HomeMy WebLinkAboutBasinwide_Hydrologic_Model_Dev_Status_Report_11-2011Page | 1
Department of Environment and Natural Resources
Division of Water Resources
STATUS REPORT TO THE GENERAL ASSEMBLY ON
DEVELOPMENT OF BASINWIDE HYDROLOGIC MODELS
OCT. 1, 2010, THROUGH SEPT. 30, 2011
Introduction
The North Carolina General Assembly directed the N.C. Department of Environment and Natural
Resources to develop basinwide hydrologic models, as recommended by the Environmental Review
Commission. Session Law 2010-143 requires that the department report to the Environmental Review
Commission on the development of basinwide hydrologic models no later than Nov. 1 of each year.
Under the session law, the first report is due no later than Nov. 1, 2011.
The priority for model development by the department is based on three factors:
1. The degree to which a river basin or a portion of a river basin is experiencing or will be likely to
experience water supply shortages;
2. Whether the ecological integrity of surface waters in the river basin is threatened or will likely
become threatened; and
3. A river basin for which an existing hydrologic model has not been developed by the department
or others.
Model Development Schedule
In accordance with the priorities established in Session Law 2010-143, the department has drafted the
following table for river basin model development. The table lists the name of the river basin along with
the year when the hydrologic model for that basin is proposed to be completed. A map showing the North
Carolina river basins for which basinwide hydrologic models will be developed is shown below.
Completion
Year River Basin Hydrologic Models
2011 Tar and Broad
2012 Cape Fear, Roanoke and Neuse Updates
2013 Hiwassee and Little Tennessee
2014 French Broad and Lumber
2015 New and Watauga
2016 Catawba and Savannah
2018 Albemarle Sound, Chowan and Onslow Bay
2019* Yadkin-Pee Dee
Page | 2
North Carolina River Basins
*The Yadkin-Pee Dee is scheduled for completion in 2019, but if the Federal Energy Regulatory
Commission issues new licenses for the Yadkin and Yadkin-Pee Dee Hydroelectric Projects in that basin,
priority for model development for the Yadkin-Pee Dee would be elevated and the basin model completed
much sooner.
Completed Models
The N.C. Division of Water Resources completed three river basin hydrologic models prior to the
enactment of the 2010 legislation. The Cape Fear river basin model was completed in 2003 and the
Neuse river basin model was completed in November 2009. The Cape Fear and Neuse models are being
updated with the most current information and additional functions. The updated versions will have the
ability to be run together as one model to assist in the analysis of alternatives for the next round of water
supply allocations from the B. Everett Jordan Reservoir. The Roanoke River basin hydrologic model was
first completed in 1995 and the updated version will be completed in 2012.
Models Being Developed
Currently, the division is developing two additional river basin hydrologic models. The division will
complete models for the Tar River Basin and the Broad River Basin by the end of 2011. After
completion, these two models are scheduled for EMC review and approval later this year, or in early
2012. Work began on these models in spring 2010. Improved features of these two new models will
include the incorporation of the water shortage response plans for water systems, as well as location place
holders for future ecological flow determinations. Three stakeholder meetings were held in each river
basin at specific stages of the model development process. The purpose of these meetings was to provide
information to water systems and other stakeholders on collection of model input data and how the model
was constructed. Stakeholders had the opportunity to review all of the information in the model related to
their water system for accuracy. DWR also provided model demonstrations and gave representatives of
each water system an opportunity to review a model simulation of their system. A fourth meeting will be
held in each basin upon model completion to provide training for interested parties in using the completed
river basin hydrologic model.
Page | 3
Ecological Flows Science Advisory Board
Session Law 2010-143 also required the department to create a Science Advisory Board to assist the
department in characterizing the natural ecology of the different river basins and to develop procedures
for determining the flows necessary to maintain ecological integrity in surface waters. The Ecological
Flows Science Advisory Board was convened according to the guidelines in the legislation, and its first
meeting was held in November 2010. The Science Advisory Board has met six times so far in 2011, with
two additional meetings scheduled for the remainder of this year. All meetings are open to the public and
participation is also available through webinars. The board’s work will continue through 2012 and
possibly beyond. More information on ecological flows or the Ecological Flows Science Advisory
Board, meeting summaries, presentations and recordings of the meetings is available on the division’s
website at http://www.ncwater.org/Data_and_Modeling/eflows/.
Summary
This document serves as the first report to the Environmental Review Commission on the development of
basinwide hydrologic models by the department from Oct. 1, 2010, through Sept. 30, 2011, as required by
the session law. A similar status report on the development of river basin hydrologic models will be
provided by Nov. 1 of each year.