HomeMy WebLinkAboutSW6220505_Design Calculations_20221220 (2)Project Name Riprap Dissipator #1 Date Shahbain Reserve - Phase 1 Sep, 2021 DD Project No. Location Double D Engineering, PLLC DD2018 Hoke County, North Carolina 150 S. Page Street Calculated By Southern Pines, NC 28387 J LH (910) 684-8646 Checked By JLH STORM DESIGN: 10 Year BACKGROUND: Use the E&S Control Planning REFERENCE: (NCOEHNR, 1993) Step 1, Minimum Tailwater Condition Step 2. D-o = 36 in. D-o = 3.00 ft. Q-25 = 43.29 cfs d-50 = 0.7 ft. L-a = 20 ft. Step 3. 3`D-o = 9.00 ft. W = 23.00 ft. Step 4. d-max 1.05 ft. d-max 13 in. Step 5. Thickness = 1.58 ft. Thickness = 19 in. DESIGN DIMENSIONS: Manual, Section 8.06. Pipe diameter in inches Pipe diameter in feet Pipe outlet (from drainage calculations) from Figure 8.06 a from Figure 8.06 a 3 times the outlet pipe diameter Pipe diameter + Apron length Maximum Stone Diameter (1.5*d-50) in inches Maximum Stone Diameter (1.5*d-50) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in inches Apron Dimensions Riprap Class _Len..c t Width 3-D-o Thick 20 23 9 36in. 2 RMINOLOGY: Q10 = I 0-Yei ir Design Storm, Peak Discharge, (cfs) D-o = Pipe Diameter, (in. & ft.) d-50 = Mean t Dne Diameter of Rip -Rap, (ft.) L-a = Lengt Rip -Rap Apron, (ft.) 3*D-o = Width f Rip -Rap Apron @ Pipe Outlet, (ft.) W = Width f Rip -Rap Apron @ End of Apron, (ft.) d-max = Maxim jr n Stone Diameter of Rip -Rap, (ft. & in.) Thickness = Thickn s of Rip -Rap Apron With Filter Fabric, (ft. &in.) Project Name Riprap Dissipator #2 Date Shahbain Reserve - Phase 1 Apr, 2022 DD Project No. Location Double D Engineering, PLLC DD2115 Hoke County, North Carolina 150 S. Page Street Calculated By Southern Pines, NC 28387 JLH (910) 684-8646 Checked By JL11 STORM DESIGN: 10 Year BACKGROUND: Use the E&S Control Planning & Design Manual, Section 8.06. REFERENCE: (NCDEHNR, 1993) Step 1. Minimum Tailwater Condition Step 2. D-o = 30 in. D-o = 2.50 ft. Q-25 = 21.17 cfs d-50 = 0.5 ft. L-a = 16 ft. Step 3. 3*D-o = 7.50 ft. W = 18.50 ft. Step 4. d-max 0.75 ft. d-max 9 in. Step 5. Thickness = 1.13 ft. Thickness = 14 in. DESIGN DIMENSIONS: Pipe diameter in inches Pipe diameter in feet Pipe outlet (from drainage calculations) from Figure 8.06 a from Figure 8.06 a 3 times the outlet pipe diameter Pipe diameter + Apron length Maximum Stone Diameter (1.5*d-50) in inches Maximum Stone Diameter (1.5*d-50) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in inches Apron Dimensions Riprap Lent It Width 3-D-o Thick I Class 16 19 8 24in. 1 TERMINOLOGY: Q10 = 10-Ye r Design Storm, Peak Discharge, (cfs) D-o = Pipe Ciarneter, (in. & ft.) d-50 = Mean t ne Diameter of Rip -Rap, (ft.) L-a = Lengt f Rip -Rap Apron, (ft.) 3*D-o = Width Rip -Rap Apron @ Pipe Outlet, (ft.) W = Width Rip -Rap Apron @ End of Apron, (ft.) d-max = Maxim ir ri Stone Diameter of Rip -Rap, (ft. & in.) Thickness = Thick s of Rip -Rap Apron With Filter Fabric, (ft. &in.) Project Name Riprap Dissipator #3 Date Shahbain Reserve - Phase 1 Apr, 2022 DID Project No. Location Double D Engineering, PLLC 11D2115 Hoke County, North Carolina 150 S. Page Street Calculated By Southern Pines, NC 28387 JLH (910) 684-8646 Checked By JLH STORM DESIGN: 10 Year BACKGROUND: Use the E&S Control Planning & Design Manual, Section 8.06. REFERENCE: (NCOEHNR, 1993) Step 1. Minimum Tailwater Condition Step 2. D-o = 30 in. D-o = 2.50 ft. Q-10 = 28.17 cfs d-50 = 0.5 ft. L-a = 16 ft. Step 3. 3*D-o = 7.50 ft_ W = 18.50 ft. Step 4. d-max 0.75 ft. d-max 9 in. Step 5. Thickness = 1,13 ft_ Thickness = 14 in. DESIGN DIMENSIONS: Pipe diameter in inches Pipe diameter in feet Pipe outlet (from drainage calculations) from Figure 8.06 a from Figure 8.06 a 3 times the outlet pipe diameter Pipe diameter + Apron length Maximum Stone Diameter (1.5*d-50) in inches Maximum Stone Diameter (1.5*d-50) in feet Min. Apron Thickness With Filter Fabric (1.5'd-max) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in inches Apron Dimensions Riprap Len t Width 3-D-o Thick Class 1 19 8 24in. 1 TERMINOLOGY: Q10 = 10-Ye ar Design Storm, Peak Discharge, (cfs) D-o = Pipe I ie meter, (in. & ft.) d-50 = Mean Slone Diameter of Rip -Rap, (ft.) L-a = Lengtl i of Rip -Rap Apron, (ft.) 3*D-o = Width 0 Rip -Rap Apron @ Pipe Outlet, (ft.) W = Width o Rip -Rap Apron @ End of Apron, (ft.) d-max = Maxirr u Stone Diameter of Rip -Rap, (ft. & in.) Thickness = Thickre s of Rip -Rap Apron With Filter Fabric, (ft. &in.) Project Name Riprap Dissipator #4 Date Shahhain Reserve - Phase 1 Apr, 2022 DD Project No. Location Double D Engineering, PLLC DD2115 Hoke County, North Carolina 150 S. Page Street Calculated By Southern Pines, NC 28387 JLH (910) 684-8646 Checked By JLH DESIGN: 10 Year tOUND: Use the E&S Control Pla ERENCE: (NCDEHNR, 1993) Step 1. Minimum Tailwater Condition Step 2. D-o = 24 in. D-o = 2.00 ft. Q-10 = 12.73 cis d-50 = 0.4 ft. L-a = 13 ft. Step 3. 3*D-o = 6.00 ft. W = 15.00 ft. Step 4. d-max 0.60 ft. d-max 7 in. Step 5. Thickness = 0.90 ft. Thickness = 1 t in. DESIGN DIMENSIONS: Design Manual, Section B.06. Pipe diameter in inches Pipe diameter in feet Pipe outlet (from drainage calculations) from Figure 8.06 a from Figure 8.06 a 3 times the outlet pipe diameter Pipe diameter + Apron length Maximum Stone Diameter (1.5*d-50) in inches Maximum Stone Diameter (1.5*d-50) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in inches Apron Dimensions Rlprap Lent Width 3-D-o Thick Class 1 15 6 24in. 1 INOLOGY: Q10 = 1 0-Ye ar Design Storm, Peak Discharge, (cfs) D-o = Pipe I liameter, (in. & ft.) d-50 = Mean Stone Diameter of Rip -Rap, (ft.) L-a = Lengt1i of Rip -Rap Apron, (ft.) 3*D-o = Width o Rip -Rap Apron @ Pipe Outlet, (ft.) W = Width o Rip -Rap Apron @ End of Apron, (ft.) d-max = Maxin un Stone Diameter of Rip -Rap, (ft. & in.) Thickness = Thickr e s of Rip -Rap Apron With Filter Fabric, (ft. &in.) Project Name Riprap Dissipator #5 Date Shahbain Reserve - Phase 1 Apr, 2022 DID Project No. Location Double D Engineering, PLLC DD211-5 Hoke County, North Carolina 150 S. Page Street Calculated By Southern Pines, NC 28387 JLH (910) 684-8646 Checked By JLH STORM DESIGN: 10 Year BACKGROUND: Use the E&S Control Planning & Design Manual, Section 8.06. REFERENCE: (NCDEHNR, 1993) Step 1. Minimum Tailwater Condition Step 2. D-o = 24 in. D-o = 2.00 ft. 0-10 = 38.78 cfs d-50 = 0.7 ft. L-a = 22 ft. Step 3. 3*D-o = 6.0D ft. W = 24.00 ft. Step 4. d-max 1.05 ft. d-max 13 in. Step 5. Thickness = 1.58 ft. Thickness = 19 in. DESIGN DIMENSIONS: Pipe diameter in inches Pipe diameter in feet Pipe outlet (from drainage calculations) from Figure 8.06 a from Figure 8.06 a 3 times the outlet pipe diameter Pipe diameter + Apron length Maximum Stone Diameter (1.5*d-50) in inches Maximum Stone Diameter (1.5*d-50) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in inches Apron Dimensions Riprap Len t Width 3-D-o Thick Class 2 24 6 36in. 2 TERMINOLOGY: Q10 = 10-Ye ir Design Storm, Peak Discharge, (cfs) D-o = Pipe I i meter, (in. & ft.) d-50 = Mean 3tDne Diameter of Rip -Rap, (ft.) L-a = LengtIr of Rip -Rap Apron, (ft.) 3*D-o = Width Rip -Rap Apron r@ Pipe Outlet, (ft.) W = Width 3f Rip -Rap Apron @ End of Apron, (ft.) d-max = Maxim jin Slone Diameter of Rip -Rap, (ft. & in.) Thickness = Thickness of Rip -Rap Apron With Filter Fabric, (ft. &in.) Project Name Riprap Dissipator # 6 Date Shahbain Reserve - Phase 1 Apr, 2022 DID Project No. Location Double D Engineering, PLLC DD2115 Hoke County, North Carolina 150 S. Page Street Calculated By Southern Pines, NC 28387 JLH (910) 684-8646 Checked By JLH STORM DESIGN: 10 Year BACKGROUND: Use the E&S Control Plan REFERENCE: (NCDEHVR, 1993) Step 1. Minimum Tallwater Condition Step 2. D-o = 24 in. D-o = 2.00 ft. Q-10 = 27.02 cfs d-50 = 0.5 ft L-a = 13 ft. Step 3. 3*D-o = 6.00 ft. W = 15.00 ft Step 4. d-max 0.75 ft. d-max 9 in. Step 5. Thickness = 1.13 ft, Thickness = 14 in. DESIGN DIMENSIONS: Design Manual, Section 8.06. Pipe diameter in inches Pipe diameter in feet Pipe outlet (from drainage calculations) from Figure 8.06 a from Figure 8.06 a 3 times the outlet pipe diameter Pipe diameter + Apron length Maximum Stone Diameter (1.5*d-50) in inches Maximum Stone Diameter (1.5*d-50) in feet Min, Apron Thickness With Filter Fabric (1.5*d-max) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in inches Apron Dimensions Riprap Len itl I Width 3*D-o Thick Class 1 15 6 241n, 1 NOLOGY: Q10 = 10-Yew Design Storm, Peak Discharge, (cfs) ❑-o = Pipe i meter, (in. & ft.) d-50 = Mean S one Diameter of Rip -Rap, (ft.) L-a = Lengt i of Rip -Flap Apron, (ft.) 3*D-o = Width o Rip -Rap Apron @ Pipe Outlet, (ft.) W = Width o Rip -Rap Apron @ End of Apron, (ft.) d-max = Maxi u Stone Diameter of Rip -Rap, (ft. & in.) Thickness = Thicki e s of Rip -Rap Apron With Filter Fabric, (ft. &in.) Project Name Riprap Dissipater #7 Date Shahbain Reserve - Phase 1 Apr, 2022 DD Project No, Location Double D Engineering, PLLC DD2115 Hoke County, North Carolina 150 S. Page Street Calculated By Southern Pines, NC 28387 JLH (910) 684-8646 Checked By JLH RM DESIGN: 10 Year KGROUND: Use the E&S Control Pla ERENCE: (NCDEHNR, 1993) Step 1. Minimum Tailwater Condition Step 2. D-o = 24 in. D-o = 2.00 ft. Q-10 = 37.00 cfs d-50 = 0.7 ft. L-a = 22 ft. Step 3. 3*D-o = 6.00 ft. W = 24,00 ft. Step 4. d-max 1.05 ft. d-max 13 in. Step 5. Thickness = 1.58 ft. Thickness = 19 in. DESIGN DIMENSIONS: Design Manual, Section 8.06. Pipe diameter in inches Pipe diameter in feet Pipe outlet (from drainage calculations) from Figure 8.06 a from Figure 8.06 a 3 times the outlet pipe diameter Pipe diameter + Apron length Maximum Stone Diameter (1 .5*d-50) in inches Maximum Stone Diameter (1.5*d-50) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in inches Dimensions Riprap 4Apron Lan t Width 3-D-o Thick Class 2 24 6 3Bin. 2 TERMINOLOGY: 010 = 10-Ye3r Design Storm, Peak Discharge, (cfs) D-o = Pipe I i meter, (in. & ft.) d-50 = Mean Slone Diameter of Rip -Rap, (ft.) L-a = Lengtl i of Rip -Rap Apron, (ft.) 3*D-o = Width o Rip -Rap Apron @ Pipe Outlet, (ft.) W = Width o Rip -Rap Apron @ End of Apron, (ft.) d-max = Maxi u Stone Diameter of Rip -Rap, (ft. & in.) Thickness = Thick e ss of Rip -Rap Apron With Filter Fabric, (ft. &in.)