Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
NC0036269_Corrective Action Plan_20221229
309 East Morehead Street, Suite 220 Charlotte, NC 28202 T: 704.358.7204 December 28, 2022 EB:n,ANDll ' Min Xiao, PE Environmental Engineer NPDES Industrial Permitting NC DEQ/ Division of Water Resources/ Water Quality Permitting 512 N. SalisburySt. Office #925E Raleigh, NC 27604 157299 Subject: Construction Progress Report for the Phase 3 Expansion to 30 MGD at the Rocky River Regional WWTP Dear Ms. Xiao Per the compliance schedule of the NPDES permit NC0036269, we are submitting a brief report summarizing the progress of the construction project for the past calendar year (NTP date: May 31, 2022). With this report, compliance schedule items 1 through 4 of paragraph A(7) of the NPDES permit are now complete. The Rocky River Regional WWTP Phase 3 Expansion project includes the following im- provements and modifications: • New Influent Flow Equalization (EQ) Tank and Nitrification Enhancement Facility (NEF) • New Aeration Basin (AB) No. 6 • New Blower Building to house three new aeration blowers for AB No. 6 • New Effluent Parshall Flume • Raising of the walls of the existing Chlorine Contact Basins (CCBs) No. 1 and No. 2 • Two new waste activated sludge (WAS) pumps in the existing WAS Pump Station Representative pictures showing the construction progress to date are provided below. Attachment includes a construction schedule as prepared by the Design -Builder Crowder Construction Company. EQ Tank and NEF • The area for the new EQ Tank and NEF has been cleared and partially excavated (Fig- ure 1). Excavation will continue for the next few weeks. • The EQ influent and effluent vaults have been constructed, awaiting piping and equipment to be installed next (Figure 2). • The slab for the NEF Junction Box has been poured and rebar is being installed for the walls (Figure 3). 2022 Construction Progress Rpt for RRRWWTP Ph.3 Expansion Min Xiao, PE NC DEQ December 28, 2022 Page 2 Figure 1. Site Excavation for New EQ/NEF Figure 2. EQ Influent (Left) and Effluent (Right) Vaults 2022 Construction Progress Rpt for RRRWWTP Ph.3 Expansion Min Xiao, PE NC DEQ December 28, 2022 Page 3 Figure 3. NEF Junction Box Aeration Basin No. 6 The floor and most of the walls of the new Aeration Basin No.6 have been constructed (Figures 4 and 5). 2022 Construction Progress Rpt for RRRWWTP Ph.3 Expansion Min Xiao, PE NC DEQ December 28, 2022 Page 4 Figure 5. Aeration Basin No.6 2022 Construction Progress Rpt for RRRWWTP Ph.3 Expansion Min Xiao, PE NC DEQ December 28, 2022 Page 5 New Blower Building The site for the new Blower Building has been cleared and the stone for the subgrade has been stockpiled (Figure 6). The new blowers are under fabrication at the factory in Finland. Figure 6. Site Preparation for New Blower Building New Effluent Parshall Flume Support of excavation has been installed. Installation of reinforcing for the new walls and bottom slab has started and will continue for the next few weeks (Figure 7). 2022 Construction Progress Rpt for RRRWWTP Ph.3 Expansion Min Xiao, PE NC DEQ December 28, 2022 Page 6 Figure 7. Construction for New Effluent Parshall Flume Chlorine Contact Basins Interior forms have been placed to raise the walls starting with CCB No.2 (Figure 8). 2022 Construction Progress Rpt for RRRWWTP Ph.3 Expansion Min Xiao, PE NC DEQ December 28, 2022 Page 7 of } 'r �' - 'Ar-: NOW. 7 Figure 8. Installation of Formwork at CCB No.2 Should you have any questions, please do not hesitate to call me at 407.409.5152 or by email at anipsitakis@brwncald.com. Very truly yours, Brown and Caldwell George Anipsitakis, PhD, PE Supervising Engineer Charlotte, NC Attachments: . Attachment A: Construction Schedule 2022 Construction Progress Rpt for RRRWWTP Ph.3 Expansion ATTACHMENT A CROWDER CONSTRUCTION TASK ID TASK WORK START DATE FINISH DATE DAYS I JAIMIJIJIAS O N D J F M A M J J A S ON D JFMAMJ JASONDJFMAMJ JASOND J F M A M MILESTONES 1050 Construction Notice to Proceed @ Phase 3 Capacity Upgrades 0 31-May-22A I 105Q ♦ Construction! Notice f F rowed @ phase Capacity Upgrades 1200 commissioning @ Phase 3 Capacity Upgrades 1200 Commissioning @ Phase 3 Capacity Upgrades 32 18-Mar-24 30-Apr-24 1140 Substantial Completion @ Phase 3 Capacity Upgrades 0 30-Apr-24* 1140 ♦ Substantial Completion a�F hase 3' Capacity U 1270 Fir 1270 Final Completion 0 09-May-25 PRECONSTRUCTION 30•� DESIGN I I 1000 PER & 30% Design @ Phase 3 108 01-Apr-21 A 01-Sep-21 A O P,ERI& a0% Design @ Phase a 1120 Owner Review 30% Design @ Phase 3 5 02-Sep-21 A 09-Sep-21 A 1120 ❑ Owner Rev 1130 ❑' Incorpora 1150 I[= Prepa ew 30% Design a@ Phase' 3 e 30%'Design' Review Comments @' Pha e 35%',Constructign Cost Estimate @ Ph is e 3 3 1130 Incorporate 30% Design Review Comments @ Phase 3 10 10-Sep-21 A 23-Sep-21 A 1150 Prepare 30% Construction Cost Estimate @ Phase 3 30 10-Sep-21 A 21-Oct-21 A 60% DESIGN I I 1010 GMP Level Design Documents @ Phase 3 107 24Sep 21 A 25-Feb 22A 1010',7_3 GMP',Level Design Documents', hase 3 1160 Owner Review GMP Level Design Documents @ Phase 3 5 28-Feb-22A 04Mar-22A 11601 0 Owner Review GMP Level IDesi 1170 ❑ Incorporate Design Review Co 1180 b P';repare GM p Level', Constru n Documents @ Phase 3 1 i rents P Phase 3' ti n Cost Estimate @ phase 3'1 1170 Incorporate Design Review Comments @ Phase 3 10 19 07-Mar-22A 07-Mar-22 A 18-Mar-22A 31-Mar-22 A 1180 Prepare GM P Level Construction Cost Estimate @ Phase 3 FINAL DESIGN 1060 Final Design Documents @ Phase 3 101 21-Mar-22A 10-Aug-22A 10601 O Final Design rcicuments @ Phase 3 GMP I I 1070 Submit GMP #1 - Generators & Blowers @ Phase 3 0 10-Nov-21 A 1070 Sub 1080 I it GM'P #1 - Generators'& Blowers'@ P ia3e Submit GMP;¢2 -!Electrical Upgrades @ 1040 r-----1 Final GM,P #3 Negotu tic 1190 ♦ Execute Final GMP 3 ase, 3 ns /, Contract ( Phase 3 PlhaSe 31 1080 Submit GMP #2 - Electrical Upgrades @ Phase 3 0 16-Dec-21 A 1040 Final GM P #3 Negotiations / Contract @ Phase 3 43 31-Mar-22 A 31-May-22 A 1190 Execute Final GMP #3 @ Phase 3 0 31-May-22A 1260 Execute Balance Subcontracts @ Phase 3 60 01-Jun-22A 24Aug-22A 1260 Execute B la ce'Subcontracts @ Phase 31 WORKSHOPS I I 5 22-Oct-21 A 28-Oct-21 A 1220 30% Design Estimate Review Workshop @ Phase 3 12201 0', 30% Design Estimate Review Workshop @ Ph ise 3 1 1230 Electrical Design Review Workshop @ Phase 3 5 05-Nov-21 A 11-Nov-21 A 1230 10 Electrical Design Review Workshop (@ Phase 3 1240 60% Design Constructibility Review Workshop @ Phase 3 1240 ',1 60% Design Constructibility Re iew Workshop a@ Phase 3 5 07-Mar-22A 11-Mar-22 A HURRICANE REMEDIATION 1380 Hurricane Weather Excavation Remediation 21 02-Oct-22A 22-Oct-22A I 1380 Hur is ne',Weather Excavation Remediatior PROCUREMENT I I STORM 6850 Storm Shop Drawings Prep/ Submit 33 12-Sep-22A 26-Oct-22A 68$0 E:�=, St Stop Drawings prep,/ Submit 6860 Storm Shop Drawings Review/Approve 6860 0 St, rr i Shop,Drawings Review l,Approve 4 27-Oct-22A 01-Nov-22A 6870 Storm Structure Fabrication 6870 0 Storm Structure Fabrication 21 02-Nov-22 A 02-Dec-22 A UNDERSLAB PIPING ROCKY RIVER WWTP VERSION 12-Dec-22 DATA DATE: 12-Dec-22 PROJECT SCHEDULE PAGE 1 OF 17 RR-09 (12-12-22) 12-Dec-22 CROWDER CONSTRUCTION TASK ID TASK WORK DAYS START DATE FINISH DATE A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 2310 2350 2570 2360 2730 2740 2750 2321 UnderslabPiping Fabrication -AB6 UnderslabPipingPrep/Submit- EQTank 17 40 01-Jun-22A 23-Jun-22A I 31 O', UndersiabPiping; 2350 'OI UmderslabPipi 2570 2360 Q Underalab' I 273Q ',O Reber Shop, Dre 2740 O Reber Shop! 2750! O Reblar (Base 2321 I Reber Shop' r rication-A 6; gPrep /'Submit', EQTenkl I Underslab IPipi'ng Fabrication EQ Tank ingShopDrawingReViewYAPprobe;EQTa g (Sass' Slabs;ABQ) Prep;/ Submit r wing (Base Slabs AB6) Review / Approve abs!AB6)Fabrication ing (NEF'Junction Box/'Box 8) Submit' k 01-Jun-22A 27-Jul-22A Underslab Piping Fabrication - EQ Tank 180 01-Jun-22A 15-Feb 23 UnderslabPlpingShopDrawingReview/Approve- EQTank Reber Shop Drawing (Base Slabs A136) Prep / Submit 17 27 28-Jul-22A 01-Jun-22A 19-Aug-22A 08-Jul-22A Reber Shop Drawing (Base Slabs A136) Review / Approve 20 11-Jul-22 A 05-Aug-22 A Reber (Base Slabs AB6)Fabrication 15 21-Jul-22A 10-Aug-22A Reber Shop Drawing (NEF Junction Box/ Box8) Submit 1 03-Aug-22A 03-Aug-22A 2761 2771 6290 AB BLOWER 2580 Reber Shop Drawing (NEF Junction Box/ Box 8) Review /Approve 10 04-Aug-22A 17-Aug-22A I I I 2580 p76';1 ■';Reber 8hop 2171; Reber 6290 I AB Blower S io Dawing'(NE';FJpnction';Box/Box8)Review / N FjunctiopBgx/0ox8)Fabrication; Reber Fabrication @ CCBT/ CCB2 Drawi,ng Prep / Submit ' pprove Reber (NEF Junction Box/ Box 8) Fabrication 30 18-Aug-22A 29-Sep-22A Reber Fabrication @ CCB1 / OCB2 AB Blower Shop Drawing Prep / Submit 63 153 30-Sep-22 A 31-Dec-21 A 30-Dec-22 05-Aug-22 A 2590 2600 NEF BLOWS 3510 3520 AB Blower Shop Drawing Review /Approve 101 13-Apr-22A 02-Sep-22 A I 2590 AB 8lowe I �600 60 3510 NEF BI 3520Q NEF BI Shop Drawing Review /;Approve AB; Blower; Fat r Shop Drawing Prep / S b it wer Shop';Drawing Review /Approve ricetio AB Blower Fabrication NEF Blower Shop Drawing Prep/Submit 200 69 31-Oct-22A 15-Jun-22A 14-Aug-23 21-Sep 22A NEF Blower Shop Drawing Review /Approve 17 22-Sep-22 A 14-Oct-22 A 3540 3560 3530 2640 NEF Blower Shop Drawing Resubmit 43 17-Oct-22A 16-Dec-22 I 3540 3560 3530 2640 ''Q'' Ductile Irdn Pi I NER Blower S'hop'Drawing Resubmit 11 NEF; Blower, Shop Dravying;Re$ubrmittel R NEF! Blower, Fabric Fittings Shop'Drawing Prep Submit view /Approve ation NEF Blower Shop Drawing Resubmittal Review /Approve 10 19-Dec-22 03-Jan-23 NEF Blower Fabrication Ductile Iron Pipe / Fittings Shop Drawing Prep/ Submit 130 42 04-Jan-23 01-Jun-22A 06-Jul-23 29-Jul-22A NJ 1210 6840 2650 W 2670 Ductile Iron Pipe / Fittings Fabrication (Larger than 16") 233 01-Jun-22A 01-May-23 I I I 1210 6840 2650 O Ductile Iron I 2670' Ductile Iron Pip6/ Fittings F 060 Ductile Iron Pip Pipe / Fittings Shop Drawing Review /Ap AS''Pumps Shop Drawing Prep/'SuVSmiti abrigatign (Larger than';16'� / Fittings Fabrication (,Less than 16"); rove Ductile Iron Pipe / Fittings Fabrication (Less than 16") 300 01-Jun-22A 04-Aug-23 Ductile Iron Pipe / Fittings Shop Drawing Review /Approve WAS Pumps Shop Drawing Prep/Submit 44 67 01-Aug-22 A 25-Aug-22A 30-Sep-22 A 30-Nov-22A 2680 WAS Pumps Shop Drawing Review /Approve 6 01-Dec-22 A 08-Dec-22 A68Q p 26Q0 2700 271 WAS Pumps Shop Drawing Review /'Ppprov WAS, Pumps Fabrication Gravity Thiclkehers!Shop DraWing'Prelp/ GraVityThickeners Shop Drawing ReviewYApprobe ubmitl 2690 WAS Pumps Fabrication GRAVITY THICKENERS 2700 Gravity Thickeners Shop Drawing Prep/Submit 56 81 09-Dec-22A 12-Sep-22A 28-Feb-23 06-Jan-23 2710 Gravity Thickeners Shop Drawing Review/Approve 20 09-Jan-23 03-Feb-23 2720 2120 2400 1610 Gravity Thickeners Fabrication PEMB Shop Drawing Prep/ Submit 160 43 06-Feb-23 28-Jul-22A 20-Sep- 23 27-Sep-22A 2120 O! PEMBS 2400 1610 Gravity T iop0rawing Prep/ Submit PEMIBSIho0DrawingReview /Approve PEM'B Fabrication ickoners Fabrication PEMB Shop Drawing Review /Approve 65 28-Sep-22A 30-Dec-22 PEMB Fabrication 75 16-Dec-22 03-Apr-23 LV SWITCHGEA 1110 LV Switchgear Fabrication 1110 LV;Switch ear Fabrication 300 18-Jul-22A 20-Sep-23 VERSION 12-Dec-22 DATA DATE: 12-Dec-22 ROCKY RIVER WWTP PROJECT SCHEDULE 12-Dec-22 PAGE 2 OF 17 RR-09 (12-12-22) CROWDER CONSTRUCTION TASK ID TASK WORK DAYS START DATE FINISH DATE A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 1280 1290 2390 LVSwitchgear Prep/Submit 99 LV Switchgear Review /Approve 10 28-Jul-22A 16-Dec-22 03-Jan-23 1,28q I 1290 2 LVSwQchgear; Prep;Submit 11 LV Switohgear Review/,Approve I Elt;ctrlcal IProductionlDrawinps 19-Dec-22 Electrical Production Drawings 5 18-Jan-23 24-Jan-23 6800 Electrical Production Drawings Review/Approve EMT fCHBOARDS 6580 LV Switchboard Fabrication 10 186 25-Jan-23 18-Jul-22A 07-Feb-23 10-Apr-23 I 6$ I 6580 656Q O Low 6570 0 * Eledtricbl Production Drawings Revie LV Switchboard Fabrication Voltage Switchboard 'Prep/Submit ) V Switchboard Review / Approve /Approve 6560 Low Voltage Switchboard Prep/Submit 75 28-Jul-22A 10-Nov-22A 6570 LV Switchboard Review / Approve 20 11-Nov-22 A 12-Dec-22 7070 9642 6390 4370 LV Switchboard Switchboard Resubmittal 15 04-Jan-23 24-Jan-23 I I I 7070 9642 I 6390 4370 1 LV Switchboard Switchboard Resubmittal NO'; LV';Switchboard Switchboard Resubmittal LIS Fabrication', LIS'ShopDrawing Prep/'Submit ReviewlApprove LV Switchboard Switchboard Resubmittal Review/Approve LIS Fabrication 20 143 25-Jan-23 18-Jul-22A 21-Feb-23 08-Feb-23 LIS Shop Drawing Prep/Submit 99 28-Jul-22A 16-Dec-22 6380 MCC 6450 6430 6440 LIS Shop Drawing Review/Approve MCC's Fabrication 20 152 19-Dec-22 18-Jul-22A 17-Jan-23 21-Feb-23 I I 6380 I 6450 6430 O 6440 M IN ;LIS Shop Drawing Review /Approve' MCC's Fabrication C 's IPrep/Submit) MCC-s�ReVievv/Apprbve! MCC's Prep/Submit 76 28-Jul-22A 11-Nov-22A MCC's Review /Approve 20 14-Nov-22A 13-Dec-22 9652 9662 6550 6530 MCC's Resubmittal 15 04-Jan-23 24-Jan-23 I I 9652 9632 I 6550 6530 OAFS I■' MCC's Resubmittal I ON'', MCC's Resubmittal Review/,Appro 1 ATS Fabrication Prep/Sdbmlt e MCC's Resubmittal Review/Approve ATS Fabrication 20 152 25-Jan-23 18-Jul-22A 21-Feb-23 21-Feb-23 ATS Prep/Submit 76 28-Jul-22A 11-Nov-22A 6540 9672 9682 PANELBOARDS 6590 ATS Review/Approve 20 14-Nov-22A 13-Dec-22 I I I 6540 010 967� 96 I 6590 ATS Review /Appro e IN ATS Resubrnittal'; 2 Imo; ATS ResUbm,ittal;Review,/Approve Fanelboards Prep/SUbmit ATS Resubmittal 15 04-Jan-23 24-Jan-23 ATS Resubmittal Review/Approve Panelboards Prep/Submit 20 89 25-Jan-23 28-Jul-22A 21-Feb 23 02-Dec-22A 6600 PanelboardsReview /Approve 20 05-Dec-22A 03-Jan-23 I I I I 6600 I 069� 97 I 01 Pan?IboerdsReview/ Approve Panelboards Res,ubmitta;l 2 Panelgoar,ds kesubmittal Review 1A 6610 Panelboards Fabrication pprpve; 9692 Panelboards Resubmittal 15 04-Jan-23 24-Jan-23 9702 Panelboards Resubmittal Review/Approve 20 25-Jan-23 21-Feb-23 6610 Panelboards Fabrication TRANSFORMERS 30 22-Feb-23 04-Apr-23 6620 6630 9712 9722 6640 Transformers Prep/Submit 89 28-Jul-22A 02-Dec-22A I I 6620 6630 I 071 97 ransformers Prep Submit T;ransfor;mersHeview/'Approve Transformers Rpsubmittpl ; 2 Transformers ResubMittal Review/ 6 401 Transfor rierslFabricatio tkIpprove Transformers Review/Approve 20 05-Dec-22A 03-Jan-23 Transformers Resubmittal 15 04-Jan-23 24-Jan-23 Transformers Resubmittal Review/Approve 20 25-Jan-23 21-Feb-23 Transformers Fabrication 20 22-Feb-23 21-Mar-23 ACTIVE HARMONIC FILTER 6650 Active Harmonic Filters Prep/Submit I I 6650 A 6660 ti eHarmonicFiilters P'rep';/Submit ctve Harmonic Filters Rpvieyv/Approvp 74 28-Jul-22A 09-Nov-22A 6660 Active Harmonic Filters Review/Approve 20 10-Nov-22A 09-Dec-22A VERSION 12-Dec-22 DATA DATE: 12-Dec-22 ROCKY RIVER WWTP PROJECT SCHEDULE 12-Dec-22 PAGE 3 OF 17 RR-09 (12-12-22) CROWDER CONSTRUCTION TASK ID TASK WORK DAYS START DATE FINISH DATE A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 9732 Active Harmonic Filters Resubmittal 15 Active Harmonic Filters Resubmittal Review /Approve 20 04-Jan-23 24-Jan-23 I 973 9742 �;Active Ha'rmQnic!Fllters Reswbmiftal Active Harmonic Filters Resubmittal Review /Alpprove 9742 25-Jan-23 21-Feb-23 6670 VFD 6700 Active Harmonic Filters Fabrication VFDs Fabrication 120 205 22-Feb-23 18-Jul-22A 10-Aug-23 05-May-23 I I 6700 068Q O' VFDs; 66901 O VFDs 6 70 I Active Harrhon 0000000100 VFDs Fabrication r p/Submit, Review /Approve 3 Filters Fabricatioh 6680 VFDs Prep/Submit 40 28-Jul-22A 22-Sep-22A 6690 VFDs Review/ Approve 10 23-Sep-22A 06-Oct-22A 7050 VFDs Resubmittal 58 07-Oct-22A 30-Dec-22 I I 7050 7060 I 075� 9; 11300 1320 131, 67170 VFDs Resubmittal r, VFDs Resubmittal Review Approve V1FDs';Resubrnittal 2 �; VrDs;Requbr Resubmittal Review /Approv Substation Shc'p DYawi'ngs' Prep /'Submit Substation Fbbrioati No Substation Shop Drawings' Review /A Instrumentation Shop Drawings PrepJ Submit n Dprove' 7060 VFDs Resubmittal Review/Approve 20 03-Jan-23 30-Jan-23 9752 VFDs Resubmittal 15 20 113 04-Jan-23 25-Jan-23 28-Jul-22A 24-Jan-23 21-Feb 23 09-Jan-23 9762 SUBSTATIO 1300 VFDs Resubmittal Review /Approve Substation Shop Drawings Prep/ Submit 1320 Substation Fabrication 210 29-Aug-22A 26-Jun-23 1310 INSTRUMENTATION 6770 Substation Shop Drawings Review /Approve Instrumentation Shop Drawings Prep/ Submit 20 60 10-Jan-23 17-Oct-22A 06-Feb 23 12-Jan-23 6780 6790 AIR DISTRIBUTION 2410 Instrumentation Shop Drawings Review /Approve 20 13-Jan-23 09-Feb-23 I 678 7 I 241Q MEWOMEk::]', 242Q Insttum'ent�tiohShop Drawings R'evi 0 MONIONOMMEM Instrumentation A r Distributign Piping S op braving Prep /; Su Air Distribution Piping Shop Drawing Revie w/Approve abrication' mid /Approve Instrumentation Fabrication PIPING Air Distribution Piping Shop Drawing Prep /Submit Air Distribution Piping Shop Drawing Review /Approve 120 85 20 10-Feb-23 28-Jul-22 A 29-Nov-22 A 31-Jul-23 28-Nov-22 A 27-Dec-22 2420 2430 2440 *AirDistribution Piping Fabrication ctuators Shop Drawing Prep /Submit 80 86 28-Dec-22 01-Jun-22A 19-Apr-23 30-Sep-22 A I I 2430 $440 Vpiv / I �450 ',0 Valve 2460 E=M Air'.Distributioh PipinglFabric ctuators Shop Dewing P,rep';/S ubrnit / Actuators Shop Drawing e✓iew j Approve Valves Fabrication tioVALVES 2450 Valves /Actuators ShopDrawing Review/Approve 5 03-Oct-22A 07-Oct-22 A 2460 Valves Fabrication 90 17-Oct-22A 23-Feb 23 3220 VEMMINE 2470 Actuators Fabricaton DIFFUSERS Membrane Diffusers Shop Drawing Prep/ Submit 150 96 17-Oct-22A 14-Jul-22A 18-May-23 29-Nov-22A I I I 3220 2470 �'; 484 2490 I 2500 O ';Mixers E hc 2510 '; C) Mixeq �760 Ir--J 27701 11 !Actuators Fabricaton Memorane diffusers Shop Drawing Prep /!Submit!; Mpmbrare giffugerq Shpp Drawing Revie Membrane Diffusers Fabrica pDrawing Prep /Submit ' hop', Drawing Review/';Approve ers;Requbrnittpl erS Resubmittal Review/!Approve /A,pprgve; ion', 2480 Membrane Diffusers Shop Drawing Review /Approve 20 30-Nov-22A 28-Dec-22 2490 MIXERS 2500 Membrane Diffusers Fabrication "MixersShoping Prep/Submit 80 33 29-Dec-22 28-Jul-22A 20-Apr-23 13-Sep-22A 2510 MixersShop Drawing Review /Approve 14 14-Sep-22A 03-Oct-22A 2760 Mixers Resubmittal 34 04-Oct-22A 18-Nov-22A 2770 Mixers Resubmittal Review/Approve 3 21-Nov-22A 23-Nov-22A 2520 SLIDE GATE 3480 Mixers Fabrication Slide Gates Shop Drawing Prep/Submit 110 58 28-Nov-22A 15-Jun-22A 02-May-23 06-Sep-22A I 2520 I 34$0'; Slide Gat 13490 Slidg Mixers Fabrication Shop drawing';Prep/Sub;mit'; tes;Shop Drawing! Review/ Approve ; 3490 Slide Gates Shop Drawing Review/Approve 23 07-Sep-22A 07-Oct-22A VERSION 12-Dec-22 DATA DATE: 12-Dec-22 ROCKY RIVER WWTP PROJECT SCHEDULE 12-Dec-22 PAGE 4 OF 17 RR-09 (12-12-22) CROWDER CONSTRUCTION TASK ID TASK WORK DAYS START DATE FINISH DATE A M J J A S O N DJIFIMIAIMIJIJIAISIOIN15JIFIMIAIMIJIJIAISIOINIII J A S O N D J F M A M _ 3500 I Slide Gates Fabrication 80 9552 Slide Gate Actuators Fabrication 260 SHORING SYSTEM 4000 Shoring System Procurement @ NEF Junction Box 44 FLUME 103 4180 Flume Shop Drawing Submit 15 24-Oct-22A 16-Feb-23 31-Oct-23 14-Oct-22A 18-Nov-22A 3500 Slide Gates Fabrication 24-Oct-22A 15-Aug-22A 31-Oct-22A I 95521 400Shor n I 418p ❑ 1 Slide System Procurement @'NEF Junction Box u e Shop Drawing', Submit', GateActuators Fabrication 6940 Flume Shop Drawing Review /Approve 13 21-Nov-22A 09-Dec-22A I I 69401 E 6950 4440', 445(5 Flume Shop Drawing Review /,Approve I I Flume' Fabrication 0 Handrail Shop Drawings! Prep/;Suomit',@ Handrail Shgp D,rawingq Review /pppr B6 ve, @AB6 6950 HANDRAI 4440 Flume Fabrication Handrail Shop Drawings Prep / Submit @AB6 50 88 12-Dec-22 25-Aug-22A 21-Feb 23 30-Dec-22 4450 Handrail Shop Drawings Review pprove @AB6 20 03-Jan-23 30-Jan-23 4400 6710 Handrail Fabrication @AB6 Grating Embeds Shop Drawings Prep / Submit @AB6 50 88 31-Jan-23 25-Aug-22A 10-Apr-23 30-Dec-22 4 6710' 6720 5 3 Handrail Fabrication @AB6 Grating Embeds Shop Drawings PrepY S 00 Crating E=mbeds, Shop Drawings Revi Grating!, Embeds Fgbrigatign (A bmit @'AB6 /Approve @ AB6 6 6720 6730 Grating Embeds Shop Drawings Review /Approve @ AB6 20 03-Jan-23 30-Jan-23 Grating Embeds Fabrication @AB6 30 31-Jan-23 13-Mar-23 METAL STAIRS 6740 Metal Stairs Shop Drawings Prep Submit @AB6 I 6740 6 I Metal Stairs Shop Drawings Prep /ISu 50 00 M'etal' Stairs Shop Drawings, Review E 760 0000 Metal Stairs, Fabrication @ mit @AB6 /approve @ AB6 AB6 41 20 50 02-Nov-22A 01-Feb-23 01-Mar-23 31-Jan-23 28-Feb-23 09-May-23 6750 Metal Stairs Shop Drawings Review /Approve @ AB6 6760 Metal Stairs Fabrication @AB6 ODOR CONTROL COVERS 9562 9592 Odor Control Cover Shop Drawings Prep / Submit 52 17-Oct-22A 30-Dec-22 9562 95921 9572 9 8 Odor! Control! Cover'Shop Drawings Prep / 1 As Built Meter Vaults r, Odor'Cohtrol Cover Shop Drawings Review Odor Control Submit /Approve Cover Fabrication - deter Vaults 9Q12, As BuiltraW tythiCke jar As Built Meter Vaults 5 23-Dec-22 30-Dec-22 9572 Odor Control Cover Shop Drawings Review /Approve 20 03-Jan-23 30-Jan-23 9582 Odor Control Cover Fabrication - Meter Vaults 180 31-Jan-23 12-Oct-23 9612 As Built Gravity Thickener 5 27-Mar-24 02-Apr-24 9622 SITEWORK 2080 Odor Control Cover Fabrication - Gravity Thickeners Mobilization 180 10 03-Apr-24 01-Jun-22A 17-Dec-24 14-Jun-22A I I I 2080 C ',Mobilization 2010 0', Ergs id Cpntrpl I 9622 Odor Control Cover 2010 Erosion Control 5 15-Jun-22A 21-Jun-22A 2020 Temporary Construction Access Roads 10 15-Jun-22A 28-Jun-22A I I 2020 ❑ Temporary Const 20001 0 Asphalt Dembliti0 1850 IN' As i 8290 00 2230 1 c ion'Access Roads F eld'Reclamation @ Phase 3' C iradeG;ravel Access Road Dugtbgnk Md, 2000 Asphalt Demolition 5 22-Jun-22A 28-Jun-22A 1850 Ash Field Reclamation @ Phase 3 16 07-Oct-22A 28-Oct-22A 3290 Grade Gravel Access Road 23 31-Oct-22A 02-Dec-22A 2230 Ductbank MC 2 19-Dec-22* 20-Dec-22 1990 Ductbank 105 10 24-Apr-23 05-May-23 19901 ■ Ductbank 105 2046, MEN Ductbank 102 -IEQI (East)! 1970' EEE 2140 2160 uctbank101 00 Fine, Grading EE Asphalt Paving 2040 Ductbank 102 - EQ (East) 30 26-Apr-23 07-Jun-23 1970 Ductbank101 33 25-Oct-23 12-Dec-23 2140 Fine Grading Asphalt Paving 22 10-Jan-24 08-Feb-24 2160 22 24-Jan-24 22-Feb-24 VERSION 12-Dec-22 DATA DATE: 12-Dec-22 ROCKY RIVER WWTP PROJECT SCHEDULE 12-Dec-22 PAGE 5 OF 17 RR-09 (12-12-22) CROWDER CONSTRUCTION TASK ID TASK WORK DAYS START DATE FINISH DATE A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 1980 Ductbank - Site Lighting Ductbank 102 -TSPS (West) 21 20 06-Feb-24 05-Mar-24 I I I I 3580 II 3/4' 3610 I 11980 133 f amer + Flume1103 30'1 / 15" / 24' Storm Draih - Maihtenance C 8 0 M 121n TD AB6 to M'H27 $740 PO INFM;V to MH-A';1 QuctbanR- ite;Llghting Ductbank 102 - ITSPS (West) 0 Sidewalks I nopy 2130 I♦ Final 8812 07-Feb 24 05-Mar-24!8812 3390 Sidewalks 18 09-Feb-24 05-Mar-24 2130 .D PIPING 3580 Final Seeding 10 31-Mar-25 11-Apr-25 3/4' Defoamer - Flume 103 5 03-Oct-22A 07-Oct-22 A 3610 30" / 15" / 24' Storm Drain - Maintenance Canopy 10 07-Dec-22 A 20-Dec-22 3830 12in TD AB6 to M H27 29 13-Feb-23 23-Mar-23 3740 2" PD INFMV to MH-A1 3 03-Apr-23* 05-Apr-23 3840 12" TD - AB6 to M H33 1 12-Apr-23 12-Apr-23 I I 3840 1 12";7D L AB6 to M H33, 37601 1 Relocate I2'",NPW Box 1 3620 M361' MLtoAB6 3640 42" 3590' 10 12" Storm /Frehch!Dre RS' Bok 10 to EQ Tank in 3760 Relocate 12" NPW - Box 10 4 26-Apr-23 01-May-23 3620 36" MLtoAB6 15 02-May-23 22-May-23 3640 42" RS Box 10 to EQ Tank 141 02-May-23 17-Nov-23 3590 12" Storm /Trench Drain 10 23-May-23 06-Jun-23 3630 42" MLAB6 toAB5 10 23-May-23 06-Jun-23 I I 3630 16 42" MLABF,toAB5, 3690 I1 10"IWAS at W 380¢0 6' Scum at G1 3710 '■ '12in/6in NPW 3680 4"/ 6'' PVV t S PS 3/4 SPS/GTs' ECG Tank 3690 10" WAS at WAS PS 6 07-Aug-23 14Aug-23 3800 6" Scum at GT 3/4 6 07-Aug-23 14Aug-23 3710 12in/6in NPW TSPS/GTs 9 07-Aug-23 17-Aug-23 3680 4" / 6" PW to EQ Tank 19 07-Aug-23 31-Aug-23 3810 6" PS to GT 3/4 7 15-Aug-23 23-Aug-23 I I 3810 1 6";PS;to OT 3780 M 4in/Qin TIS 3790' M '6" /18" TD 3700 I♦ 12'' P© 382b ;1 18in FA';GT /4 GT 3/4 erflow to Existing M H9 3/44o Ex 3780 4in/6in TS 14 18-Aug-23 07-Sep-23 3790 6" / 8" TD GT 3/4 16 24Aug-23 15-Sep-23 3700 12" PD Overflow to Existing M H9 13 01-Sep-23 20-Sep-23 3820 18in FA GT 3/4 to Ex 2 08-Sep-23 11-Sep-23 3650 24' NEF - NEF Box to EQ Tank 46 15-Sep-23 17-Nov-23 I I I I I I 3650 EJEW ;24" 37170 8" WA 3670 1 14' Tank 3850 1 4' DI n $730 M $0" NE,F - NEH Box to EQ Tank 3 from Existing to GT 3/4 Drain ; EQ Tank to 24' Tank Drain ar'Box 10' Overflow Pipe 3770 8" WAS from Existing to GT 3/4 23 18-Sep-23 18-Oct-23 3670 4" Tank Drain - EQ Tank to 24' Tank Drain 3 13-Oct-23 17-Oct-23 3850 4" DI near Box 10 2 18-Oct-23 19-Oct-23 3730 60" Overflow Pipe 6 01-Nov-23 08-Nov-23 3660 18" / 24' Tank Drain - EQ to B101 2" PD EFFMV to BOX101 6 & BOX ON GRADE Excavation @ AB 6 30 20-Nov-23 04Jan-24 I I I 1$40'; ';Exo,avation,@', 3060 3750 1,8" /;24'lank Drain;- EQ to B1,01 1 2" PD EFFMV to BOX'1011 3750 AERATIONNO. SITEWORK/SLABS 1340 3 05-Jan-24 09-Jan-24 16 23-Jun-22A 15-Jul-22A 3210 Ductbank Removal @AB 6 5 28-Jul-22A 03-Aug-22A I Q21Q Quctoank Re 1360 IO Balance 56701 ❑ FRP! SO 1370' Stone 5680 ; 0 ';FRP S cval @AB x avdtion @' AB! 6 - Pour #1 (cD AB 6 AB'6 ; ; ; ; ; Pour #2 @ Ag 6' ; ; ; ; ; 1360 Balance Excavation @AB 6 26 04Aug-22A 09-Sep-22A 5670 FRP SOG -Pour #1 @ AB 6 11 22-Aug-22 A 06-Sep-22 A 1370 Stone @ AB 6 29 22-Aug-22 A 30-Sep-22 A 5680 FRP SOG - Pour #2 @ AB 6 5 07-Sep-22 A 13-Sep-22 A 1490 Underslab Piping @ AB 6 13 07-Sep-22A 23-Sep-22A 1490 ❑; Unders Piping,@ABA VERSION 12-Dec-22 DATA DATE: 12-Dec-22 ROCKY RIVER WWTP PROJECT SCHEDULE 12-Dec-22 PAGE 6 OF 17 RR-09 (12-12-22) CROWDER CONSTRUCTION TASK ID TASK WORK START DATE FINISH DATE DAYS A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 5690 FRP SOG - Pour #3 @ AB 6 4 FRP SOG - Pour #4 @ AB 6 3 12-Sep22 A 15-Sep22 A 5690 0 IFR S 57bo 1 I `RIP S 5710 1 FRP S 5720' 1' FRPSD - Pour #3 @ A,B 6, - Pour, #4 @ AB 6 - Pour #51@ AB 6 - Pour #6 @ AB'6 5700 16-Sep22 A 20-Sep22 A 5710 FRP SOG - Pour #5 @ AB 6 4 19-Sep22 A 22-Sep22 A 5720 FRP SOG - Pour #6 @ AB 6 3 23-Sep22 A 27-Sep22 A 6250 FRP SOG - Pour #7 @ AB 6 2 24-Oct-22A 25-Oct-22 A 6�50'1 I, FF2 6310, 1, FIR 6320, 1 FF P 1500 I FI OCg - Pour #7', @ AB 5 30Q - Pour #8, @ AB 6 SOG -!Pour #9 @AB! 6 P SOG -I Pour #10 (Q AB 61 6310 FRP SOG - Pour #8 @ AB 6 2 26-Oct-22 A 27-Oct-22 A 6320 FRP SOG - Pour #9 @ AB 6 3 28-Oct-22A 01-Nov-22 A 1500 FRP SOG -Pour #10 @ AB 6 2 02-Nov-22 A 03-Nov-22 A WALL POUR 6300 FRP Wall - Pour #1 (Wall Crew #1) @AB 6 3 10 31-Oct-22A 03-Nov-22 A 02-Nov-22A 12-Nov-22 A I 6300 1 F', $40b In ur P Wall - Pour #1',(We11 Crew #1) @¢113;6 D Wall Pour 01 (Wall Crew #1) a AO 6 6400 1 Cure Wall - Pour #1 (Wall Crew #1) @ AB 6 WALL POUR #2 9052 FRP Wall - Pour #2 (Wall Crew #2) @ AB 6 4 10 03-Nov-22 A 09-Nov-22 A 08-Nov-22 A 18-Nov-22 A 9052 '0 171 ZF 9072 ❑ VVe11- Pour #2 (Wall Crew #2) @ AB 6 u e Wall'- Pour #2 (Wall' Crew #2) @ AB 6' 9072 Cure Wall - Pour #2 (Wall Crew #2) @ AB 6 WALL POUR #3 I I 6 03-Nov-22 A 10-Nov-22 A 8822 FRP Wall - Pour #3 (Wall Crew #1) @ AB 6 I $82� 0 PRPVV411-,Pour 8832 0 #$ (\/Wall Grew #1) @ AE� 6 u e Walk- Pour #3 (Wall Crew #1) @ AB 6 8832 Cure Wall - Pour #3 (Wall Crew #1) @ AB 6 10 11-Nov-22 A 20-Nov-22 A WALL POUR #4 9062 FRP Wall - Pour #4 (Wall Crew #2) @ AB 6 7 09-Nov-22 A 17-Nov-22 A 9062 I R D Wall Pour #4 (Wall' Crew #2) @ AB 6' 9092 Cure Wall -Pour #4 (Wall Crew #2) @ AB 6 10 18-Nov-22 A 27-Nov-22 A 9d92 ■', C re Wall - Pour #4'(VVall Crew! )!@ @ AB 6 WALL POUR #5 I I 8842 FRP Wall - Pour #5 (Wall Crew #1) @ AB 6 4 10 11-Nov-22 A 17-Nov-22 A 16-Nov-22 A 26-Nov-22 A 8842 1 8852 ■I CureWall R Wall Pour #r (WaIIICrew #0) @ AB 61 - Pourl#5 (VVd11 Crew #1) I@ AB 6 8852 Cure Wall - Pour #5 (Wall Crew #1) @ AB 6 WALL POUR #8 9102 FRP Wall - Pour #8 (Wall Crew #2) @ AB 6 4 10 17-Nov-22 A 23-Nov-22 A 22-Nov-22 A 02-Dec-22 A I 9102 9132 111 P Wa11',- Pqur #8 (Wall Crpw d¢2) @ AB 6 C ure,Wall - Four #8', (V\b11 Grew #2) @, AB, 6 9132 Cure Wall - Pour #8 (Wall Crew #2) @ AB 6 WALL POUR #6 I I 9082 FRP Wall - Pour #6 (Wall Crew #2) @ AB 6 6 10 18-Nov-22 A 30-Nov-22 A 29-Nov-22 A 09-Dec-22 A 9082 ❑I 9112 F P Wall - Pourl#6 (Well Crewl#2)I @ AB 6 C ure Wall -!Pour #6 (Wall Crew #2) @ AB 6 9112 Cure Wall - Pour #6 (Wall Crew #2) @ AB 6 WALL POUR #7 4 23-Nov-22 A 30-Nov-22 A 8862 FRP Wall - Pour #7 (Wall Crew #1) @ AB 6 I 8$62, OI 8872 E FIRP Wall - Pour1#7 (Wall Crewe,#1), @ AB ¢ Cure Wall -,Pour #7 (Wall Crew #1) @ AB 6 8872 Cure Wall -Pour #7 (Wall Crew #1) @ AB 6 10 01-Dec-22 A 10-Dec-22 A WALL POUR #9 I I 8882 FRP Wall - Pour #9 (Wall Crew #1) @ AB 6 3 01-Dec-22 A 05-Dec-22 A 8882 0 F RPM/all - Pour #9' (Wall Crew #1) @'AB'6 8892 Cure Wall - Pour #9 (Wall Crew #1) @ AB 6 10 06-Dec-22 A 15-Dec-22 889 ure Vy/all -, Pour 49 (Wall Crew #';1) Q A0 6 WALL POU 9122 FRP Wall -Pour #10 (Wall Crew #2) @ AB 6 5 10 30-Nov-22 A 07-Dec-22 A 06-Dec-22 A 16-Dec-22 9122 0 9152 1 F RPIVUdII -Pour #10 (Wall Crew #2) @ AB 6 Cure Wall, Pour #10 (VVa'll Crew 92) I@ AB 9152 Cure Wall - Pour #10 (Wall Crew #2) @ AB 6 WALL POUR #11 I I 8902 FRP Wall - Pour #11 (Wall Crew #1) @ AB 6 3 06-Dec-22 A 08-Dec-22 A 890� I 891,2 RP' Wall -Pour #1'1 ( Wall Crew #1) @ AB 6 Cure Wall Pour #11 (Wall Crew #1),@ AB 13 8912 Cure Wall - Pour #11 (Wall Crew #1) @ AB 6 10 09-Dec-22 A 18-Dec-22 ROCKY RIVER WWTP VERSION 12-Dec-22 DATA DATE: 12-Dec-22 PROJECT SCHEDULE PAGE 7 OF 17 RR-09 (12-12-22) 12-Dec-22 CROWDER CONSTRUCTION TASK ID TASK WORK START DATE FINISH DATE DAYS A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA M J J A S O N D J F M A M WALL POUR #12Mod9142 FRP Wall - Pour #12 (Wall Crew #2) @ AB 6 37MOTDec-22A 09-Dec-22 A 19-Dec-22 9142 9172 1 RP, Wall - Pour #12 (Wall)Crew #2) @ AB 6 Cute WallPour #12!(VVall Crew! #2)! @ AB 9172 Cure Wall - Pour #12 (Wall Crew #2) @ AB 6 10 10-Dec-22 A WALL POUR #16 4 08-Dec-22 A 13-Dec-22 9182 FRP Wall - Pour #16 (Wall Crew #2) @ AB 6 918'2 9212 1 RP Wall -',Pour #16 (Wall Crow 92) @ AB Cure Wall',- PQur #16, (Wall Grew #2) @'',AB 6 9212 Cure Wall - Pour #16 (Wall Crew #2) @ AB 6 10 14-Dec-22 23-Dec-22 WALL POUR #1 I I 8942 FRP Wall - Pour #15 (Wall Crew #1) @ AB 6 4 09-Dec-22 A 14-Dec-22 8942 1 FRP Wall -I Pour #15 (Wall Crew #1) @ AB 8952 Cure Wall - Pour #15 (Wall Crew #1) @ AB 6 10 15-Dec-22 24-Dec-22 8952 ■ Cure Wall' - Pour'#15 (Wall Crew #1) @'AB 6 WALL POUR #19 8982 FRP Wall - Pour #19 (Wall Crew #1) @ AB 6 4 12-Dec-22 15-Dec-22 I 89$2 1 I 8992 1 FRS' V\tall -', Pour #19 (Wall Crew #1) '@ AB Cure Wall',- Pour',#19 (Wall Crew #1) @IAB 6 8992 Cure Wall - Pour #19 (Wall Crew #1) @ AB 6 10 16-Dec-22 25-Dec-22 WALL POUR #13 I I 8922 FRP Wall - Pour #13 (Wall Crew #1) @ AB 6 5 14-Dec-22 20-Dec-22 8922 1 8932 FRP Wall = Pour 913 (Wall Crew'#1)' @ AB 13 Cure'Wall - Pour; #13 (Wall Crew #1,) @ AQ 6 8932 Cure Wall - Pour #13 (Wall Crew #1) @ AB 6 10 21-Dec-22 30-Dec-22 WALL POUR #14 9162 FRP Wall - Pour #14 (Wall Crew #2) @ AB 6 Cure Wall - Pour #14 (Wall Crew #2) @ AB 6 5 10 15-Dec-22 22-Dec-22 21-Dec-22 31-Dec-22 9162 1 9192 FRP Wall ',, Pour #14(Wall Crewl#2)I @ AB 1 Clare) Wall - Pout #14 (Wall Crew #K2) (cD AE1 6 9192 WALL POUR #18 4 19-Dec-22 22-Dec-22 9202 FRP Wall - Pour #18 (Wall Crew #2) @ AB 6 9202 9232', 1 FRP Wall'- Pour 918'(Wall Carew #2) @';AB Cure, Wall - Four #18 (Wall Crew 0) @ A 6 9232 Cure Wall - Pour #18 (Wall Crew #2) @ AB 6 10 23-Dec-22 01-Jan-23 WALL POUR #17 I I 8962 FRP Wall - Pour #17 (Wall Crew #1) @ AB 6 4 23-Dec-22 29-Dec-22 89621 FRP Wall -Pour!#17 (Wall Crew #11) @ AE 6 8972 Cure Wall -Pour #17 (Wall Crew #1) @ AB 6 10 30-Dec-22 08-Jan-23 8972 1 Curb Wall -!Pour #17 (Wall' Crew 91) @ AB 6' WALL POUR #21 9002 FRP Wall - Pour #21 (Wall Crew #1) @ AB 6 5 10 28-Dec-22 05-Jan-23 04-Jan-23 14-Jan-23 I 9002 9012 1 ARP, Wall - Four #21 (Wall Crew #1) @ AB 1 Cure Wall Pour #21 (Wall Crew #1) '@ AB 6 6 ' 9012 Cure Wall - Pour #21 (Wall Crew #1) @ AB 6 WALL POUR I I 9222 FRP Wall - Pour #20 (Wall Crew #2) @ AB 6 4 30-Dec-22 05-Jan-23 9222 925� FRP Wall - Pour #20 (Wall Crew #2,) @ Al6! ■ ;Cure Wall 1 Pour #r20 (Wa';II Crew #2)!@) B C 9252 Cure Wall -Pour #20 (Wall Crew #2) @ AB 6 10 06-Jan-23 15-Jan-23 UPPER AERATION SLAB POURS 9282 FRP Upper Aeration Slab -Pour #1 @ AB 6 5 29-Dec-22 05-Jan-23 9282 9292 1 FRP Upper Aeration Slab -, Pour #1 @ AB 1 FRP UpperlAetatidn Slab; Pour #2 (cll AB 6 6 9292 FRP Upper Aeration Slab - Pour #2 @ AB 6 5 04-Jan-23 10-Jan-23 WALL POUR #22 I I 9242 FRP Wall - Pour #22 (Wall Crew #2) @ AB 6 4 05-Jan-23 10-Jan-23 I 924� 92t 1 �RP Well -';Pour #�2 (Wall', Crew #2) @ A ■ Cure Wall'!- Pour j#22',(VVall Crew, #2), @ B 6, AB;6 9272 Cure Wall - Pour #22 (Wall Crew #2) @ AB 6 10 11-Jan-23 20-Jan-23 WALL POUR #23 9022 FRP Wall - Pour #23 (Wall Crew #1) @ AB 6 4 06-Jan-23 11-Jan-23 9022 1 FRP Wall -Pour #23 (Wall! Crow #1) @ A B 61 9042 Cure Wall -Pour #23 (Wall Crew #1) @ AB 6 10 12-Jan-23 21-Jan-23 904 1 ',Cure Wall'- Pour #23'(VVall Crew #1)' @ B 6 WALL POUR #24 9302 FRP Wall - Pour #24 @ AB 6 4 11-Jan-23 16-Jan-23 93$ 1 FRp Wall Pour #24 @ AB 6 ROCKY RIVER WWTP VERSION 12-Dec-22 DATA DATE: 12-Dec-22 PROJECT SCHEDULE PAGE 8 OF 17 RR-09 (12-12-22) 12-Dec-22 CROWDER CONSTRUCTION TASK ID TASK WORK DAYS START DATE FINISH DATE 4jAjMjJjJjAjS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 9312 Cure Wall - Pour #24 @AB 6 10 17-Jan-23 ALL POUR #25 9322 FRP Wall - Pour #25 @ AB 6 4 17-Jan-23 26-Jan-23 I 931 9 912 9472 9482 1, Core Wall - Pour,#2 @AB,6 1 FRP Wall, Pour #25 @ AB 6 r Cure'Wall - Pout #25 @ AB 6 1 Form Walkway, Pour #2 @ AB 6, I Electric! al R/I Walkway!- Pour #2 @ A'B 6 20-Jan-23 9332 WALKWAY 9472 Cure Wall - Pour #25 @AB 6 POUR #2 Form Walkway - Pour #2 @ AB 6 10 2 21-Jan-23 04-Jan-23 30-Jan-23 05-Jan-23 9482 Electrical R/I Walkway - Pour #2 @ AB 6 5 06-Jan-23 12-Jan-23 9372 Pour Walkway -Pour #2 @ AB 6 1 13-Jan-23 13-Jan-23 I 937 938 95p 94,c 2 1 Polar Walkway!- Pour #2 Q AIB 61 1 Cure Walkway - Pour #2'@ AB 6 I ,Form Walkway- Four, #3;@ AB 1Electrical',R/I Walkway - Pour #3 @'AB 9382 WALKWAY 9502 Cure Walkway -Pour #2 @ AB 6 POUR Form Walkway - Pour #3 @ AB 6 7 2 14-Jan-23 16-Jan-23 20-Jan-23 17-Jan-23 9492 Electrical R/I Walkway- Pour #3 @AB 6 5 18-Jan-23 24Jan-23 9392 9402 WALKWAY 9512 Pour Walkway - Pour #3 @ AB 6 1 25-Jan-23 25-Jan-23 I I 93 9' I 9512 95 2 2 1' Pour Walkway - Pour #3 @ AB 6 2 1 Cure Walkway -' Pour #3 @ AB 6 1 Form Walkway - Four #4;@ AB 11 Electrical!R/I ,Walkway - Poor #4 @AB 6 Cure Walkway - Pour #3 @ AB 6 POUR #4 Form Walkway - Pour #4 @ AB 6 Electrical R/I Walkway - Pour #4 @ AB 6 7 2 5 26-Jan-23 18-Jan-23 20-Jan-23 01-Feb-23 19-Jan-23 26-Jan-23 9522 9412 9422 WALKWAY 9532 Pour Walkway - Pour #4 @ AB 6 1 02-Feb-23 02-Feb-23 I 9412 9 122 I 9$2 95 1 Pout W21kWay Pour #4 @AB 6 1 Cure Walkway', Pour #4 @ AB 6' 1',Form Walkway -Poor #5@',AB,6 2 1 Electrical R/11 Walkway -I Po I or# I 5@AE 6 Cure Walkway - Pour #4 @ AB 6 POUR #5 Form Walkway - Pour #5@AB6 7 2 03-Feb-23 23-Jan-23 09-Feb-23 24Jan-23 9542 Electrical R/I Walkway- Pour #5 @AB 6 5 25-Jan-23 31-Jan-23 9432 Pour Walkway - Pour #5 @ AB 6 1 7 2 5 10-Feb-23 11-Feb-23 31-Jan-23 02-Feb-23 10-Feb-23 17-Feb-23 01-Feb-23 08-Feb-23 432 9 9 1 Poor Walkway � Pour #5 (n AB 61 412 I Cure Walkway - Pour'#5 @ AB 6 Form Walkway Pour tit @AO6 1 Electrical R/I Walkway' Pour #1 @A 3 61 9442 WALKWAY 9462 Cure Walkway - Pour #5 @ AB 6 POUR #1 Form Walkway - Pour #1 @AB6 9452 Electrical R/I Walkway- Pour#1 @AB 6 Pour Walkway - Pour #1 @ AB 6 Cure Walkway - Pour #1 @AB6 /TESTING / STARTUP Grounding @ AB 6 9352 9362 EQUIPMENT 6370 1 20-Feb-23 20-Feb-23 9352 Q37p ',p I Poor Walkway -Pour'. #1! AB 6 9 62' 1 Core Walkway - Poor #1 @'AB'6 o jnding@AB6, Field Measure & Fab',Misc Metals @ AB 6 7 5 21-Feb-23 04Nov-22A 27-Feb-23 10-Nov-22A 4340 Field Measure & Fab Misc Metals @ AB 6 50 13-Feb 23 21-Apr-232 4490 Slide Gates @ AB 6 11 28-Feb 23 14Mar-23 I I I I 0 0 Slide Gates @AB16 1640 Concrete'Finish @A'B 6' 1500 No Leak Test @ A0 6'; 21y0 NO Oackfill @AB 9 2560 I Fine Bubble Diff uSerE @'AB 16 1640 Concrete Finish @AB 6 20 28-Feb 23 27-Mar-23 1590 Leak Test @ AB 6 20 15-Mar-23 11-Apr-23 2170 Backfill @AB 6 20 12-Apr-23 09-May-23 2560 Fine Bubble Diffusers @ AB 6 45 21-Apr-23 23-Jun-23 2530 Mixers @AB 6 15 03-May-23 23-May-23 2530 m Mixers @AB16 4410 I ';Metal Stair's @AB 6 2540' 1000 ';Pipe Supports 2550 06 Coarse Bob @ AB 6 le Diffusers @ AB 6 4410 Metal Stairs @ AB 6 5 10-May-23 16-May-23 2540 Pipe Supports @ AB 6 35 26-Jun-23 14Aug-23 2550 Coarse Bubble Diffusers @ AB 6 15 15-Aug-23 05-Sep-23 VERSION 12-Dec-22 DATA DATE: 12-Dec-22 ROCKY RIVER WWTP PROJECT SCHEDULE 12-Dec-22 PAGE 9 OF 17 RR-09 (12-12-22) CROWDER CONSTRUCTION SKID TASK WORK DAYS START DATE FINISH DATE A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 4420 Metal Handrails @AB 6 50 Stainless Air Distribution Piping @ AB 6 35 15-Aug-23 24Oct-23 I I I I I I 4420 Metal 1580 Stainless 1660! 1 Ellect 4360' 1♦' Ex3osed 4390 01 ';Ins 443Q E; M andralls @ AB 6; Air Distribution Piping @ AIB 6 icall Pahels & Gear @IABI6 BlectricN Conduit RJI @AB 6 runjentatiop @AB6 tal Grating;@AB 6 1580 06-Sep 23 24Oct-23 1660 Electrical Panels & Gear @AB 6 5 25-Oct-23 31-Oct-23 4360 Exposed Electrical Conduit R/I @AB 6 20 25-Oct-23 21-Nov-23 4390 Instrumentation @AB 6 10 01-Nov-23 14Nov-23 4430 Metal Grating @AB 6 13 03-Nov-23 21-Nov-23 6330 Pull & Terminate Wire #12 / #6 @ AB 6 10 22-Nov-23 07-Dec-23 I I I I 6330! ■ Pull 6350 M 6340' 6860 1 433Q 11 & Terminate Wire #12 '/ #6 @IABI6 Pull1 & Terminate Wire Control!@ AB 6 Prep for Startup I Checkout'@ AB6' Site Lighting @ A$ 6 Rubber 0iffUser5 / testing @ AB6 6350 Pull & Terminate Wire Control @ AB 6 16 22-Nov-23 15-Dec-23 6340 Prep for Startup / Checkout @ AB6 44 22-Nov-23 26-Jan-24 6360 Site Lighting @ AB 6 3 18-Dec-23 20-Dec-23 4330 Rubber Diffusers / Testing @ AB6 5 28-Dec-23 04Jan-24 1670 1740 Checkout / Startup / Testing @ AB6 Excavate /Shoring /Stone @NEF Junction Box 35 38 29-Jan-24 24Oct-22A 15-Mar-24 16-Dec-22 I 1740' 1001 41,30 ; 1670 Excavate /'Shoring / Stone a@ NEF Junction 1 FRP Rase Slpb @ N,EF ;Junption Bqx ,Checkout /',Startup / Testing @ A Box 6 4130 FRP Base Slab @ NEF Junction Box 5 19-Dec-22 23-Dec-22 4120 FRP Walls @ NEF Junction Box 20 27-Dec-22 24Jan-23 I I 41201 39 I I FRP Walls @ NEF J nctionlBox 0 Leak Test!@ NEF Junction Box 4 40* Badkfill'@ NEF Junction Box' 3990 1 ';Demo rzxis,ting,Pipe @ NEF Junction 4060 1 Misc Metals @ NEF Junction Bo Box 3980 Leak Test @ NEF Junction Box 20 25-Jan-23 21-Feb-23 4140 Backfill @ NEF Junction Box 15 22-Feb-23 14Mar-23 3990 Demo Existing Pipe @ NEF Junction Box 2 15-Mar-23 16-Mar-23 4080 Misc Metals @ NEF Junction Box 3 15-Mar-23 17-Mar-23 4110 Bypass Pumping @NEF Junction Box Slide Gates @NEF Junction Box Raise Box Elevation 8' @ Box 8 Excavation / Grading (No Blasting) @ EQ Tank 1 12 15-Mar-23 30-Mar-23 I I I I I I I I I I I I I I I I I I I I 4110 ■ Bypass Pumping @lNEF Junc 4100 ■ Slide (Gates o� NEFIJuhctioln Box I I I I I I I I I I I 1400 Raise Box!, Elevvation 8' @ Bo ion Box I I I I I I I I I I I < 8 I I I I I 4100 :• 1400 2250 10 15 10 17-Mar-23 03-Apr-23* 17-Oct-22A 30-Mar-23 21-Apr-23 28-Oct-22 A I 2250 ❑' Ex 2260 17�0 I a ation / Grading (No Blasting)'@ EQTank 1 lasting @ EQ;Tank 1 Excavation / Grading, (Post Blasting) @;EC Tank 1; 2260 Blasting @ EQ Tank 1 17 14Nov-22 A 08-Dec-22 A 1730 Excavation / Grading (Post Blasting) @ EQ Tank 1 10 09-Dec-22 A 22-Dec-22 1760 Underslab Piping @ EQ Tank 1 15 16-Feb-23 08-Mar-23 I I 17 I I iO W Underslab Piping @ EQ Tank 1 1750 ■ I Stone'@ EQ Tank 1 1 1550 Pre$tre 1410 ■'; Leak 68�O 00 Co sed Concrete'Tank -Ready for Leak'Test est';@ EQ;7ank 1 plete P,restres5ed;Concrpte tpnk @ Q �'Tar EQ Tahk 1 k 1 1750 Stone @EQTank 1 8 09-Mar-23 20-Mar-23 1550 Prestressed Concrete Tank - Ready for Leak Test @ EQ Tank 1 134 03-Apr-23* 10-Oct-23 1410 Leak Test @ EQ Tank 1 10 11-Oct-23 24Oct-23 6820 Complete Prestressed Concrete Tank @ EQ Tank 1 20 11-Oct-23 07-Nov-23 1450 Backfill @ EQ Tank 1 10 25-Oct-23 07-Nov-23 1450! ■ Bac 45801M IDiff 4460 Submersible 1780 On 4560, 11 dill @ EQ Tank 1 isers (cll EQ Tank 1 Mixers @';EQ',Tank 1' Electrical / IInstr;umentation, @';EQ! Tank 1 Air Piping to, NE,F Blowers @ EQ tank 1 4580 Diffusers @EQTank 1 15 25-Oct-23 14Nov-23 4460 Submersible Mixers @ EQ Tank 1 13 15-Nov-23 05-Dec-23 1780 Electrical / Instrumentation @ EQ Tank 1 20 13-Dec-23 11-Jan-24 4560 Air Piping to NEF Blowers @EQTank 1 7 27-Dec-23 05-Jan-24 VERSION 12-Dec-22 DATA DATE: 12-Dec-22 ROCKY RIVER WWTP PROJECT SCHEDULE 12-Dec-22 PAGE 10 OF 17 RR-09 (12-12-22) CROWDER CONSTRUCTION TASK ID TASK WORK DAYS START DATE FINISH DATE 4jAjMjJjJjAjS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 4590 DI Piping @ EQ Tank 1 20 08-Jan-24 Checkout / Startup / Testing @ EQ Tank 1 30 05-Feb-24 Grading / Stone / Backfill @ NEF Blower Pad 2 08-Nov-23 02-Feb-24 15-Mar-24 09-Nov-23 I I 4590 !177D 4660 I Grading QI Piping @;EQ;Tank 1! ,Checkout /',Startup / Testing @ E0 / Stone / Backfill @ NFF Mower pad Tank 11 1770 • 4660 4720 Underslab Electrical @NEF Blower Pad 1 10-Nov-23 10-Nov-23 I I 14720 I Und 6910 4730 1 Ilnsl 4680 1 F 4740 ;1 Set rslab Electrical @ NEF Slower Pad; oughin!EQTank Electrical Conduit @ NEF E b Electricil @ NEF Blower Pad! RP'Slab @ NEF Blower Pad' E House @ NEF Blower pad'; lower Pad! 6910 Roughin EQ Tank Electrical Conduit @ NEF Blower Pad 15 10-Nov-23 04-Dec-23 4730 Inslab Electrical @ NEF Blower Pad 3 13-Nov-23 15-Nov-23 4680 FRP Slab @ NEF Blower Pad 4 29-Nov-23 04-Dec-23 4740 Set E House @ NEF Blower Pad 2 05-Dec-23 06-Dec-23 4700 NEF Blowers @ NEF Blower Pad 17 05-Dec-23 28-Dec-23 I I 470Q ;M 6890 I 6920 1 6900 ■ 6880' 11 NEF Blowers @;NEp Blower Pad Roughin Panels @ NEF Blower Pad Lighting @ NEF Blower Pad Electrical Instrumentation & Control StationE Pull Wire &!Terminate @ NEF! Blower! Pad @';NE'F Blower Pa 6890 Roughin Panels @ NEF Blower Pad 5 07-Dec-23 13-Dec-23 6920 Lighting @NEF Blower Pad 5 14-Dec-23 20-Dec-23 6900 Electrical Instrumentation & Control Stations @ NEF Blower Pad 6 14-Dec-23 21-Dec-23 6880 • 1530 Pull Wire & Terminate @ NEF Blower Pad I ' 1• Demolition Maintenance Canopy @Blower Bldg 10 15 22-Dec-23 05-Dec-22A 08-Jan-24 23-Dec-22 I I I I I I I I I I I I I I I I I I I 1530 11 1540' 1560 I I I I I I I I I I I I Demo'litioh Maintenahce Canbpyl@ Blower 10 Exdavation1Grading /'Stone @ Blower Bldg' ■'; Underslab Electrical @ Blower pldg I I I I I I I I I I I Idc I I I I I 1540 Excavation / Grading / Stone @ Blower Bldg 12 27-Dec-22 12-Jan-23 1560 Underslab Electrical @ Blower Bldg 10 08-Feb-23 21-Feb-23 1570 FRP Slab on Grade @ Blower Bldg 21 22-Feb-23 22-Mar-23 I I 1 I I 70; i ; FRP 91ab!on Grade (0 BlowerBldg! '■ 'In Slab!Elertrioal @ Blower Bldg 4380! 0 FRP Curbs / Wills @ Blower 1600 PEMB Install'@ Blower 1650 MM'; UG Electrjcal';(Yard) Idgl Bldo plower 8ldg;(DWtbank';103) 4350 In Slab Electrical @Blower Bldg 10 02-Mar-23 15-Mar-23435Q 4380 FRP Curbs / Walls @ Blower Bldg 10 23-Mar-23 05-Apr-23 1600 PEMB Install @ Blower Bldg 35 06-Apr-23 24-May-23 1650 UG Electrical (Yard) @ Blower Bldg (Ductbank 103) 30 10-May-23 21-Jun-23 4710 Lowers @ Blower Bldg 2 25-May-23 26-May-23 I I I I 4�10! 1', Louvers ( Blower BIdg 4510! ■ Roofing'.@ Blower BId 4480 0 Pairtting @IBloWer!Bld 4470 1 Dobrs & Hardware / Roll 45�0 ■'; Electr;ical';Ropghin Conduit Up Door @' Blower! Bldg ' / digljts @ Blower Bldg 4510 Roofing @ Blower Bldg 10 25-May-23 08-Jun-23 4480 Painting @ Blower Bldg 10 30-May-23 12-Jun-23 4470 Doors & Hardware / Roll Up Door @ Blower Bldg 5 13-Jun-23 19-Jun-23 4520 Electrical Roughin Conduit / Lights @ Blower Bldg 10 13-Jun-23 26-Jun-23 1720 Electrical Gear/ Install @ Electrical Room 70 11-Aug-23 17-Nov-23 I I 17�0 ;Ele 1620 M Blower InstE 1700 I■ I Stainless 4500' E 'FRP Exterior 6810 01 Starless trival Gear/ Install @;Electrigal Room ; Ilation @ B',lower Bldg l it Distribution Piping -I Interior! @'Blower IBId Pads @';BloWer'Bldg Air, Distribution Piping,- Exterior to AS6 @ Blower Bldg! 1620 Blower Installation @ Blower Bldg 15 15-Aug-23 05-Sep-23 1700 Stainless Air Distribution Piping - Interior @ Blower Bldg 13 06-Sep-23 22-Sep-23 4500 FRP Exterior Pads @ Blower Bldg 15 25-Sep-23 13-Oct-23 6810 Stainless Air Distribution Piping - Exterior to AB6 @ Blower Bldg 15 16-Oct-23 03-Nov-23 1680 Electrical / Instrumentation @ Blower Bldg 30 16-Oct-23 28-Nov-23 I I 16$0 NO!I E 1690 ■ IHV 1'710 ctr,ical;/ Instrumentation @ Blower Bldg; C @ Electrical Room Checkout / StartC p /Testing @ Blower BId /Electrical Room 1690 HVAC @ Electrical Room 15 30-Oct-23 17-Nov-23 1710 Checkout /Startup /Testing @Blower Bldg /Electrical Room IL ON 1440 1 Mechanical / Concrete Demo @ WAS PS 20 10 29-Nov-23 27-Dec-23 15-Aug-23 28-Aug-23 1440 ■; Mechanical / orcrete Demo @ WAS PS VERSION 12-11l DATA DATE: 12-Dec-22 ROCKY RIVER WWTP PROJECT SCHEDULE 12-Dec-22 PAGE 11 OF 17 RR-09 (12-12-22) CROWDER CONSTRUCTION TASK ID TASK WORK DAYS START DATE FINISH DATE A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 6270 FRP Pads @ WAS PS 4 Pump Install @ WAS PS 10 29-Aug-23 01-Sep-23 18-Sep-23 270 -Pads ac 1800 I■ Pump Ilnst 1950 !DIP Install 1940 1" Elect WASPS! II @ WAS! PS @ WAS PS ical'/ Instrumentation @ WASPS 1800 05-Sep-23 1950 DIP Install @ WAS PS 20 19-Sep-23 16-Oct-23 1940 Electrical / Instrumentation @ WAS PS 30 19-Sep-23 30-Oct-23 6280 FRP Supports @WAS PS 3 17-Oct-23 19-Oct-23 1830 ❑ExcaVatiorGrading 6280 I FR';P Supports, 1960 1 C / Stone @' Flow EQ Influent M V ' @';WAS FS iecRout / Startup /,Tes,ting, @ WAS PS 1960 1830 Checkout /Startup /Testing @WAS PS Excavation / Grading / Stone @ Flow EQ Influent M V 5 10 21-Nov-23 15-Aug-22 A 29-Nov-23 26-Aug-22 A 1860 FRP Base Slab @Flow EQ Influent MV 7 29-Aug-22A 07-Sep 22A I 1866 0 FRP, Bas 1420 p FRP, lab',@',Flow EO Influent MV Its @ Flow ,EQ,lnfluent MU 1820 ■ 'DIP Install @ Flow EQ Infuent 1790 1 Electrical / Ihstr 2030 1 Odor Control MV mentation'@ Flow EQ Influent MV Cover @ Flow EQ Influent'MV 1420 FRP Walls @ Flow EQ Influent MV 13 19-Sep-22A 05-Oct-22A 1820 DIP Install @Flow EQ Influent MV 10 02-May-23 15-May-23 1790 Electrical / Instrumentation @ Flow EQ Influent MV 5 01-Aug-23 07-Aug-23 2030 Odor Control Cover @ Flow EQ Influent MV 5 13-Oct-23 19-Oct-23 1870 1390 Checkout /Startup /Testing @Flow EQ Influent MV Excavate for One Sided Wall @ Flume 103 5 11 09-Jan-24 17-Oct-22A 15-Jan-24 31-Oct-22 A I I 1390 ■ E 3230 K::� 1870 a ate for One Sided Wall (cD Flume 103 horing System Procurement'✓ Installation @ I ';Checkout G, Startup /Testing @ Flow rQ Flume103 Effluent fluent' MV 3230 Shoring System Procurement / Installation @ Flume 103 Effluent 26 31-Oct-22A 07-Dec-22 A 3600 Drill &Epoxy Dowels @Flume 103 5 28-Nov-22 A 02-Dec-22 A I 8600, dE �550 I 3280 4020 4010' rill Epoxy Dowels @ Flume'10 FRP One Sided \/Vail @ F,lum;e 1b3 Excavate Effluent I@ Flume 103 1 Support Existing 84' @ Flume 103 Complete E�cavatioh fot Southern Slab on Grade'(Below'84"'Pipe) @Flume 103 3550 FRP One Sided Wall @ Flume 103 10 05-Dec-22A 16-Dec-22 3280 Excavate Effluent @Flume 103 5 12-Dec-22* 16-Dec-22 4020 Support Existing 84' @ Flume 103 5 19-Dec-22 23-Dec-22 4010 Complete Excavation for Southern Slab on Grade (Below 84" Pipe) @Flume 103 3 27-Dec-22 29-Dec-22 2780 Grade Beams / Utility Support at 72" Existing @ Flume 103 5 30-Dec-22 06-Jan-23 I I �780 a72q !403 40' 4050 1 Grade Beams /', Utility Support at 7Z" Exist I FRP Southern Slab on;Grade(Selbw 84" 1 FRP Balance One Sided Wall @ Flume 1 Excavate for Slab belbw 72" @Flume 1 1' FRP Slab below 72"'Pipe @ Flume'10 ng @ Flume 103 ipe) @ Flume! 10a 03 3 3720 FRP Southern Slab on Grade(Below 84" Pipe) @ Flume 103 5 30-Dec-22 06-Jan-23 4030 FRP Balance One Sided Wall @ Flume 103 5 09-Jan-23 13-Jan-23 4040 Excavate for Slab below 72" @Flume 103 5 16-Jan-23 20-Jan-23 4050 FRP Slab below 72" Pipe @Flume 103 5 23-Jan-23 27-Jan-23 4090 FRP Walls at 72" @Flume 103 10 30-Jan-23 10-Feb 23 I +90 I M rRF? Walls at 7" @ Flume 103 9 0 ■, FkP WVaII5 484", @ Fiume 103 , 708G 1 Effluent Leak Test @ Flume 103 701 Backfill to EL 531' Fiume 103 4060 1 !FRP M!ain!F lume Slab @'Flupne 03' 6930 FRP Walls at 84' @ Flume 103 10 13-Feb-23 24-Feb-23 7080 Effluent Leak Test @ Flume 103 5 27-Feb-23 03-Mar-23 4070 Backfill to EL 531' @ Flume 103 5 06-Mar-23 10-Mar-23 4060 FRP Main Flume Slab @Flume 103 5 13-Mar-23 17-Mar-23 4150 FRP Balance Walls @ Flume 103 15 20-Mar-23 07-Apr-23 I I I I 4150', No FRO Balance Vyalls, @';Flume 6960 1 ,Leak Test @ Flume 1n3 4170 ■ Flume! Install & Grout! @ Flume 5200 EI Mlisc Metals @ Flume 103 4190 1 Backfill Flume 103 03', 103 6960 Leak Test @ Flume 103 5 10-Apr-23 14-Apr-23 4170 Flume Install &Grout @Flume 103 10 10-Apr-23 21-Apr-23 5200 Misc Metals @ Flume 103 15 10-Apr-23 28-Apr-23 4190 Backfill @ Flume 103 5 17-Apr-23 21-Apr-23 1430 Bypass Pumping & MOPO @ Flume 103 10 24-Apr-23 05-May-23 1430' 10 Bypass Dumping &' MOP 5210! i 91ide!Gates @ Flume 1P3 @'!Flume';103' 5210 Slide Gates @ Flume 103 6 25-Apr-23 02-May-23 VERSION 12-Dec-22 DATA DATE: 12-Dec-22 ROCKY RIVER WWTP PROJECT SCHEDULE 12-Dec-22 PAGE 12 OF 17 RR-09 (12-12-22) CROWDER CONSTRUCTION TASK ID TASK WORK DAYS START DATE FINISH DATE A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 2270 Electrical / Instrumentation @ Flume 103 10 01-Aug-23 2290 Checkout /Startup /Testing @ Flume 103 5 21-Nov-23 6970 Drill & Epoxy Dowels @ CCB2 29 28-Nov-22 A 14Aug-23 29-Nov-23 09-Jan-23 I 6970; 001 F980 101 699 70 227Q N !Electrical /,Inst 22901 1 C Drill Epoxy Epoxy Dowels @ 0013� Set One Side Foray @,CO,B2 ■ FRP Wall IExtenslonsl @ ,CCB2 0 I Strip IForrns I@ CCB2 umentation @ Flurne,103 ieckout / Startup /ITes,ting! @ Flume 103 6980 Set One Side Form @CCB2 29 28-Nov-22 A 09-Jan-23 6990 FRP Wall Extensions @ CCB2 10 10-Jan-23 23-Jan-23 7000 Strip Forms @ CCB2 5 24-Jan-23 30-Jan-23 7010 Metal Stairs / Misc Metals @ CCB2 1 • 5370 Drill & Epoxy Dowels @ CCB1 10 10 31-Jan-23 31-Jan-23 13-Feb-23 13-Feb-23 I I I I I I I I I 7 10 I I I I I I I I I I I 5 70 r 'Metal Stair's / Misc Metals @',CCB2 I I I I I I I I I I I ■ ',Drill & Epoxy Dowels @ CCB1 3 0 III! set Ohe Side'Form e CCB1 I I I I I I I I I I I I I I I I 5380 Set One Side Form @ CCB1 5 14-Feb 23 20-Feb 23 5390 FRP Wall Extensions @ CCB1 10 21-Feb-23 06-Mar-23 I I I I I I I I I I I I I I I I I I I I I I 1880 ',0 Exca 1890 0 FRr 1900 [n 423Q 5 90' 0 FRP'VVell Extensions @ CCB1 9772' 1', Balance PRP; Wall Extensio 6260 M Strip, For,ms!@ CC01 I I I I I I I I I I I a ion J Grading /'Stone @F'low'EQ; Effluent M B se Slab @ Flow EQ Effluent'MV Walls,@ flow ECG Effluent M,V ackfill @ FIowIEQlEfflluent MV 1920 ■ DIP Install) @ Fldw EQ s (after; Flume! Backfill) @ CCB1' I I I I I I I I I I I fflul nt MV I I I I I 9772 Balance FRP Wall Extensions (after Flume Backfill) @ CCB1 5 24-Apr-23 28-Apr-23 6260 Strip Forms @ CCB1 • • ' 1880 Excavation / Grading / Stone @ Flow EQ Effluent M V 5 7 01-May-23 03-Oct-22A 05-May-23 11-Oct-22 A 1890 FRP Base Slab @ Flow EQ Effluent MV 5 12-Oct-22A 18-Oct-22A 1900 FRP Walls @ Flow EQ Effluent MV 18 19-Oct-22A 11-Nov-22 A 4230 Backfill @ Flow EQ Effluent MV 3 30-Nov-22A 02-Dec-22A 1920 DIP Install @ Flow EQ Effluent MV 10 16-May-23 30-May-23 1910 Electrical /Instrumentation @ Flow EQ Effluent MV Odor Control Cover @ Flow EQ Effluent M V Checkout / Startup / Testing @ Flow EQ Effluent M V Excavate /Stone @ Box 101 FRP Slab @ Box 101 5 01-Aug-23 07-Aug-23 I I 1910 If Flectricel / Ihstr 96$2 I Odor Control 1930, mentation @ Flow EQ Effluent MV Cover @ Flow EQ Efflue � MV I Checkout,/ Startup / testing @ Flow, EC Effluent M,V 9632 5 13-Oct-23 19-Oct-23 1930 3890 5 40 16-Jan-24 19-Dec-22 22-Jan-24 14Feb 23 I I 3890 I I Excavate /' Stone @ Box 101 130 1', FRP Slab, @';Bo> 10j 4206 M ,FRP VWalls,@ Oox,101 3860 I Leak Test Structure @ Box 101 42201 0 Shoring for Elevated Slab x 101 4160 7 15 15-Feb-23 24-Feb-23 23-Feb-23 16-Mar-23 4200 FRP Walls @ Box 101 3860 Leak Test Structure @ Box 101 5 17-Mar-23 23-Mar-23 4220 Shoring for Elevated Slab @ Box 101 10 24Mar-23 06-Apr-23 4240 FRP Elevated Slab @ Box 101 5 07-Apr-23 13-Apr-23 I I I I 4240 ',1 FRP Elevated Slab @' Box 10 4260 I Strip Forms @ Box 101 4Q60 16 M IC Coating Interior of,Bo 4210 1 2W TD outside of B©x @ Box 3900 Backfill @ @, Box 10,1 1Q1 ox 1011 4250 Strip Forms @ Box 101 5 14-Apr-23 20-Apr-23 4260 M IC Coating Interior of Box @ Box 101 15 21-Apr-23 11-May-23 4210 24' TD outside of Box @ Box 101 1 02-May-23 02-May-23 3900 Backfill @ Box 101 90 03-May-23 08-Sep-23 4270 Grout to Crown of Existing 66" @ Box 101 2 12-May-23 15-May-23 I I I I I I I I I I I I I I I I I I 4270 1 Grout to Crown of Existing 420,Sawcut & Remove Crowr I I I I I I I I I I I 66'' @'Box 101 of Existing 669 @' ;Box 10 I I I I I I I I I I I I I I I I 4290 • Sawcut & Remove Crown of Existing 66" @ Box 101 1 16-May-23 I -May-23 ROCKY RIVER WWTP VERSION 12-Dec-22 PROJECT SCHEDULE PAGE 13 OF 17 DATA DATE: 12-Dec-22 RR-09 (12-12-22) 12-Dec-22 CROWDER CONSTRUCTION SKID TASK WORK DAYS START DATE FINISH DATE 2022 IAIMIJIJIAISIOINID J F M A M J JjjAjjSjjOjjNjj J F M A M J J A S O ND J F MA M J JASOND J F M A M 4550 Slide Gates / Weirs @ Box 2A 2 4530 Demo FRP Plates @ Box2A 1 •' 4960 Excavate / Stone @ Maintenance Canopy 4 17-Feb-23 IL A 20-Feb-23 4150 1 I Slide Gates / Weirs @ Box 2A I 15-Mar-24 21-Dec-22 15-Mar-24 27-Dec-22 I 4960 5000, 1 Excavate/ Stone @, Maintenance Canopy 11 Insla'b Electr,ical!@ Maintenance Canopy 4530 1 'Demo FRP Plates!@ Box!2A1 5000 Inslab Electrical @Maintenance Canopy 5 28-Dec-22 04Jan-23 4980 FRP Slab on Grade @Maintenance Canopy 20 28-Dec-22 25-Jan-23 I I 4980 6830 I I FRP Slab onlGrede @ Maintenance Canopy 1 FRP'Curbs / V41s @ Maintenance Canopy $260 ',�', PEM81natall',@ Mainten 4990, I Painting @ MaintenanCE 50401 1 Roofing @ M',aintena',nce I anceCanopy Canopy Canopy 6830 FRP Curbs / Walls @ Maintenance Canopy 5 26-Jan-23 01-Feb-23 5260 PEMB Install@ Maintenance Canopy 35 04-Apr-23 22-May-23 4990 Painting @ Maintenance Canopy 5 23-May-23 30-May-23 5040 Roofing @ Maintenance Canopy 5 23-May-23 30-May-23 4970 8801 Electrical Roughin / Lights @ Maintenance Canopy Excavation @ Gravity Thickeners 3 & 4 10 20 31-May-23 17-Jul-23* 13-Jun-23 11-Aug-23 4970 0 'Electrical Roughin % Lic 8801 ME Excavation,@ 8802 1 11 6ih TS/8inl TD hts'@ Maintenance Canopy GrayityThickeners,3 & 4 UnderSlabl@ Gravity Thickeners!3 &I4 8802 6in TS/8in TD Underslab @ Gravity Thickeners 3 & 4 8 14Aug-23 23-Aug-23 3930 FRP Pipe Encasement @Gravity Thickeners 3 & 4 12 24Aug-23 11-Sep 23 I I 39301 IN FRP Pipe E 3910 1 FR'P Center 3960', 1', FRP Cen 3920, 111 Stone Stjbgradq 3880 IN FRIP Slab nceserhent @I GrevitN Thickeners 3 & 41 Pier @ Gravity Thickener 3' er Plea @;Gravity;Thickener 4 @!Gravity! Thickeners 3 4 @ Gravity Thickener 3 3910 FRP Center Pier @ Gravity Thickener 3 6 12-Sep-23 19-Sep-23 3960 FRP Center Pier @ Gravity Thickener 4 6 20-Sep-23 27-Sep-23 3920 Stone Subgrade @ Gravity Thickeners 3 & 4 4 28-Sep-23 03-Oct-23 3880 FRP Slab @ Gravity Thickener 3 13 02-Oct-23 18-Oct-23 3970 FRP Slab @Gravity Thickener 4 13 19-Oct-23 06-Nov-23 I I 3970 IN FR 3940 ME F 0400 1 y020 5520 Sleb Q Gravity Thickener 4 P WaI'IS @ Gravity Thickener 3 eak Test S';tructure @';Gravity,Thickener 3 FRP Vyalls,@ Grayity'ThiGkener 4 Patch/Rub Walls @' Gravity Thickener 3 3940 FRP Walls @ Gravity Thickener 3 30 19-Oct-23 01-Dec-23 5400 Leak Test Structure @ Gravity Thickener 3 5 04-Dec-23 08-Dec-23 7020 FRP Walls @ Gravity Thickener 4 30 04-Dec-23 16-Jan-24 5520 Patch/Rub Walls @ Gravity Thickener 3 15 11-Dec-23 02-Jan-24 7030 Leak Test Structure @ Grav tyThickener 4 5 17-Jan-24 23-Jan-24 I I 7030 5430 7040 549D 3950 1 Leek TestlStructulre @ Gravity Thicken 0 Backfill @ Gravity Thickeners 3 &'4 10 ';PatcWF,ub;VValls @ G'ravkyTpickener 1 `RP Stair Landings @ Gravity TIhickE Misc',Metals',@ Gravity',Thickener r 4! 4 ners 3;& 4, 3 & 4 5430 Backfill @Gravity Thickeners 3 & 4 10 24-Jan-24 06-Feb 24 7040 Patch Rub Walls @ Gravity Thickener 4 15 24-Jan-24 13-Feb 24 5490 FRP Stair Landings @ Gravity Thickeners 3 & 4 4 07-Feb-24 12-Feb-24 3950 Misc Metals @ Gravity Thickeners 3 & 4 15 13-Feb-24 04Mar-24 5550 Process Equipment Install @ Gravity Thickeners 3 & 4 30 14-Feb-24 26-Mar-24 I I 5550 ME! Process Equipment Install @ G 2050 !Electrical /'Instrurhentetioh @ 5560', 1ME Exposed Mechanical Pjpin 55�0 I Sweep! Menh Grout @ Gravity 2240 avityThickeners 3 GrevityThickeners @',GravityTIhicken Thickener 3 Odor Control 2050 Electrical / Instrumentation @ Gravity Thickeners 3 & 4 30 05-Mar-24 15-Apr-24 5560 Exposed Mechanical Piping @ Gravity Thickener 3 & 4 30 27-Mar-24 07-May-24 5530 Sweep Mech Grout @ Gravity Thickener 3 & 4 2 15-May-24 16-May-24 2240 Odor Control Cover Install @ Gravity Thickeners 3 & 4 40 18-Dec-24 14Feb-25 2060 Checkout / Startup / Testing @ Gravity Thickeners 3 & 4 30 17-Feb-25 28-Mar-25 2 60 EEIII Checko 2380 Cc 2380 Commissioning @ Gravity Thickeners 3 & 4 THICKENED SL UD GE PUMP S TA • 30 31-Mar-25 09-May-25 ROCKY RIVER WWTP VERSION 12-Dec-22 PROJECT SCHEDULE DATA DATE: 12-Dec-22 12-Dec-22 PAGE 14 OF 17 RR-09 (12-12-22) CROWDER CONSTRUCTION TASK ID TASK WORK DAYS START DATE FINISH DATE 4jAjMjJjJjAjS O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 2070 Excavation / Stone @ Thickened Sludge PS 24 FRP Base Slab @ Thickened Sludge PS 8 17-Jul-23 17-Aug-23 I I I I I I 2070 Excavation / S 2Q90 ■I FRP Base S 2100 FRIP V 2110 * bus 5080 1606D one @, Thickened! Sludge, PS', ab @ Thickened sludge PS lalls! @ Thickened SludgePS, nded'Slab /Concrete Beams @ Thickened * $ackfill @ Thickened Sludge PS I FRP Stair Landings @,Thjckened,Slu Sludge PS ge,PS 2090 18-Aug-23 29-Aug-23 2100 FRP Walls @ Thickened Sludge PS 35 30-Aug-23 18-Oct-23 2110 Suspended Slab /Concrete Beams @Thickened Sludge PS 15 19-Oct-23 08-Nov-23 5980 Backfill @ Thickened Sludge PS 10 24-Jan-24 06-Feb-24 6060 FRP Stair Landings @ Thickened Sludge PS 3 07-Feb-24 09-Feb-24 2150 Masonry @ Thickened Sludge PS 30 07-Feb-24 19-Mar-24 I I I I 21 161 !Masonry @ Thickened Sludge P 0 MisdMetals @IThickenedSludge 2180 Roof Joist & Decking / Roofini 2190 No Pump/ Pad', Install @ Thickened 2210 Eleptrioal / jnstrum;entptio PS! @ Thickened Slud Sludge PS @,Thipkened,Slu;d 6160 Misc Metals @Thickened Sludge PS 20 12-Feb-24 08-Mar-24 2180 Roof Joist & Decking / Roofing @ Thickened Sludge PS 20 20-Mar-24 16-Apr-24 2190 Pump/ Pad Install @ Thickened Sludge PS 15 17-Apr-24 07-May-24 2210 Electrical / Instrumentation @ Thickened Sludge PS 20 17-Apr-24 14May-24 2200 DIP Install @Thickened Sludge PS 33 08-May-24 24Jun-24 2200 DIP Install @ �Thickei 61801 I' Doors & Hardware @ 2220' 0 Checkout /Startup/Testing@aThicken( 2370 EW Comm,issioni ied Sludge PS', Thickened Sludge g @ Thickened Slu 6180 Doors & Hardware @ Thickened Sludge PS 3 25-Jun-24 27-Jun-24 2220 Checkout / Startup/Testing @ Thickened Sludge PS 10 25-Jun-24 09-Jul-24 2370 Commissioning @ Thickened Sludge PS 30 10-Jul-24 20-Aug-24 ROCKY RIVER WWTP VERSION 12-Dec-22 PROJECT SCHEDULE PAGE 15 OF 17 DATA DATE: 12-Dec-22 RR-09 (12-12-22) 12-Dec-22 CROWDER CONSTRUCTION TASK ID TASK WORK I START DATE DAYS ELECTRICAL UPGRADES I FINISH DATE JAIMIJIJIAS O N D J F M A M J J A S ON D JFMAMJ JASONDJFMAMJ JASOND J F M A M MILESTONES I 2�31Q Notice to',Propeep @ Electric al I 3260 I 4ZFI'#15; - D;uctbank Co rd 340 '',RFI'',#1g - Cjuctpan4c ipgradps 307p nation with'Future'NEp - Submitted ordination with Future, NE P - Gogrdi ptiog / Illi, Substantial Completion!@ Electrical Upgrades eview Provide Direction 2330 Notice to Proceed @ Electrical Upgrades 0 3070 Substantial Completion @ Electrical Upgrades 0 ISSUES III 1 RFI #15 - DUCTBANK COORDINATION111 WITH FUTURE NEF 3260 RFI #15 - Ductbank Coordination with Future NEF -Submitted 1 10-May-22 A 28-Mar-22 A 05-Jan-24 10-May-22 A 3470 RFI #15 - Ductbank Coordination with Future NEF -Coordination Review & Provide Direction PROCUREMENT PAD MOUNTED SWITCHES 2790 Pad Mounted Switches Shop Drawing Prep / Submit 23 72 11-May-22 A 25-Mar-22A 13-Jun-22 A 06-Jul-22A I I 2790' Pad 'Mounted S' itches'Shop $080 ',I Pad Mounted Switc;hes',Prq u �4a0 0 Pad Mounted Switches Prc JLct 2810 r-- -1 Rad 2800 Ip Pad Mounted Drawing', Prep/ Submit' t Data Submitted Data Review /Approve', Mounted Switches Fabrication tcheslShbpDrawinglRevieW/Approve 3080 Pad Mounted Switches Product Data Submitted 1 06-Apr-22A 06-Apr-22A 3430 Pad Mounted Switches Product Data Review /Approve 4 07-Apr-22A 12-Apr-22A 2810 Pad Mounted Switches Fabrication 153 13-Apr-22A 16-Nov-22A 2800 1 Pad Mounted Switches Shop Drawing Review/Approve 20 07-Jul-22A 03-Aug-22A PAD MOUNTED TRANSFORMERS 2820 Pad Mounted Transformers Shop Drawing Prep/Submit I 2$20', ] Pad Mquntgd7r an 8160 '.I Pad,MountedTransformers 3170 0 Pad Mounted Tran sformerE 2830 O Pad MounteI 3forMers8hop Drawing P';rep';/Subrnit durtData,Submitted, Product Data Review / Approve (release transformers) ransformers Shop Drawing Review / Approv 77 25-Mar-22A 13-Jul-22A 3160 Pad Mounted Transformers Product Data Submitted 1 06-Apr-22A 06-Apr-22A 3170 Pad Mounted Transformers Product Data Review / Approve (release transformers) 4 07-Apr-22A 12-Apr-22 A 2830 Pad Mounted Transformers Shop Drawing Review Approve 84 13-Apr-22A 10-Aug-22 A 2840 GENERATOR 2610 2620 2630 Pad Mounted Transformers Fabrication Generator Shop Drawing Prep/ Submit 349 128 13-Apr-22A 31-Dec-21 A 25-Aug-23 30-Jun-22A �61d I 28a10 G;ene,ratgr Shop! r 2620' Goner tar 2630 Pad Mounted ing Prep%SUbmjt Shop!Drawing Review /Approve Geheretor'Fab rication' Transfbrmers'Fabrication Generator Shop Drawing Review/Approve 132 25-Mar-22A 29-Sep-22A Generator Fabrication 163 23-Jun-22A 14-Feb-23 SWITCHGEAR 3440 SwitchgearShop DrawingPrep /Submit I 3440 I I SwitchgearSho 3450, E S,witphg $ 346Q rawing';Prep/ Submit ', Drawing Review tApprove Switchgear Fabrication 133 31-Dec-21A 08-Jul-22A 3450 SwitchgearShop Drawing Review/ Approve 92 25-Mar-22A 03-Aug-22A 3460 Switchgear Fabrication SWITCHBOARDS 316 31-May-22A 25-Aug-23 2850 2860 2870 MVT 2880 Switchboards Shop Drawing Prep/ Submit 25 03-Jun-22A 08-Jul-22A I I I 2850 'Q Switchboards S 28C0 ',0',Switch'boardshop I 2$70', I 2880 I' MVTCShop'DraWiniOSubmli Drawing Prep,/ Submit Dravying!'Review /Approve Switchboards Fabrication', Switchboards Shop Drawing Review/Approve 8 11-Jul-22A 20-Jul-22A Switchboards Fabrication MVTC Shop Drawing Submit 167 1 21-Jul-22A 28-Mar-22A 17-Mar-23 28-Mar-22A 2890 MVTC Shop Drawing Review /Approve 3 29-Mar-22A 31-Mar-22A 2890 N MVTCShooDr6wingRbviev/ 400 3690 ❑ 'DuctbahkB(crew'#1)I pprove MON MVYCF;abrication 2900 MVTC Fabrication DUCTBANKS 3090 DuctbankB(crew #1) 212 13 01-Apr-22A 28-Mar-22A 01-Feb-23 I 13-Apr-22A VERSION 12-Dec-22 DATA DATE: 12-Dec-22 ROCKY RIVER WWTP PROJECT SCHEDULE 12-Dec-22 PAGE 16 OF 17 RR-09 (12-12-22) CROWDER CONSTRUCTION TASK ID TASK WORK DAYS START DATE FINISH DATE 41AIMIJIJIAISIOINID J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M _ 3100 Ductbank C (crew #1) 13 Ductbank F (crew #1) 19 14-Apr-22A 02-May-22A I 31Q0 quctbankC(crew #,1) 3130 =1 DuctbanklF(crew #1,) 3140 O DuctbankGl( 3110 0 Ductbank D 3105; r w#1) I I I I I I I ci ew #1)' 1=0 Ductbank Aj(crew 91)'; 3130 03-May-22A 27-May-22A 3140 Ductbank G (crew #1) 46 31-May-22A 03-Aug-22A 3110 Ductbank D (crew #1) 5 08-Aug-22 A 12-Aug-22 A 3105 Ductbank A (crew #1) 30 27-Dec-22* 07-Feb-23 3300 Ductbank N (Crew #2) 9 28-Mar-22 A 07-Apr-22 A I 330Q 0 Ductbank NI (Crew #2) 3270 ❑ DUctbenk M (Crew #K2) 3420' 0 DuctbankL(Crew#2) 8250 ';❑ ';Duptbaink K (Crew #2) 3270 Ductbank M (Crew #2) 9 08-Apr-22 A 20-Apr-22 A 3420 Ductbank L (Crew #2) 9 21-Apr-22A 03-May-22A 3250 Ductbank K (Crew #2) 9 04-May-22A 16-May-22A 3240 Ductbank J (Crew #2) 22 19-May-22A 20-Jun-22A I 3240' p;DuptbankJ(grew 3120 0 Ductbank E'J Includii g 3310 O Ducfbank OI/ Inc u 3150 Ductbank H (C e I I 3200' C1 duc8bank I (Cr T4, T5 Refeed ,(Crew #2) ing T4,75 Refeed' (Crew ##2) #2J ) 3120 Ductbank E / Including T4, T5 Refeed (Crew #2) 5 31-May-22A 06-Jun-22A 3310 Ductbank O / Including T4, T5 Refeed (Crew #2) 21 07-Jun-22A 06-Jul-22 A 3150 Ductbank H (Crew #2) 33 07-Jun-22A 22-Jul-22 A 3200 Ductbank I (Crew #2) 11 21-Jun-22A 06-Jul-22A 3190 Owner Equipment Operation Coordination 20 21-Jun-22A 19-Jul-22A I 3190 En;Owner;Eggipr 3180 OI Wire Pull,ITest &Terminate I 2910 IMMEN Opgra�ion,Cogrdinatiqn T4, T5 Refeed M V'/ Fiber r;RP'Pads for Switches' 3180 2910 Wire Pull, Test & Terminate T4, T5 Refeed M V /Fiber FRP Pads for Switches 15 53 07-Jul-22 A 14-Nov-22 A 27-Jul-22 A 31-Jan-23 1840 Precast Pads for MVTC 5 26-Jan-23 01-Feb 23 I 1$ 40 2 1 10 I 111 precast pads for MVTC Set Pad Mounted Switches Set MVTCI 2 40' $000" Pull Wire - Loo0A1' 2 70'; 0000 Pull Wire - LoopA� 2340 Set Pad Mounted Switches 15 01-Feb-23 21-Feb-23 1810 Set MVTC 15 02-Feb-23 22-Feb-23 2940 Pull Wire - Loop Al 55 23-Feb-23 10-May-23 2970 Pull Wire - LoopA2 55 23-Feb-23 10-May-23 2980 Pull Wire - Loop 131 55 23-Feb-23 10-May-23 I I 2 80 Pull ,Wire - Loop 131, 2 90 Pull Wire -Loop B2 3000 Terminete Plant LbopS 3010 Testing Plant Loops ¢920 ';E'; FF2P Pads foi Transformers'; 2990 Pull Wire - Loop B2 55 23-Feb-23 10-May-23 3000 Terminate Plant Loops 55 02-Mar-23 17-May-23 3010 Testing Plant Loops 40 30-Mar-23 24-May-23 2920 FRP Pads for Transformers 15 07-Aug-23 25-Aug-23 3020 FRP Pads for Generator / Switchgear 10 14-Aug-23 25-Aug-23 I I 3020 ■; FRP pads foi 2950 1 Set Generator 2660 0 SetTransf 2930 ■' Set Switc 30$0 No Generator Generator, / Switchgear / Switchgear, rmers ilboards /';Switchgear Commissioning 2950 Set Generator / Switchgear 5 28-Aug-23 01-Sep-23 2660 Set Transformers 10 28-Aug-23 11-Sep-23 2930 Set Switchboards 10 12-Sep-23 25-Sep-23 3030 Generator /Switchgear Commissioning 20 12-Sep 23 09-Oct-23 2960 Pull Wire - Switchboards to Transformers 30 10-Oct-23 20-Nov-23 2930 NO Pu 3040 ITe 3050 Te 3060 I Wire Switchboards to Transformers urinate' Switchboards toTransfgrmers tiny - Switbhbbards tolTrensfbrm'ers Demolition 3040 Terminate -Switchboards to Transformers 30 10-Oct-23 20-Nov-23 3050 Testing - Switchboards to Transformers 30 10-Oct-23 20-Nov-23 3060 Demolition 60 10-Oct-23 05-Jan-24 ROCKY RIVER WWTP VERSION 12-Dec-22 PROJECT SCHEDULE PAGE 17 OF 17 DATA DATE: 12-Dec-22 RR-09 (12-12-22) 12-Dec-22