HomeMy WebLinkAbout20140866 Ver 1_email on stream call / site visit_20150116Baker, Virginia From: Turlington, Chad Sent: Friday, January 16, 2015 1:19 PM To: King, Scott Cc: Baker, Virginia Subject: RE: Flea Hill Ditch EEP project Scott, After yesterday's site visit and stream determination, I agree with the Intermittent /Perennial stream calls as shown on the map "DWR Stream ID Flea Hill Site (revised 1/15/15) ". From: King, Scott [ mailto :Scott.King @mbakerintl.com] Sent: Friday, January 16, 2015 1:09 PM To: Baker, Virginia; Turlington, Chad Subject: RE: Flea Hill Ditch EEP project Good afternoon folks, Thank you for meeting me on site yesterday for the stream ID walkover. I bet before this project is over, you'll both be asked to review various aspects of it so I'm glad you got to see it at least once first hand! Attached is a revised map of the project showing the stream ID calls. Again, those two tributaries to the east flowing into the main channel that we called intermittent are not directly on the project but since they contribute a significant flow I'm glad we took a look at them and made a call. Though with all the rain it was admittedly difficult... If you agree with the revised map, I would appreciate it if you could both respond back in an email simply saying that you agree or approve of the stream ID calls as given the map (revision date 1/15/15). We do not need you to process all the paperwork for the full Preliminary -JD application, especially since the Corps has already done that here. We can just attach your comments and email with our mitigation plan to the IRT so they can have a level of assurance that the calls we're making are reasonable as that could potentially affect our design (and their approval of the design). Oh and that adjacent landowner we met at the end? Well, Chris Roessler (our project manager who found the site) is quite familiar with him. He's spoken to him on several occasions and says he's a friendly enough man. He even considered (for a second) participating in a restoration himself. Please let me know if you have any questions! Thank you very much, Scott From: Baker, Virginia [ mailto :virainia.bakerCa)ncdenr.Qov] Sent: Monday, January 12, 2015 10:17 AM To: King, Scott Subject: RE: Flea Hill Ditch EEP project Thanks for sending these Scott. See you Thursday. From: King, Scott [ mailto: Scott. King Cd)mbakerintl.com] Sent: Friday, January 09, 2015 4:34 PM To: Baker, Virginia; Turlington, Chad Subject: RE: Flea Hill Ditch EEP project Hi guys, Attached are a few maps you might find useful for the walkover. Let me know if you need anything else! Thanks, Scott From: Baker, Virginia [ mailto :virainia.bakerCa)ncdenr.Qov] Sent: Thursday, January 08, 2015 6:04 PM To: King, Scott Subject: Re: Flea Hill Ditch EEP project thanks scott!! Sent from my iPad On Jan 8, 2015, at 1:51 PM, King, Scott <Scott.King @mbakerintl.com> wrote: Great! Well it looks like we're all set for next Thursday at 9am. My cell number is 919 - 219 -6339. Ginny, I'll keep yours handy in case anything comes up at the last minute. Later today I'll I email you both some site maps you might find useful. Thanks, Scott From: Baker, Virginia [ mailto :virainia.bakerCa)ncdenr.aov] Sent: Thursday, January 08, 2015 10:27 AM To: King, Scott Subject: RE: Flea Hill Ditch EEP project Thanks Scott, assuming this time is all right with Chad I will plan to see you next week. My cell is 919- 802 -7194. That is your cell below, right? Also would you mind bringing me or emailing me a soft copy of a site map. thanks From: King, Scott [ mailto: Scott. King Cd)mbakerintl.com] Sent: Thursday, January 08, 2015 10:12 AM To: Baker, Virginia; Turlington, Chad Subject: RE: Flea Hill Ditch EEP project Sure thing - 9am would work fine for me as well! Thanks, Scott From: Baker, Virginia [ mailto :virainia.bakerCa)ncdenr.aov] Sent: Thursday, January 08, 2015 10:10 AM To: King, Scott; Turlington, Chad Subject: RE: Flea Hill Ditch EEP project I have a fpm meeting I would like to get to (or be late to) which came up after my email. Would it be possible to meet earlier, say at 9am? The stream determination is the main thing and I just want to get a look at the site. Thanks, ginny From: King, Scott [ mailto: Scott. King Cd)mbakerintl.com] Sent: Thursday, January 08, 2015 8:42 AM To: Turlington, Chad; Baker, Virginia Subject: RE: Flea Hill Ditch EEP project Sounds great — how about we meet down there at 10am next Thursday Jan 15th? Attached is a vicinity map for the project and a Google Earth screen shot showing a good meeting location. It's along a rural road that Google Maps says is at approximately 5047 Daughtry Rd, Wade, NC 28395. 1 suppose our primary purpose for meeting is to assess the stream determination calls (perennial, intermittent, ephemeral). And I'd be happy to discuss the general restoration plan as a whole as well. Is there anything else you're particularly interested in? Thank you, Scott 919 - 219 -6339 (cell) From: Turlington, Chad [ mailto :chad.turlinaton(a-)ncdenr.aov] Sent: Thursday, January 08, 2015 7:17 AM To: Baker, Virginia; King, Scott Subject: RE: Flea Hill Ditch EEP project From: Baker, Virginia Sent: Wednesday, January 07, 2015 11:53 AM To: King, Scott; Turlington, Chad Subject: RE: Flea Hill Ditch EEP project I'm available all day. Will that work for you Chad? From: King, Scott [ mailto: Scott. King Cd)mbakerintl.com] Sent: Wednesday, January 07, 2015 11:50 AM To: Baker, Virginia; Turlington, Chad Subject: RE: Flea Hill Ditch EEP project Hi folks, Yes indeed, I'm also trying to avoid fieldwork during this most recent arctic blast. I'm free next week on Thursday the 15th if you're still both free then to meet on site for a walkover? Just let me know! Thank you, Scott 919 - 219 -6339 From: Baker, Virginia [ mailto :virainia.bakerCa)ncdenr.Qov] Sent: Monday, January 05, 2015 2:36 PM To: King, Scott Cc: Turlington, Chad Subject: RE: Flea Hill Ditch EEP project Hi Scott, Thanks, just let me know what will work for you and we can also look at February. I'm fine with waiting until after this week. I have plenty to keep me busy in the office and cold weather is coming our way. Ginny From: King, Scott [ mailto: Scott. King Cd)mbakerintl.com] Sent: Monday, January 05, 2015 2:19 PM To: Baker, Virginia Cc: King, Scott; Turlington, Chad Subject: Re: Flea Hill Ditch EEP project Hi Ginny, That's fine, I'd be happy to walk the site with you guys. Let me get back in the office tomorrow and check my calendar for available dates but I know the rest of this week is booked. Thank you, Scott Sent from my iPhone On Jan 5, 2015, at 10:49 AM, Baker, Virginia <virginia.baker @ncdenr.gov> wrote: Hope you had a nice holiday. Since Eric left I thought I had all of his responsibilities down of who does what (me or the regions) but it turns out I am still learning. For stream determinations Eric would have regional staff take care of that. His supervisor would like to continue having the regions do those calls. I will still be reviewing the draft and final mitigation plans. I contacted Chad Turlington at our Fayetteville office about a field visit so we can get you this stream determination letter. Also, since I missed the field visit last summer I would like to go out with Chad at the same time and see the site so I thought we could coordinate a time with you if you need to meet us on property. We both have time available Jan 6 and 9 (would need to be done by Ipm on the 6 th or 51th), 12, 15, 22, 26, or 29 of this month and can schedule out if February too. Thanks, Ginny From: King, Scott [ mailto: Scott. King Cd)mbakerintl.com] Sent: Tuesday, December 23, 2014 12:39 PM To: Baker, Virginia Subject: Re: Flea Hill Ditch EEP project Sure thing Ginny! I'm out on holiday now too anyway. I just wanted to check in and make sure you didn't need anything more from me or that DWR didn't consider the matter settled. Thank you and have a great holiday! Scott Sent from my iPhone On Dec 23, 2014, at 12:12 PM, Baker, Virginia <virginia. baker@ ncdenr.gov> wrote: Hi Scott, | was out the last few days and wanted to follow-up with someone else at DVVR before responding. Staff is fairly thin right now, would it be all right if| got back to you after Xmas or the New Year? Ginny From: King, Scott Sent: Friday, December 19\ 20148:39AM To: Baker, Virginia Subject: RE: Flea Hill Ditch EEPproject Good morning Ginny, I just wanted to check in and see if you had any more questions about the Flea Hill Ditch EEP prelim-JD application? Assuming that everythin is good, would you be able to provide me with some sort of letter or emafl-giving, tacit DWR aWoroval to the stream calls we made? We'd 11"In to include something in our mitigation plan that shows that we have had regulatory input into our calls to justify the designs. Thank you vel much. Hope you have a great holiday break! Scott 919-219-6339 From: Baker Virginia Sent: Friday, December 05, 20149:54AM To: King, Scott Subject: RE: Flea Hill Ditch EEPproject Hi Scott, Thanks for sending this. Yes | have spent time | that part ofthe state. My co-workers have Verizon which is usually pretty good everywhere, but that place is no man's land. Since | still have AT&T my no man's land is half the state. Ginny From: King, Scott Sent: Friday, December 05, 20149:12AM To: Baker, Virginia Subject: RE: Flea Hill Ditch EEPproject Good morning Ginny. Sorry for the slow responses recently. The past three days | was in the field ina swamp by Lake Mattamuskeet and out of cell phone range. You know you're ina remote location when you can't get coverage these days huh?! Attached isa scan of the signed ]D form that Tyler sent me. That was all | got, no other cover letter orexplanation. VVe had discussed itinthe field and over the phone previously though. Please let me know if you need anything else. Thank you, Scott From: Baker Virginia Sent: Thursday, December 04, 20149:20 AM To: King, Scott Subject: Re: Flea Hill Ditch EEPproject Hi Scott, that would be fine thanks. Ginny Sent from my iPhone On Dec 3, 2014, at 8:52 PIVI, King, Scott HiGinny, | spoke with Tyler over the phone and then hejust mailed me the signed ]D without written comment. I'd be happy to send you a copy of the the form ifyou'd like? Scott Sent from my iPhone On Dec 3, 2014,at12:54PIVI, Baker, Virginia Hi Scott, | just took a look atthe prelim ]D review and don't have any questions on it. Would you mind [C'ingmeonTyler's response, thanks. Ginny From: King, Scott [ma i Ito: Scott. King (a)mbakeri ntl.corn] Sent: Tuesday, December 02, 2014 11:29 AM To: Kanoly, Cvndi Cm: Baker Vinginia;Tudingtnn Chad; Sullivan, Shelton Subject: RE: Flea Hill Ditch EEP project Thank you Cyndi! Ginny and Chad, JIL 219 -6339 if you have any questions about the project. Thanks, Scott From: Karoly, Cyndi [ mailto :cyndi.karolyCa)ncdenr.Qov] Sent: Tuesday, December 02, 2014 11:24 AM To: Sullivan, Shelton; King, Scott Cc: Baker, Virginia; Turlington, Chad; Higgins, Karen Subject: RE: Flea Hill Ditch EEP project Scott — Ginny and .• will be From: Sullivan, Shelton Sent: Tuesday, December 02, 2014 11:09 AM To: King, Scott Cc: Karoly, Cyndi; Baker, Virginia; Turlington, Chad; Higgins, Karen Subject: RE: Flea Hill Ditch EEP project IM .. - - • in our database but I do not conduct a Someone - in the Division may however, have copied them i ti i s - 117.1"i , Shelton Su]li�Tan 401 & Buffer Permitting Unit NCDENR I DMsion of grater Resources grater Quality Permitting Section 1617 Mail Sei0ce Center, Raleigh, NC 27699 -1617 Phone: (919)807 -6361 Fax: (919)807 -6494 Email: shelton.sullivan @ncdenr.gov �/Vebsite: http://portal.ncdenr.org/web/wq/sLAT/ws /webscape E -mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to third parties hef(Ve printing this crIliall, From: King, Scott [ma i Ito: Scott. King (a)mbakeri ntl.com] Sent: Tuesday, December 02, 2014 11:04 AM To: Sullivan, Shelton Subject: RE: Flea Hill Ditch EEPproject Good morning Shelton, I was wondering if you'd had a chanc yet to review the Flea Hill Prelim JD application I sent you a while back. It the I RT but left before we had completed this part of the process. I he p ad received approval from Tyler Crumle of the Corps of Engineers last week a just wanted to follow up with you to see if you had any questions. Feel fre to give me a call at 919-219-6339 if you'd like to chat about it. Thank you very much, Scott From: King, Scott Sent: Friday, October 24, 2014 12:52 PM To: 'SuUivan,Shelton' Subject: RE: Flea Hill Ditch EEPproject Hi Shelton, The application ison its way to you via USPS. Thanks again, Scott From: Sullivan, Shelton Sent: Thursday, October 2],2O14 11:07 AM To: King, Scott Cm: Baker Virginia Subject: RE: Flea Hill Ditch EEPproject That is the correct Mail Service Center address. |f using a different delivery service (UPS,FedEx), then use the street address below: Thanks Shelton Su]li�Tan 401 & Buffer Permitting Unit NCDENR I DMsion of grater Resources grater Quality Permitting Section 1617 Mail Sei0ce Center, Raleigh, NC 27699 -1617 Phone: (919)807 -6361 Fax: (919)807 -6494 Email: shelton.sullivan @ncdenr.gov �/Vebsite: http://portal.ncdenr.org/web/wq/sLAT/ws /webscape E -mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to third parties hef(Ve printing this crllialL From: King, Scott [ma i Ito: Scott. King Ca)mbakerintl.com] Sent: Tuesday, October 21, 2014 4:48 PM To: Sullivan, Shelton Cc: Baker, Virginia Subject: RE: Flea Hill Ditch EEP project Good afternoon Shelton, I'm working on the Flea Hill Ditch EEP restoration site in Cumberland County and I've been searching for who new DWR contact person would be for the project now that Eric Kulz is no longer there. Ginny Baker has informed me that you are the person I need to contact. I just completed a preliminary JD application for the project and have sent it off to Tyler Crumbley of the Corps for review and we also send a copy of the application to DWR as well (usually to Eric as he was the IRT rep for most of the EEP sites) for their review and acceptance of the perennial /intermittent /ephemeral calls, etc. This was a pretty straightforward project —just an incised ditch through a farm field. Feel free to contact me or E Tyler for any specific questions about the site (or Eric | guess if he's not too busy over at the City of Cary!). And is the following mailing address for you accurate? NCDENR — Div.ofVVaterResources 401 And Buffer Permitting Unit c/o Shelton Sullivan 1617 Mail Service Center Raleigh, NCZ7699'1617 Thank you very much, Scott King 919'219'6339 P3|f you would like an electronic copy asvxe|| | can put one on our FTP site for downloading at your convenience. Just let meknow. From: Baker Virginia Sent: Tuesday, October 21, 2014 4:37 PM To: King, Scott Cc: Sullivan, Shelton Subject: RE: Flea Hill Ditch EEPproject Hi Scott, Were you on the MT closeouts most recently? | know | have meta Scott over at Baker more than once. Will I am the contact for email but since you could instead send hard copy project info to Shelton Sullivan in the 401 & Buffer Permitting Unit (anything sent there I will get and review if it is an could send to me and CC Shelton until Eric is replaced. |f you are on any bank projects our regional staff would be your primary contact again until Eric is replaced (later this year???? ). Ginny 10 From: King, Scott [ma i Ito: Scott. King Ca)mbakerintl.com] Sent: Tuesday, October 21, 2014 4:23 PM To: Baker, Virginia Subject: RE: Flea Hill Ditch EEP project Hi Ginny, Thanks for following up with me! We actually met a while back at the Browns Summit EEP restoration site in Guilford County (in April) when you accompanied Eric Kulz in representing DWR in the IRT. I'm now working on the Flea Hill Ditch EEP restoration site in Cumberland County and I've just been wondering who new DWR contact person for the project now that Eric is no longer there. I just completed a preliminary JD application for the project and have sent it off to Tyler Crumbley of the Corps for review and we usually also sent a copy of the application to DWR as well (usually to Eric as he was the IRT rep for most of the sites) for their review and acceptance of the perennial /intermittent /ephemeral calls, etc. This was a pretty straightforward project —just an incised ditch through a farm field. Feel free to contact me or Tyler for any specific questions about the site (or Eric I guess if he's not too busy over at the City of Cary!). And if you are, in fact, the correct person to send this to would the following address be accurate? NCDENR — Div. of Water Resources Transportation Permitting Unit c/o Ginny Baker 1617 Mail Service Center Raleigh, NC 27699 -1617 Thank you very much, Scott PS If you would like an electronic copy as well I can put one on our FTP site for downloading at your convenience. Just let me know. 11 From: Baker, Virginia [ mailto :virainia.bakerCa)ncdenr.Qov] Sent: Tuesday, October 21, 2014 4:11 PM To: King, Scott Subject: Flea Hill Ditch EEP Hi Mr. King, Cyndi Karoly asked me to follow up with you on the Flea Hill Ditch EEP restoration project. I was not out at the initial site review as Eric was. I am the DWR contact so feel free to follow up with me on anything and I will try to help. His position probably will not be filled until late in the year or next. I am out the rest of this week, but will be available all of next. Thanks, Gihhy 3'�l<ei- Ti-�hspot-t�&oo Pet-mittiog l/hit NCDENR- P1v151o12 ofw'�tei-Resouires 1650 M,il Service Ceotet- R'�lelgh, NC276PP - -t650 Phooe -(WP) 707 -8788, Fix -(WP) 755 - t2PO 12