portion of the Lot, to
the west of the north -south ditch that is located near the centerline of the Lot. With reference to the latter
possibility, you indicated that you saw no reason to be concerned over impacts to wetlands, and would be
able to complete your agency's comments in rather short order, so that the CAMA Permit Application
could be processed. I had indicated that I would need to speak with my clients to determine whether they
were amenable to such relocation.
I have since been able to speak with them, and being reluctant to relocate the Fish Pond to that area, they
have chosen to remove their request for a Fish Pond in its entirety from their application. They now plan
to obtain backfill for their bulkhead project from an offsite source, and from the uplands that lie adjacent
to the existing erosion escarpment. I trust that you will find this alternative equally unobjectionable. I
have revised the relevant submittals of the CAMA application to reflect their wishes, and am submitting a
revised application to the NC Division of Coastal Management. I am providing a copy of those revised
submittals to you as enclosures to this letter.
Upon your satisfactory review of the enclosures, we respectfully request that you indicate to the NC
Division of Coastal Management that, from the perspective of the Division of Water Resources, the hold
on the processing of the application can be removed.
If you require any additional information, submittals, or clarification, please contact me so I can
expeditiously address any concerns.
Encl:
Sincerely,
Ted Sampson
(1) DCM MP 1 Application for Major Development Permit — Lane, Revised 01/24/2023
(2) DCM MP 2 Excavation and Fill — Lane, Revised 01/24/2023
(3) DCM MP 3 Upland Development — Lane, Revised 01/24/2023
(4) Sampson Contracting Drawing No. 04-071422-002, Sheet 1, titled Site Drawing Overview,
Rev. 1 dated 01/19/2023
(5) Sampson Contracting Drawing No. 04-071422-002, Sheet 2, titled Site Drawing
Development Area (South), through Rev, 3 dated 01/23/2023
(6) Sampson Contracting Drawing No. 04-071422-002, Sheet 3, titled Site Drawing
Development Area (North), Rev. 1 dated 01/19/2023
(7) Sampson Contracting Drawing No. 04-071422-002, Sheet 4, titled Site Drawing Shoreline
Development Area Expanded, through Rev. 4 dated 01/23/2023
(8) Project Narrative, Revised 01/23/2023
2