HomeMy WebLinkAbout20221520 Ver 1_01 Cover Letter-PCN v1.0 MCZ T-Hanger_USCOE 2021 09-13_20221026GEORGE K LANKFORD, LLC 238 Shady Grove Road
Pittsboro, NC 27312
919-602-0127 gklankford91 @gmail.com
October 26, 2022
Mr. Billy Standridge
U.S. Army Corps of Engineers
Washington Regulatory Field Office
2407 W. 5th Street
Washington, NC 27889
RE: Pre -Construction Notice (PCN) for the Martin County Airport T-Hanger Expansion
Martin County Airport, Williamston, NC
Dear Mr. Standridge,
I am pleased to submit a Nationwide Permit 39 Pre -Construction Notification (PCN) for the proposed new
Martin County Airport (MCZ) T-Hangar Expansion. The PCN is being submitted as a notification on behalf
of the Martin County Airport and the design engineers, W.K. Dickson & Co., Inc.
The Martin County is a publicly -owned, public -use airport that serves the general aviation community
and many commercial businesses that depend upon air transport. The airport currently has a waiting list
for hangar space and is in need of additional T-Hangars. To address the public need for additional hangar
space, the project includes construction of ten individual hangar bays on the north side of the existing T-
Hangar building. Access will be provided by construction of a taxilane and apron connecting to existing
taxiway infrastructure. The taxiway is under construction. Construction of the T-Hangar expansion will
provide 10 individual hangar spaces, will address the waiting list, and provide safe access to the taxiway
and runway.
This project will consist of 3 construction phases: Taxilane, Apron/parking area, and T-Hangar expansion.
The first phase will be construction of the taxilane that will provide access to the north side of a 10-unit
T-Hangar building and preparation of the building site. The second phase will be construction of an apron
that will provide locations for two (2) future 60'x60' hangars. The third phase will be construction of the
additional T-Hangars. Within the study area is a small, depressional, wetland of 0.15 acres without an
apparent surface connection to the drainage network. The wetland is mostly herbaceous with small shrubs
and saplings that are removed occasionally to prevent overgrowth of trees and to limit wildlife habitat
near the runway. The wetland is anticipated to be filled, resulting in a permanent loss of this wetland and
require compensatory mitigation. An In -Lieu Fee compensatory request has been sent to the Division of
Mitigation Services.
Please don't hesitate to contact me at 919-602-0127 (gklankford9l@gmail.com) or Jason Elliott, PE
(Project Manager), at 919-256-5616 Oelliott@wkdickson.com) if you should have any questions. Please
include both of us on any email exchanges.
Billy Standridge
US Army Corps of Engineers
October 26, 2022
Thank you for your prompt attention to this important project and please let me know if you have any
questions or require any additional information.
Sincerely,
George K Lankford LLC
George Lankford, President
cc: U. James Bennett, County Manager, Martin County
Jason Elliott, PE, Project Manager, W.K. Dickson & Co., Inc.
Attachments
Page 2 of 2 GEORGE K LANKFORD, LLC
238 Shady Grove Road
Pittsboro, NC 27312
919-602-0127
ATTACHMENTS:
Cover Letter
Figures and Project Information
Figures
Figure 1 - USGS-Vicinity Map
Figure 2 - Project Overview
Figure 3 - Proposed Project
Figure 4 - Soils Map
HPOW 2.0 — Street View
HPOW 2.0 — Aerial View
Photo Log
Property Tax Card
Protected Species Information
Natural Heritage Program Element Occurrences Report
IPaC List of Threatened and Endangered Species List for this Project
Biological Evaluation
Wetland Data Sheets and WAM printouts
Wetland Data Sheets
NCWAM Field Assessment Form
Plan Sheets