Gentlemen,
Thank you for your patience on getting this information to you. I am enclosing 4 revised drawings which show the
revised items clouded. Some of the notes are just to further clarify. Two of the drawings are detail sheets. I am sending
back sheet 4 of the PCN, which has also been revised. Please note that the column for the “Average Stream Width” has
changed, some of the numbers according to Alan’s field observation. Matthew is going out to the site on Friday for a
field inspection. He is going to have another look at and measure the stream widths. I can wait to send you the hard
copies in the mail, incase his field work shows differently (mainly on S3). The number given is from field shots edge of
water, I took from our surveyor’s survey.
If you see anything on the attachments that you have a question about or need us to revise, please let me know.
Alan, to answer your question about the length of time the temporary crossings will be in, is until around 2/28/16, which
is projected end of project date. They may be able to come out sooner if the work in that area is done earlier.
Thanks,
Christine
Christine Brown