July 12, 2022
Patrick Adams
M/I Homes of Raleigh, LLC
1511 Sunday Drive Suite 100
Raleigh, NC 27607 Expiration of Acceptance: 1/12/2023
Project: Friendship Station Sections 1&2 County: Wake
The purpose of this letter is to notify you that the NCDEQ Division of Mitigation Services (DMS) is willing to
accept payment for compensatory mitigation for impacts associated with the above referenced project as
indicated in the table below. Please note that this decision does not assure that participation in the DMS in-
lieu fee mitigation program will be approved by the permit issuing agencies as mitigation for project impacts.
It is the responsibility of the applicant to contact permitting agencies to determine if payment to the DMS will
be approved. You must also comply with all other state, federal or local government permits, regulations or
authorizations associated with the proposed activity including G.S. § 143-214.11.
This acceptance is valid for six months from the date of this letter and is not transferable. If we have not
received a copy of the issued 404 Permit/401 Certification within this time frame, this acceptance will
expire. It is the applicant’s responsibility to send copies of the permits to DMS. Once DMS receives a copy
of the permit(s) an invoice will be issued based on the required mitigation in that permit and payment must
be made prior to conducting the authorized work. The amount of the in-lieu fee to be paid by an applicant is
calculated based upon the Fee Schedule and policies listed on the DMS website.
Based on the information supplied by you in your request to use the DMS, the impacts for which you are
requesting compensatory mitigation credit are summarized in the following table. The amount of mitigation
required and assigned to DMS for this impact is determined by permitting agencies and may exceed the
impact amounts shown below.
River Basin Impact Location
(8-digit HUC) Impact Type Impact Quantity
Cape Fear 03030002 Riparian Wetland 0.226
Upon receipt of payment, DMS will take responsibility for providing the compensatory mitigation. The
mitigation will be performed in accordance with the In-Lieu Fee Program instrument dated July 28. Thank
you for your interest in the DMS in-lieu fee mitigation program. If you have any questions or need additional
information, please contact Kelly.Williams@ncdenr.gov.
Sincerely,
FOR James. B Stanfill
Asset Management Supervisor
cc: Jeff Harbour, agent
Cohn, Colleen M
From:Harbour, Jeff W <Jeff.Harbour@terracon.com>
Sent:Thursday, August 4, 2022 11:09 AM
To:Phillips, George L CIV USARMY CESAW (USA)
Cc:Cohn, Colleen M; Patrick Kiernan
Subject:\[External\] RE: Friendship Station Section 1&2 / Apex / Wake County /
SAW-2017-00235 / Request for Additional Information
Attachments:Friendship Station Sections 1 and 2 DMS Acceptance.pdf
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Here is the SOA. I will address your other comment asap. Thanks Lyle
Jeff Harbour, PWS
Senior Scientist I Natural Resources
2401 Brentwood Road, Suite 107 I Raleigh, NC 27604
D (919) 547-1080 I M (919) 805-4208
jeff.harbour@terracon.com I Terracon.com
From: Phillips, George L CIV USARMY CESAW (USA) <George.L.Phillips@usace.army.mil>
Sent: Thursday, August 4, 2022 10:58 AM
To: Harbour, Jeff W <Jeff.Harbour@terracon.com>
Cc: Cohn, Colleen M <colleen.cohn@ncdenr.gov>
Subject: Friendship Station Section 1&2 / Apex / Wake County / SAW-2017-00235 / Request for Additional Information
Mr. Harbour,
I have reviewed the above referenced project and need the following questions/comments addressed to ensure
compliance with NWP terms and conditions.
1. Based on the application the project proposes to discharge fill material at Impact Area A. Based on the scale of
the site (232 townhome lots) it is unclear if the project has avoided and minimized to the maximum extent
practicable as required by NWP General Conditions 23(a) and (b). Please provide additional information to assist
the Corps in verifying compliance with GC 23(a) and (b) or redesign to avoid or minimize to the maximum extent
practicable.
2. Based on the application it is unclear which mitigation option is proposed. The options presented on the on the
PCN include: mitigation bank, payment to in-lieu fee program, and permittee responsible mitigation. Please
provide a brief statement indicating which options is proposed and if necessary what ratio is proposed. If a bank
or ILF is proposed please provide a letter from the entity.
Please submit the above information within 30 days of receipt of this Notification or we may consider your application
withdrawn and close the file. Please email (George.L.Phillips@usace.army.mil) me if you have any questions/concerns.
1
Lyle Phillips
Regulatory Specialist
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Phone: (919) 554-4884, Ext. 25.
Fax: (919) 562-0421
Email: George.L.Phillips@usace.army.mil
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is
located at https://regulatory.ops.usace.army.mil/customer-service-survey/ . Thank you for taking the time to visit this
site and complete the survey.