Dear Sir or Madam:
Attached is a copy of the inspection report which was prepared following an on -site inspection of the
subject site. This report is intended to provide you with information concerning the status of the site
as it relates to compliance with the North Carolina Sedimentation Pollution Control Act on 1973.
Please review this report carefully as it may contain corrective actions needed or comments which will
assist you in meeting the required performance standards of the Act.
It is our desire that any and all possible problems be discussed and resolved at the earlies possible
time. To facilitate this effort, please contact the named inspector at the address shown on the
inspection report if you have any questions.
Sincerely
Land Quality Section
Mooresville Regional Office
North Carolina Department of Environmental Quality! Division of Energy, Mineral and Land Resources
Fo�ft ME D. E Mooresville Regional Office ; 610 East Center Avenue, Suite 301 Mooresville, North Carolina 23115
704-663-1699
North Carolina Department of Environmental Quality
Land Resources: 610 East Center Avenue, Suite 301, Mooresville, NC 28115 (704) 663-1699
County: Stanly Project: PNG Prospect Ch(Airport)Rd Replace Proj Ph 11 River basin: Yadkin-PeeDee
Person financially responsible: Piedmont Natural Gas -Randy Webb, Operation Supervisor Project #: STANL-2021-006
Address: 5601 Cannon Drive, Monroe, NC 28110
1. Project Location: Airport Road, Albemarle
Pictures: No
2. Weather and soil conditions: Sunny, Workable Soils Initial inspection: No
3. - Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes If no, check violations below:
5. Violations:
6. Is the site in compliance with NPDES Permit NCGO10000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name): No One Onsite Title:
Inspection report: Sent Report Date given/sent: November 02, 2022
9. Corrective action needed:
10. Comments: Permanent ground cover sufficient to restrain erosion has been established. No additional
self -monitoring or self -inspections are required. Project is in compliance and released under
the SPCA. Termination of coverage under the NPDES General Stormwater Permit for
Construction Activities (NCGO 1) must be requested by the permittee via a Notice of
Termination (NOT) unless permit approval date was prior to April 2019.
The NOT is available at: https://edocs.deq.nc.gov/Forms/NCGOI-Termination. Please note
that this correspondence must be uploaded as part of completing the NOT process.
Reported by: Jeffrey Chandler Others present:
Date of inspection: November 01, 2022 Time arriving on site: 4:25 PM Time leaving site: 5:30 PM