HomeMy WebLinkAbout20211566 Ver 3_More Info Received_20221230Baker, Caroline D
From: Harbour, Jeff W <Jeff.Harbour@terracon.com>
Sent: Thursday, December 29, 2022 2:15 PM
To: Scheller, Roberto
Subject: [External] FW: SAW-2022-02328_Dixon Branch Sewer Extension (Notice of Incomplete
Pre -Construction Notification)
Attachments: Dixon Branch Sewer Extension DMS Acceptance.pdf
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Per your message. USACE has asked that we report 0.71 ac of the impact as permanent due to conversion and we are
providing mitigation for that.
Jeff Harbour, PWS
Senior Scientist I Natural Resources
rerracon
2401 Brentwood Road, Suite 107 I Raleigh, NC 27604
D (919) 547-1080 I M (919) 805-4208
ieff.harbour@terracon.com I Terracon.com
From: Harbour, Jeff W
Sent: Thursday, November 10, 2022 10:43 AM
To: Roden Reynolds, Bryan K CIV USARMY CESAW (USA) <Bryan.K.Roden-Reynolds@usace.army.miI>
Cc: Jackson Hendricks <JacksonH@DClnsightllc.com>
Subject: RE: SAW-2022-02328_Dixon Branch Sewer Extension (Notice of Incomplete Pre -Construction Notification)
Bryan, I believe I have addressed your questions below and attached. Please let me know if there is other info that you
may need to continue your review. Thank you for your assistance.
a. ORM spreadsheet attached
b. Agree on the 0.71 ac of conversion and mitigation will be provided for those impacts. My error for listing as
temporary.
C. SOA for the wetland mitigation for conversion is attached. We propose mitigation at a 1:1 ratio for the
conversion. Is this acceptable?
d. BELTWAY 77 NORTH CONNECTION, LLC
Mr. Richard Horn
280 E. 96th Street, Suite 250
Indianapolis, IN 46240
All correspondence goes to Jackson Hendricks 704-773-8684 JacksonH@dcinsightlIc.com
1
Jeff Harbour, PWS
Senior Scientist I Natural Resources
rerracon
2401 Brentwood Road, Suite 107 I Raleigh, NC 27604
D (919) 547-1080 I M (919) 805-4208
ieff.harbour@terracon.com I Terracon.com
From: Roden Reynolds, Bryan K CIV USARMY CESAW (USA) <Bryan.K.Roden-Reynolds@usace.army.mil>
Sent: Monday, October 31, 2022 2:05 PM
To: Harbour, Jeff W <Jeff.Harbour@terracon.com>
Subject: SAW-2022-02328_Dixon Branch Sewer Extension (Notice of Incomplete Pre -Construction Notification)
Importance: High
Mr. Harbour,
On October 26, 2022, 1 received the Pre -Construction Notification you submitted on behalf of an unknown applicant on a
property located in Mecklenburg County, North Carolina. I have completed my initial review of the report and I have
determined that it is incomplete. The following information is necessary before a permit can be issued:
a. Complete the attached Aquatic Resources Upload Spreadsheet (in excel form) for all aquatic resources located
within the proposed project area. The JD request package included a PDF version of the spreadsheet; however,
the Corps needs the spreadsheet in excel form and not a PDF supplement to the PJD request package.
b. In Section D(2) of the PCN you stated all wetland impacts were temporary; however, Impacts Nos. 1-8 and 10
are wetland conversion impacts which are considered permanent impacts. Therefore, the project as proposed
has 0.71 acers of permanent wetland conversion impacts and 0.35 acres of temporary wetland impacts.
c. The PCN lacked a Compensatory Mitigation Reservation Letter from NCDMS or a Mitigation Bank for the 0.71
acres of permanent wetland conversion impacts. Therefore, please provide a signed Compensatory Mitigation
Reservation Letter for NCDMS or a mitigation bank.
d. Please provide the following information for the applicant of the proposed project:
- Company Name
- Point of Contact (full first and last name)
- Mailing address
- Telephone number
- Email address
Please provide the information requested above in ONE consolidated response within 30-days of the date of this
correspondence. If you do not respond within 30-days, the request will be administratively canceled. Please contact me
via telephone or e-mail if you have any questions.
Thanks,
Bryan Roden -Reynolds, PWS
Senior Regulatory Project Manager
U.S. Army Corps of Engineers
Wilmington District, Charlotte Field Office
8430 University Executive Park Drive
Charlotte, NC 28262
(704)510-1440
Terracon provides environmental, facilities, geotechnical, and materials consulting engineering services delivered with
responsiveness, resourcefulness, and reliability.
Private and confidential as detailed here (www.terracon.com/disclaimer). If you cannot access the hyperlink, please e-mail
sender.
ROY COOPER.
Governor
ELIZABETH S. BISER
Secretary
MARC RECKTENWALD
Drrectar
Richard Horn
Beltway 77 North Connection, LLC
280 E. 96th Street, Suite 250
Indianapolis, IN 46240
NORTH CAROLINA
Environmental Quality
November 1, 2022
Expiration of Acceptance: 5/1/2023
Project: Dixon Branch Sewer Extension County: Mecklenburg
The purpose of this letter is to notify you that the NCDEQ Division of Mitigation Services (DMS) is willing to
accept payment for compensatory mitigation for impacts associated with the above referenced project as
indicated in the table below. Please note that this decision does not assure that participation in the DMS in -
lieu fee mitigation program will be approved by the permit issuing agencies as mitigation for project impacts.
It is the responsibility of the applicant to contact permitting agencies to determine if payment to the DMS will
be approved. You must also comply with all other state, federal or local government permits, regulations or
authorizations associated with the proposed activity including G.S. § 143-214.11.
This acceptance is valid for six months from the date of this letter and is not transferable. If we have not
received a copy of the issued 404 Permit/401 Certification within this time frame, this acceptance will
expire. It is the applicant's responsibility to send copies of the permits to DMS. Once DMS receives a copy
of the permit(s) an invoice will be issued based on the required mitigation in that permit and payment must
be made prior to conducting the authorized work. The amount of the in -lieu fee to be paid by an applicant is
calculated based upon the Fee Schedule and policies listed on the DMS website.
Based on the information supplied by you in your request to use the DMS, the impacts for which you are
requesting compensatory mitigation credit are summarized in the following table. The amount of mitigation
required and assigned to DMS for this impact is determined by permitting agencies and may exceed the
impact amounts shown below.
River Basin
Impact Location
(8-digit HUC)
Impact Type
Impact Quantity
Catawba
03050101
Riparian Wetland
0.71
Upon receipt of payment, DMS will take responsibility for providing the compensatory mitigation. The
mitigation will be performed in accordance with the In -Lieu Fee Program instrument dated July 28, 2010.
Thank you for your interest in the DMS in -lieu fee mitigation program. If you have any questions or need
additional information, please contact Kelly.Williams@ncdenr.gov.
cc: Jeff Harbour, agent
E
oe israhMi a in,;rrrtem,i ore
Sincerely,
FOR James. B Stanfill
Deputy Director
North Carolina Department of Environmental Quality I Division of Mitigation Services
217 West Jones Street l 1652 Mail Service Center I Raleigh, North Carolina 27699-1652
9I9.707.8976