NCEEP Budget Update and NCDOT/NCEEP
Operational Process Improvement
Richard Hancock, NCDOT PDEA Unit Head
Michael Ellison, Ecosystem Enhancement Program Director
June 4, 2014
Attachment 39
2
Budget Update and Business Process
•History of EEP
•Current NCDOT/NCEEP Operational Process
•Budget Update
•Operational Process Improvement Initiative
Supports
economic
development
COST CERTAINTY
REGULATORY
ACCEPTANCE
Compensatory
Mitigation for
stream,
wetland,
riparian buffer
and nutrient
offsets
Leverages
mitigation
investments to
the benefit of
the state’s
natural
resources
PARTNERS
Landowners
Contractors
Investors
Engineers
Cities &
Counties
WHAT WE DO
UT to Jumping Run – Stream and Wetland Complex
•Since June 2003, NCEEP has supported NCDOT in
meeting its mission statement by providing the
required off-site compensatory mitigation
•NCDOT and NCDENR have a joint MOA that
defines the business process we work under
•Since inception of EEP there have been no projects
where the let date has been delayed due to the lack
of mitigation
5
NCDOT / NCEEP MOA Operational
Process
•NCDOT provides NCEEP a list of transportation projects and
estimated impacts for each year based on a 7-year STIP Highway
program
•NCEEP develops Operational Strategic Plan to meet NCDOT’s
mitigation needs
•NCEEP develops biennial budget and requests NC Board of
Transportation approval
•NCDOT pays NCEEP based on quarterly invoices
= ACTUAL COST SYSTEM
6
Budget Update
•Normally present proposed biennial budget as
approach end of State fiscal year
•Due to ongoing STIP development implementing
STI prioritization process, not requesting budget
approval for SFY 15-16
•Proposal to proceed with SFY 14 -15 budgeted
amount as approved by BOT last year
7
Cash Flow Projection
EEP Biennial Budget State Fiscal Years (SFY) 2013/14 and 2014/15
Summary
MOA Year 11* (SFY 2013/14) MOA Year 12* (SFY 2014/15)
Quarter #1 Quarter #2 Quarter #3 Quarter #4 Quarter #5 Quarter #6 Quarter #7 Quarter #8
Line Item ** 07/13 - 09/13 10/13 - 12/13 01/14 - 03/14 04/14 - 06/14 07/14 - 09/14 10/14 - 12/14 01/15 - 03/15 04/15 - 06/15 Total
Administration
Salaries $ 908,991 $ 908,991 $ 908,991 $ 908,991 $ 908,991 $ 908,991 $ 908,991 $ 908,991 $ 7,271,928
Operating $ 83,275 $ 83,275 $ 83,275 $ 83,275 $ 83,275 $ 83,275 $ 83,275 $ 83,275 $ 666,200
SPO and legal $ 92,146 $ 92,146 $ 92,146 $ 92,146 $ 92,146 $ 92,146 $ 92,146 $ 92,146 $ 737,168
Restoration $ 8,585,840 $ 10,519,146 $ 6,799,012 $ 8,051,616 $ 13,260,515 $ 9,116,496 $ 8,117,302 $ 3,593,870 $ 68,043,796
Stewardship $ 58,280 $ 58,280 $ 58,280 $ 58,280 $ 65,617 $ 65,617 $ 65,617 $ 65,617 $ 495,584
Planning Framework $ 132,929 $ 96,500 $ 84,000 $ 96,000 $ 89,000 $ 50,000 $ 20,000 $ 15,000 $ 583,429
Total (by Quarter) $ 9,861,460 $ 11,758,337 $ 8,025,703 $ 9,290,307 $ 14,499,544 $ 10,316,525 $ 9,287,331 $ 4,758,899 $ 77,798,105
Total (Annual) $ 38,935,808 $ 38,862,297 $ 77,798,105
* Year of operation as EEP since 2003
** See individual linetabs for details
Summary
Administration $ 8,675,296
Restoration $ 68,043,796
Stewardship $ 495,584
Planning Framework $ 583,429
Biennial Total $ 77,798,105
Note: Biennial budget reflects operating requirements of Code of Federal Regulations as agreed with USACE, Wilmington Distric t
11%
87%
1% 1%
Distribution
Administration
Restoration
Stewardship
Planning Framework
Budget Update
•Propose to change SFY 14-15 budget line
items as follows: Total : $ 38.8 million
*New Project Starts (fee based program) - $ 4 million
Administration - $ 4 million
Ongoing Restoration Projects - $ 24 million
Additional Payment for completed projects $ 6 million
Planning and Stewardship - $0.8 million
10
Process Improvements
In June 2013, NCDOT and NCEEP agreed to
develop a new business model that would:
•Transition from a “pay as work is done” to a Fee Based
Program
•Mitigation fees will cover all facets of work from administration,
watershed planning, mitigation planning, design, site acquisition,
construction, remediation, monitoring, and long-term
stewardship.
•Payment of fees will relieve all NCDOT liability for the mitigation
that is provided by NCEEP.
11
Fee Based Program Proposal
•Within program, NCDENR-EEP will provide
NCDOT with an annual report of its work for
NCDOT
•Audits will be conducted by third party on a
biennial basis to address the fiscal and
environmental/technical components of the
program
•Annual report and audit will ensure program
efficiency
12
Expected Outcomes
•Simplifies and streamlines NCDOT and
NCEEP’s coordination process
•NCDOT has more predictable mitigation costs
•Reduces number of NCDOT changes to
mitigation orders
•Fee is all inclusive; NCDOT relieved of liability
after the mitigation fee is paid
•NCDOT can provide more focus on improving
accuracy of impact projections
13
Fee Based System Implementation
•Request approval to begin transition to lump
sum fee based payment for mitigation orders in
SFY 14-15 ($4 million new starts)
•Relatively low mitigation order & is financially
doable
14
For Future BOT Approval ( in 6-9
months)
•Proposed specific details of fee structure
•Proposed operating agreement between
NCDOT and NCDENR-EEP to reflect fee based
payment system
•Additional requests for increased mitigation
budget as STI prioritization results are obtained
and reviewed
15