HomeMy WebLinkAboutSite Inspection 11.14.22 NC 69Wetland Inspection Report
Inspection Type:
Reason for Inspection:
Inspection Date:
Site Owner Name:
Latitude:
County:
Project Name:
Project Num:
Location:
SW Plan Location:
20190210
NCDOT - NC 69 Widening (A-0011C)
Clay
NCDOT - NC 69 Widening (A-0011C)
NC DOT Division 14 - Sylva
11/14/2022
Routine
Site Inspection (DOT)
Version: 2 Status:Issued
Project Type:Road/Highway Widening
Region:Asheville
Longitude:-83° 49' 32''+35° 00'
Inspection Contact Person:Title:Phone:
On-Site Representative(s):
Secondary Inspector(s):
Primary Inspector:Phone:Robert K Mitchell
Facility Compliance Status:Compliant Not Compliant
- Site 12 Channel Relocation is under construction. Fill slopes need cover. Impacted wetland area on Left Bank
Descending needs to be restored to original contours and seeded with a native seed mix. Equipment should not be in this
area unless they are using mats.
- Site 13 Y17 - Culvert outlet is not meeting burial condition and needs to be reworked with suitable material. Please
consult with Division Environmental staff.
Program Areas: 401 (includes isolated/non-404)
Question Areas:
Permit (401 WQC)
Inspection Summary:
Site inspection was conducted on November 14, 2022 by Kevin Mitchell with the Asheville Regional Office. Jamie
Mintz and Reid Whitehead were present during the inspection. The following are items that need attention:
page:1
Inspection Date:
Site Number:
Inspection Type:
Owner:
Reason for Visit:
20190210
11/14/2022
Blazer, Keith
Site Inspection (DOT)Routine
Permit (401 WQC)Yes No NA NE
Does the impact(s) match what was approved in the 401 WQC or non 404 permit?
Are the culverts and/or filled areas installed properly?
Is the site compliant with additional conditions of the 401 WQC or non 404 permit?
Site 13 on Y17 - Culvert outlet needs to be properly embedded using suitable material.Comment:
page:2