Hi Tom and Hannah,
I wanted to send some photos of my review of the subject project.
Stephen met me onsite on 1/19/23. The contractor is working on installing the trestle. The spans
are 25’ long. The photo with the excavator shows how they are floating the mats into place to stack
for the “bents.” They are taking care to stage materials on existing riprap or the existing areas of
trestle, not on any existing coastal wetlands.
We confirmed that the access ramp at the Sta. 20+00 location is in the correct location, and the
contractor noted that it is less than the allowable 50’ wide (I think he indicated 32’ wide). Also, they
have minimized disturbance at the access points by partially spanning from the toe of the existing
slope to the trestle. We did not review the access point at Sta. 22+50. If the access ramps need to
be adjusted, Stephen reminded the contractor that they would need to be granted permission for
any changes. They are not planning to change the access ramps at this time.
Please let me know if there are questions. Thank you for meeting me, Stephen!
We are planning on visiting this project for our “first Wednesday” ride through in Onslow County on
February 1, 2023.
Anneliese
Anneliese Westphal
Environmental Senior Specialist
Division 3
NCDOT- Division of Highways
910 341 2000 office
910 604 1330 mobile
910 675 0143 fax
awestphal@ncdot.gov
5501 Barbados Blvd
Castle Hayne, NC 28429-5647
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.