From: Davis, Erin B
Sent: Tuesday, January 10, 2023 8:33 AM
To: Baker, Caroline D
Subject: FW: [External] RES Neu -Con UMB, Meadow Spring Site (SAW-2016-01989) Year 4
Annual Monitoring Report Review and Credit Release Request
Laserfiche Upload: Email
DWR#: 20160980 v.1
Doc Date: 12/16/22
Doc Type: Mitigation — Mitigation Information
Doc Name: General topic of email title
From: Haywood, Casey M CIV USARMY CESAW (USA)<Casey.M.Haywood@usace.army.mil>
Sent: Friday, December 16, 2022 9:09 AM
To: Tugwell, Todd J CIV USARMY CESAW (US) <Todd.J.Tugwell@usace.army.mil>; Kim Browning
<Kimberly.D.Browning@usace.army.mil>; Davis, Erin B <erin.davis@ncdenr.gov>; Steve Kichefski
<Steven.1.kichefski@usace.army.mil>; Bowers, Todd <bowers.todd@epa.gov>; kathryn_matthews@fws.gov; Wilson,
Travis W. <travis.wilson@ncwildlife.org>; Merritt, Katie <katie.merritt@ncdenr.gov>
Cc: Jamey Mceachran (jmceachran@res.us) <jmceachran@res.us>
Subject: [External] RES Neu -Con UMB, Meadow Spring Site (SAW-2016-01989) Year 4 Annual Monitoring Report Review
and Credit Release Request
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Good morning,
The below referenced Year 4 Monitoring Report review has been requested by EBX-Neuse I, LLC. Per Section 332.8(o)(9)
of the 2008 Mitigation Rule, this review follows the streamlined review process, which requires an IRT review period of
15 calendar days from this email notification. Please provide any comments by 5 PM on the 15-day comment deadline
shown below. When providing comments please indicate if your concerns are great enough that you intend to request a
site visit prior to the credit release. Comments provided after the 15-day comment deadline (shown below) may not be
considered.
At the conclusion of this comment period, a copy of all comments will be provided to EBX-Neuse I, LLC and the NCIRT
along with District Engineer's intent to approve or disapprove this credit release.
Sponsor:
EBX-Neuse I, LLC (RES)
Bank Name:
RES Neu -Con Umbrella Mitigation Bank
Site Name:
Meadow Spring
USACE ID:
SAW-2016-01989
River Basin:
Neuse
H UC:
03020201
County:
Johnston
Requested Credit Release: Year 4 Annual Monitoring
5% of the total stream restoration and/or enhancement credits: 272.000 Warm Water Stream Credits
10% of the total stream restoration and enhancement credits for bankfull verification: 544.000
20% of the total wetland restoration and/or enhancement credits: 2.88 Riparian Wetland Credits (15% MY3 scheduled
release, in addition to the MY4 5% release)
Please note an adaptive management plan addressing four areas of concern was submitted to the IRT in June 2022 and
work was completed in August 2022.
15-Day Comment Start Date: December 21, 2022
15-Day Comment Deadline: January 05, 2023
45-Day Credit Release Approval Deadline: February 04, 2023
NOTE: Deadlines will be extended if an on -site meeting is requested.
Please be sure to log on to RIBITS before following the link below. Once in the Cyber Repository, select the arrow beside
appropriate folder to view and/or download the documents.
Cyber Repository Link: https://ribits.ops.usace.army.mil/ords/f?p=107:10:14714630509300::::P10 BANK ID:4414
Thank you and please contact me with any questions,
Casey
Casey Haywood
Mitigation Specialist, Regulatory Division I U.S. Army Corps of Engineers
(919) 750-7397 work cell
BUILDING STRONG