Loading...
HomeMy WebLinkAboutWQ0003626_Meeting Notes_20110225Barber, Jim .7 From: Barnhardt, Art Sent: Friday, February 25, 2011 1:19 PM ' To: Barber, Jim; Shields, Joel; Honeycutt, Tony Subject: Friday Campbell Soup Meeting Notes Notes: 2/25/11 from Campbell Soup Meeting 1) Floated the proposal of taking B Field to a 30 million gallon, aerated, Tined holding structure. Using alternative site is not out of the question, just not #1 choice. 2) Discussed daily vs. monthly average flow and how it is determined what we enforce on. I told them it is a judgment call on my part and each permit violation is evaluated independently on it's own merits...but generally I will not go with daily violations unless there are monthly average violations, or other noncompliance issues like run-off, poor wastewater treatment etc..too. 3) Discussed the removal of some Field A & Field C acres (typically wet areas) by stopping the pivot, putting sub -tile drainage, berm area to prevent wastewater from collecting above the tile, all done meeting the required horizontal setbacks. 4) Asked about the outcome of the runoff event (if he should expect to get a penalty). 5) Sewer line extension being pursued to both Maxton or Westpoint Plant. They want to get one or the other but that is a 5 year plus proposition. I followed the meeting up with a call to Jon Risgaard, asked if we could allow issue a major modification to their permit (under agreement document...SOC, etc) for a set period to allow the work to proceed, not have 2T kick in until the end of the agreement period (sewer connection time). It should Work out. Jim, we need to be sure we understand the variables involved so if you could work this concept to see if any red flags are identified, that would be great. We can have a discussion whenever you are ready. Thanks ArtB. c 14-6 MEA1-11 rzek 7itev S�nA 6-e- 1 Job %X (EJLT Legend EN Improvements Maintenance Water Level Pipe New Drainage Installed i ovedExistin. Drain 444 L • ! • IR • • - Ob. e ar lk a‘` • 40 • irk°, .1' 4,40 410"1 .16.411 %MP - I 4' "IA* 'Fib 1111 ' - 4+; e• 1%0 , - Ai • • . .e, . .... ' .,.. '410 ..."' J li 4 -ft 44/10thse i * '' 1 ..%,144tati*„..ii• loy ,,,,, o• rip 1/4 Site * 4'."41P, A.". .__ ' - :14,•01_ __.___, V : ALI_ a • a• % •11.0 inw 44. of " 4«, . ••• kll 4. ' Olt ilk% ., . 4 k 14 4 pidk' ibb . 'I: rste II .. ....0 lb • i 1 .,...L. . , s,;,,,,. °pm.' % ' • • .0, -,•-a• to imihi ' • a- • ‘40 dr dies, hi •44. 411o, 4111P *tir ‘Ne, , • a • %• et • • 1i k • • • 4' 40 1 at V OM. Al 7 A Southmost Corner Bottom EL 218.455 MaxDepth 3.625 r t� NOTE: • Calculation does not account for slope along berm • MaxFiII is Calculated at Pump House overflow -6" > Lowest EL is set at Ed Tank Lowest Floor EL N" VOLUME 3 874 524.0775 CF 28 983 452.839 gallons [US, liquid] Pump Pit North Side Bottom EL 215.51 MaxDepth 6.57 i Bal ber, Jim From: Robert Ellis [raellis@laurinburg.org] Sent: Tuesday, April 19, 2011 3:01 PM To: Barber, Jim Subject: FW: Campbell Soup Company Wastewater Service Attachments: • • Tech Memo REV2.doc; WWTP Improvements Cost Opinion.pdf; PS & FM Cost Opinion.pdf; Laurin burg WastewaterSystem_Fig. pdf From: Ed Burchins jmailto:eburchins@laurinburg.orgl Sent: Tuesday, July 06, 2010 6:08 PM To: war Iaurinburq.orq; 'Robert Ellis'; 'Cindy Carpenter';. 'Stacey McQuage' Subject: FW: Campell Soup Company Wastewater Service Here is some information for a meeting I would like to have at tomorrow morning 9:00 arn, Bill and Cindy, sorry for the short notice but I feel like you both need to be involved. Let me know if there is a problem. Edward F.Burchins City Manager 910.291.1727 (Office) 910.280.1802 (Mobile) eburchins@laurinburg.org From: Zimmer, David jmailto:ZimmerDT@cdm.com] Sent: Monday, June 14, 2010 5:25 PM To: eburchins@laurinburg.orq Cc: Kennedy, Laurin; Scuras, Sean Subject: Campell Soup Company Wastewater Service Ed — Attached is the draft technical memorandum related to proposed wastewater service for the Campbell Soup Company. Please contact me or our Project Manager, Laurin Kennedy, when youare ready to discuss. Have a good night. bave «Tech Memo REV2.doc» «WWTP Improvements Cost Opinion:pdf» «PS & FM Cost Opinion.pdf» LaurinburgWastewaterSystem_Fig.pdf» 1 f Memorandum To: Edward F. Burchins, City of Laurinburg From: Sean Scuras, PhD; PE, CDM Laurin Kennedy, PE. BCEE, CDM Date: June 14, 2010 Subject Campbell Soup Company Wastewater Conveyance/ WestPoint WWTP Improvements 1.0 Background The City of Laurinburg (City) is having ;discussiojngs with tie Capmpbell Soup Company (CSC) located in Robeson County, NC about options for treatment of iibe CSC wastewater produced from their plant operations The plant is cuurrently underconsentorder by the North Carolina Department of Env' oriment and ppNatural Resources 1(NCDENR) because their wastewater cannot comply with i e terms, conditions or limitations of their National Pollutant Discharge Elimination System N iiDES emit. i y The City of1,aurinburg has'alsolbeen evaluating thelbenefits of purchasing the WestPoint pp e iW ; � �iat r � ' "` �i(WWTP) in Wagram, NC that is currently for Pe ere�l�Wastewater�Water Treatment Plants �`a�s� sale C t� was retained �by,the Ctv of Laurinbur`g to evaluate the construction and capital costs associated with pumping CSC wastewater to the WestPoint WWTP and improvements needed at the WWTP to treat;this wastewater. This memorandum presents the basic facility WI ‘to*and infrastructurearequirements capital costs, and other considerafioris to assist the City in evaluating this optic n. l 2.0 Campbell Soup Company Force Main and Pump. Station In order to convey wastewater flow from the Campbell Soup Company (CSC) to the WestPoint WWTP, a new pump station and force main are required: A preliminary force main route was identified and the proposed force main would be aptr6ximately 31,500 linear feet (6 miles) in length. The route follows existing highways and stater' pads in order to minimize the amount of permanent sewer easement and temporary construction easement needed for the project. The proposed route is shown in Figure 1. Tie proposed force main route begins at the CSC plant and follows the following roads: . • NC Hwy 71 Mr. Edward Burchins June 14, 2010 Page 2 • McGirt Rd (SR 1308) McGirt Bridge Rd (SR 1309) • McGirt Gin Rd (SR 1310) • Lee's Mill Rd (SR 1425/1427) • Airbase Rd (SR 1437) If a project can be constructed within NCDOT right-of-way, then easement does not need to be acquired. However, it is assumed that NCDOT only has maintenance right-of-way (back - of -ditch to back -of -ditch) along the majority of these roads, so some, amount of easement will be necessary. The pipeline material was assumed to be C905 PVC in order to provide corrosion protection and since this material is more cost effective than ductile iron. An 18-inch diameter pipe is recommended to accommodate the expected range in flows pumped from CSC. Air release/vacuum relief valves will be required at various locations along the alignment and would be located in a protective structure such as a manhole. Approximately 15 air/vacuum valve stations will be required depending on the final alignment. Pipeline crossings requiring trenchless construction methods are anticipated along the force main alignment. The following crossings were identified and would require trenchless construction methods such as jack -and -bore or directional drilling:. • State Roads (three assumed) • Streams and wetlands (one at Lumber River assumed) The Campbell Soup Company currently has six 800 gallon per minute (gpm) pumps that are used to convey wastewater to spray fields for land application. This equates to a firm pumping capacity of 4,000 gpm with one pump out of service, or 5,760,000 million gallons per day (mgd). The average daily wastewater flow between January 200f and April 2010 was 2.68 mgd (1,860 gpm), whereas the maximum daily flow was 4.84 mgd (3,360 gpm). It is assumed that a firm pumping capacity of 4,000 gpm is sufficient to convey all CSC wastewater flow to the WestPoint WWTP, however, the existing pumps are most likely not capable of overcoming the head conditions necessary to pump flow to the WestPoint WWTP. The ground elevation at the CSC facility is at approximately 192 feet, so it was assumed that the pump centerline elevation will be 180 feet in the wet well. The high point elevation between the pump station and the WestPoint WWTP is approximately 224 feet. This results in a static head of approximately 45 feet. Figure 2 illustrates the profile of the,proposed force main which shows these elevations. The total dynamic head (TDH) required for the CSC pump Mr. Edward Burchins June 14, 2010 Page 3 station would be approximately 225 feet, including pipe friction loss 4nd static discharge head at a design flow of 5.8 mgd. As a result, it was assumed that a new pump station will need to be constructed at CSC to pump wastewater flows to the WestPoint WWTP. Figure 2 — Sewer Force Main Profile 225 220 215 210 c 205 0 n 200 :CSC Pump - Station 195 190 185 WestPoint WWTP 0 5,000 10,000 r 15,000 20,000 25,000 30,000 Force Main Length (ft) In order to accommodate a firm pumping capacity of-4,000 gpm while keeping the appropriate velocities in an 18-inch diameter force main, a new pump station with three 2,000 gpm submersible pumps is recommended. The third pump is required for redundancy. Submersible pumps are cost-effective and currently used in this type of application. The resulting pump station criteria are summarized in Table 1. If two:pumps are in operation, then this results in a velocity of 5 feet per second (ft/sec) within the force main. When one pump is on operation, the minimum velocity is 2.6 ft/sec, which is acceptable for keeping solids from settling in the pipeline. Mr. Edward Burchins June 14, 2010 Page 4 Table 1 - Pump Station Criteria Description Number of Pumps Criteria ' 2 duty; 1 standby Pump Type Submersible Pump Output (gpm each pump) , 2,000 Firm PumpingCapacity5.8 mgd Motor Horsepower (each pump) 250 hp 3.0 WestPoint WWTP Improvements 3.1 WWTP Evaluation Summary CSCs wastewater would add 4.84 MGD of maximum day flow to: the: existing 0.7 mgd from the WestPoint/Gulistan plant for a total maximum day flow of 5.54 mgd-to the WestPoint WWTP. Peak flow (including WestPoint/Gulistan flow) would be approximately 4500 gpm (6.48 mgd). BOD loading would increase to approximately 42;48271k/ day combined loading during maximum month. On a maximum month basis the flow would be approximately'4:4 mgd (3.7 mgd CSC and 0.7 mgd Gulistan) but because the CSC wastewater is so strong,' it would require essentially all of the available aeration basin capacity during peak production periods. Also, because the waste is high in BOD but low in nitrogen and phosphorus, these nutrients will need to be added in sufficient quantity to provide the minimum required for good activated sludge performance. Clarifiers allow for up to 9.2 mgd peak flow but would require significant repairs to provide the required peak flow capacity. Two RAS pumps (currently not used) will likely need to be replaced or rebuilt. The recommended improvements are summarized below: • 30 hp 4500 gpm influent pump for firm capacity (could be`deferred because influent goes directly to aeration basin without pumping) • Chemical feed facilities for pH adjustment, nitrogen and phosphorus addition (required) • 800 hp of surface aerators at the aeration basin (required • Complete rehabilitation of one 90 ft diameter clarifier (could 'be deferred if flow is held to less than 6.1 mgd peak) Mr. Edward Burchins June 14, 2010 Page 5 • Repairs on second 90 ft diameter clarifier • Two 15 hp 1950 gpm RAS pumps and valves (could be ,deferred if further investigations show that the existing pumps are operable) • 2.3 MG of additional aerobic digester tankage • 500 hp of surface aerators at the aerobic digesters Estimated cost for these improvements is approximately $5.85 million (including a 30% contingency and a 15% allowance for engineering, legal and administrative costs). A detailed cost estimate for these improvements is attached to this memo and shown in Section 4 below. An alternative approach that may be worth consideration would be to convert the 10 MG EQ basin to service as the aeration basin (by adding the required aerators). Then the existing 6 MG aeration basin could be repurposed for use a additional aerobic. digester basin. These volumes better match the increased BOD loading and would allow some additional plant capacity for future increases in loading. Cost for this approach would be similar to the above but less the cost for new digester tanks. Also, because the EQ would be eliminated, additional wetwell or EQ volume would be needed at Campbell's to buffer peak hour flows. Note that under either treatment -scenario, the operating cost for power, chemicals, and biosolids handling will be significantly higher on a per 1000 gallons treated basis than is typical because the BOD concentration of the wastewater is so high: Such increased cost for industrial wastewater is often recovered through a surcharge on,excessive BOD concentration. 3.2 Wastewater Flow and Load Characteristics Wastewater flow and load characteristics for the wastewater generated by CSC operations during 2009 were provided and are attached as Appendix A. The. current flow at the WestPoint WWTP is approximately 0.7 mgd from the WestPoint/Gulistan operation. Characteristics of that wastewater have not been determined for this evaluation. It will be assumed that the concentrations of BOD and nitrogen in the WestPont/Gulistan flow are no greater than in the CSC flow. Actual WestPoint/Gulistan wastewater,characteristics should be reviewed to confirm this assumption. 3.2.1 Flow Daily wastewater flow data from Campbell's for the period from January 2006 through April 2010 were used to estimate daily, annual average, maximum month, and maximum day flows. A summary of those flows is shown as Table 2 below. Table 2 - Campbell's Historical Wastewater Flow Mr. Edward Burchins June 14, 2010 Page 6 Flow, MGD Annual Maximum Year Average Average Day in Maximum Month .. Day 2006 2.68 3.66 .4.84' 2007 2.58 3.33 . .4.72 2008 2.45 3.31 4.53 2009 2.31 2.86 ..4.01. 2010 2.06 ' 2.29 ' 3.44 Maximum 2.68 3.66 .4.84 According to CSC staff, the majority of the wastewater generated.fxom soup production operations is from cleaning operations on night shift and there are'no, plans for expansion that would increase the wastewater flow. Existing pumping equipment consists of six 800 gpm pumps for a total peak capacity of 4800 gpm (6.91 mgd) and a firinpeak capacity of 4000 gpm (5.76 mgd). 3.2.2 BOD A total of 20 samples were analyzed for BOD in 2009. The annual averageBOD loading was 15,933 lb/day. -However, the loading is highly seasonal with the t , ro:maxirnum BOD loading values (31,179 lb/day and 35,682 lb/day) occurring in August durin'g°the late summer period of peak production and wastewater flow. Because a limited quantity. :of data is available, the maximum values of 35,682 lb BOD/day will be used for this evaluation rather than a statistically less extreme value. Based on this design loading; the average BOD concentration during the maximum month would be approximately 1,170 mg/L. _ Therefore, the WestPoint/Gulistan flow (if at the same BOD concentration).would:increase the loading by 6,8001b/day to a total of 42,482 lb/day.. Although the EQ basin volume is sufficient to smooth daily peaks, it is too small to smooth the late summer production peak that appears to continue for 45 days or more. Therefore, we have considered the•capability to meet permit while treating at the maximum 42,482 lb/day loading. 3.2.3 Nutrients Nutrients (particularly nitrogen and phosphorus) are required to±support biological growth in the activated sludge process. In excess, nutrients may need special conditions for treatment but if not available in sufficient proportion to the wastewater BOD,, lack of nutrients can limit growth of the microorganisms that are responsible for treatment. This is uncommon when treating municipal waste but industrial waste treatment often requires nutrient addition. The typical major nutrient requirements are 0.087 mg N/mg biomass COD formed and 0.017 mg P per mg biomass COD formed. Based on the estimated WAS' production of 42,482 lb/d and that it has a COD of 1.21b COD/ lb WAS, the nitrogen and phosphorus requirements are estimated at approximately 44351b N/ day and 8661b P/ day during the maximum Mr. Edward Burchins June 14, 2010 Page 7 production period. Actual maximum loadings are less than half that requirement. It is very likely that nutrient addition (nitrogen and phosphorus) will be required to effectively operate the activated sludge process on this wastewater. 3.2.4 Sodium and TDS Based on the reported cation levels (the concentrations of sodium and other positively charge ions) the maximum total dissolved solids concentration of the wastewater is estimated at no more than 700 mg/L. Although this is somewhat higher than is typical for municipal wastewaters in the area, it is not at a level that would impact biological activity in the activated sludge process. The concentration of monovalent cations: (estimated at a maximum of 11 meq/L for this wastewater) can cause flocculation problems if greater than10 meq/L. Based on the 2009 data, for most months the monovalent cation concentration will not be a problem but when it exceeds 10 meq/L the resulting settling problems can be overcome by adding multivalent cations (such as magnesium) to reduce the monovalent :multivalent ratio to < 2:1. Magnesium addition is most common. If added in the form of mag solution (MgOH2) it can also add alkalinity and increase pH. 3.2.5 pH The pH of the CSC wastewater is low (averaging 6.0 but often as low as 4.5 or less). Chemical addition will be required to increase pH before the wastewater enters the activated sludge process. A pH of 8 is a reasonable target and adjustment of pH to this level should also provide sufficient alkalinity to maintain pH above 7.2 throughout the process (important for optimum nitrification performance). Typical chemicals usedfor.adjiistment of alkalinity and pH include lime (CaOH), caustic (NaOH), and mag (MgOH2). Of:these, both lime and caustic would further increase the concentration of monovalent cations so'tle use of mag (a divalent cation) is recommended. A chemical feed point exists near the WWTP influent, new storage, feed and mixing equipment may be required. 3.3 WWTP Evaluation Sean Scuras and Dan Barnes of CDM made a'site visit to the Westpoint Stevens Wagram WWTP on May 13, 2010 for a preliminary evaluation of the facilities and equipment. Operator Ronald Locklear provided a tour and information about.the facilities. No manufacturer information or operation and maintenance manual'was'available. 3.3.1 Headworks and Influent Pumping The existing headworks includes a mechanical bar screen in good; condition and a manual backup. The influent is then pumped up to a 10 MG equalization.basin by a pair of 40 hp screw pumps. Lift is estimated at 15 feet. Assuming 70% operating efficiency, these pumps are estimated to have a capacity of.7400 gpm (10.6 mgd) each. Tlie pumps are in poor condition with significant corrosion and deformation that is certainly reducing pumping Mr. Edward Burchins June 14, 2010 Page 8 efficiency. Only one of the pumps was operating at the time of the inspection and it is uncertain that the other pump (that appeared to be in worse condition) would operate reliably. At least one of the screw pumps should be replaced with a pump at a capacity of at least 4,500 gpm to assure firm pumping capacity. However, because the influent can be diverted directly to the aeration basin without pumping, screw pump replacement could be deferred. 3.32 EQ Basin The 10 MG EQ basin is mixed and aerated using two 50 hp aerators and two 40 hp mixers. Each aerator is rated to mix a 150 ft diameter. These could be supplemented with the two 40 mixers currently in use on the aeration basin that will no longer be needed there as the increased loading will require sufficient aeration to mix the basin. Assuming that the EQ is relatively well mixed now, adding the mixers from the aeration basin should assure that it remains well mixed even with increased solids loading. 3.3.3 Aeration Basins The existing aeration basin is reported to have a volume of 6 MG. '..Air and mixing are provided by six 50 hp (some may be 75 hp) floating aerators (at least 200 hp total) and two 40 hp mixers. Assuming the field oxygen transfer efficiency of the aerators is approximately 1.75 lb 02/hr/hp (42 lb 02/day/hp), the existing aerators can transfer. at,least 84001b 02/day. At 1.0 lb 02/lb BOD, the maximum BOD loading will require approximately 42,482 lb 02/day. The unmet oxygen demand of 34,082 lb 02/day will require approximately 811 hp of additional aeration. A spare aerator is also recommended. Electriealservice to the plant may have to be expanded to meet this significant increase in power demand. Generator capacity may also need to be increased. These costs are not estimated in this memo. With sufficient aeration, when operated at a mixed liquor of 3,500 mg/L the existing aeration basin volume is adequate to provide a minimum 5.5 day SRT during the peak production period. Because this occurs during the warmest part of the year, this SRT would be sufficient to provide complete nitrification. However, nitrification may not be.necessary because the N:BOD ratio is so low that excess ammonia is unlikely to be a problem. Without nitrification considered, the 5.5 day SRT is more than adequate to provide for good flocculation characteristics. Note however, that the large complete mix aeration basin will still be prone to filamentous bulking and the concurrent settleability problems. 3.3.4 Final Clarifiers One of three 90 ft diameter clarifiers was in operation (#2). Clarifier.,#1 was out of service but only partially drained. Although the concrete appeared to be in faireondition, the steel weirs and scraper mechanism were severely corroded. Complete rehabilitation of Clarifier #1 is recommended before placing it back into service. Mr. Edward Burchins June 14, 2010 Page 9 Clarifier #2 appears to be operating well and the steel that could be observed with the unit in service was in fair condition. The concrete is not in the best condition.as much of the aggregate is exposed. The condition of equipment and concrete below the waterline is unknown but is obviously serviceable. Clarifier #3 was out of service and mostly drained but the scraper mechanism was operating. However, the skimmer arm and center well have been damaged and require repair before the clarifier could be placed back into service. Although the major components of the scraper mechanism appear to be in fair condition, a more complete inspection is needed to confirm that there is no further damage from the same incident that bent the skimmer and center well steel. The weirs and baffles are moderately corroded and should also- be replaced. Based on clarifier diameter, SVI of 150 mL/g, and MLSS of 3500 mg/L, each clarifier is estimated to have a hydraulic capacity of approximately 4.6 mgd at•peak hour. Currently no backup is available for the operating clarifier. With Clarifier #3 repaired; the firm capacity would be 4.6 mgd, which provides Class I reliability for up to 6.1 mgd peak flow (firm capacity must be at least 75% of Class I flow). Although Clarifier #1•should be rehabilitated at some point it is not required to treat the CSC flow. 3.3.5 RAS Pumps RAS for Clarifiers #1 and #2 is pumped by a set of three centrifugal pumps located in a pit near the clarifiers. We were unable to enter the pit so couldonlyobserve the pumps from above. The pumps appear to be in moderate to poor condition. Valves on the pump suction side appear to be in poor condition and have not been exercised for long time according to the operator. If the backup pump were needed, it may not•be possible to valve it into service. At a minimum, operability and capacity of two of the three existing RAS pumps should be confirmed with Clarifier #2. It is recommend that the RAS pumps and valves.for Clarifiers #1 and #2 be replaced. A minimum RAS pumping capacity of 60% is recommended during peak hour flow so new RAS pumps should be sized to provide a capacity of at least 2.8 MGD (1950 gpm) each. Assuming a head of 20 ft, each pump would be approximately 15: gip;: The existing RAS pumps at Clarifier #3 are 15 hp each and in good condition. 3.3.6 Aerobic Digestion The existing aerobic digester has a volume of 1.5 MG. Six 40 hp (240 hp total) surface aerators are currently installed. A minimum of 30 days detention tune is recommended to achieve stabilization during the peak loading period. That detention time can be provided at a WAS flow rate of up to 50,000 gpd. With gravity thickening or decanting, the WAS can be thickened so that the digester contents will average 3 % solids (30,000'thg/L). At 30,000 mg/ L and 50;000 gpd, the digester is capable of handling up to 12,510 lb/ d of WAS. Because of the low TSS/BOD ratio, we can assume a yield of no more than0:75 lb WAS TSS/lb BOD Mr. Edward.Burchins June 14, 2010 Page 10 during peak operation, giving an estimate of up to 31,8621b WAS TSS/d produced during max month. Therefore, the existing digester volume is inadequate and approximately 2.3 MG additional digester volume is required to stabilize the maximum month WAS flow. The oxygen requirement for aerobic digestion is approximately 2.3 lb 02/1b VSS destroyed. Assuming the WAS is 80% VSS and there is 45% destruction in the digester, up to .11,4701b VSS/ day will be destroyed for a peak oxygen demand of up to 26,3811b 02/day. At 1.51b 02/hr/hp (361b 02/day/hp, oxygen transfer is less efficient in digesters) approximately 733 hp of surface aerators would be required to aerate the total digestet volume. Allowing for the existing 240 hp of aerators, approximately 500 hp of additional aerator would be needed for the digesters. Aeration density would be about 193 hp/MG, which is greater than the approximately 100 hp/MG minimum for mixing. Additional digester volume and aeration would be needed before the peak production period wastewater could be treated. 4.0 Feasibility There are many considerations the City will need to examine m developing this concept in the implementation phase. These considerations are categorized as follows: • • NCDOT • Regulatory Approvals (USACE, NCDENR) • Easement Acquisition in an adjacent County The actual NCDOT right-of-way along the state roads identified above will have to be determined. An encroachment permit from NCDOT will then have' to be obtained for working within the NCDOT right-of-way and crossing under NCDOT roads. The State Environmental Policy Act (SEPA) requires an environmental assessment (EA) for pump stations with permitted design flows greater than 2.5 mgd. Therefore, an EA would be required for this project. Since the force main will cross the Lumber River, a permit from the US Army Corps of Engineers and a 401 Water Quality Certification must be obtained from NCDENR. A NCDENR Fast Track permit for the construction of Pump Stations and Force Mains will also have to be acquired in addition to a Sedimentand<Erosion Control Permit and an Authorization to Construct for the WWTP improvements. • Easements will need to be acquired in Robeson County, so the City will need to determine the legal aspects of this easement acquisition process. A summary of planning -level capital costs for the required facilities are presented in Tables 3 and 4. Detailed cost estimates are attached to this memorandum: Improvements that can Mr. Edward Burchins June 14, 2010 Page 11 possibly be deferred at the WestPoint WWTP as described in Section 3. above are shown as Phase 2 costs in Table 4. The capital cost estimates are in current dollars (June 2010) and assume traditional design -bid -build delivery. Table 3 — Summary of Estimated Capital Costs, Pump Station and Force Main Description Pump Station Cost (2010 $). $3,240,000 Conveyance Facilities $5,080,000 Construction Total $8,320,000 Engineering, Legal & Administration (15%) $1,250,000 Land Acquisition Contingency $100,000 Total Capital Cost $9,670,000 The engineering, legal and administration cost (15-percent of the construction total) is an allowance for estimated services for preliminary design, final design, permitting and bidding assistance, and engineering services during construction (not including full-time resident engineering). Table 4 — Summary of Estimated Capital Costs, WestPoint WWTP Improvements Description Chemical Feed Cost (2010 $) Phase 1 Improvements $175,000 Cost (2010 $) Phase 2 Improvements Influent Pumps $150,000 Aeration Basin/Mixers $386,000 Final Clarifiers/RAS Pumps $79,000 $380,000 Anaerobic Digestion $2,760,000 • . Construction Total $3,400,000 • $530,000 Contingency (30%) • $1,000,000 . $160,000 Engineering, Legal & Administration (15%) $660,000 .� . $100,000 Total Capital Cost $5,060,000 ,..:; .',. $790,000 Mr. Edward Burchins June 14, 2010 Page 12 cc: Dave Zimmer, CDM City of Laurinburg, NC Project: WestPoint WWTP Improvements Date: June 2010 Subject: Planning Level Capital Cost Opinion Process Item Quantity" • Unit Rate Phase 1 Total Cost Phase 2 Total Cost Chemical Feed •Mg, N and P metering pumps 6 ea $20,000 $120,000 Mg, N and P storage tanks - 2500 gal 3 ea- $15,000 $45,000 Rapid mixer • 1 ea ' .,-$10,000 . $10,060 Influent pumps Open screw pump, 30 hp, 4500 gpm, 15 ft lift (installed in existing structure) 1 ea ' • _ $150,000 - ' $150,000 Aeration basin Floating surface aerators, 75 hp - 11 ea $32,000 $352,000 - - - Spare 1 ea' $30,000 $30,000 Mixers Move from aeration basin • 2 ea $2,000 $4,000 Final Clarifiers Rehab /replace scraper, 90 ft diameter" 1 ea"" •- " $$06,000 $306,000 Repair skimmer/center well/weirs and baffles _ 1 ea ' • .$79,000 - $79,000 RAS Pumps 15 hp, 1950 gpm 2 ea • ;.' $25,000 _ $50,000 6" plug valves 6 ea ` $4,000 $24,000 Aerobic digestion 2.5 MG tank 2 ea ' $1:250,000 $2,500,000 Floating surface aerators, 50 hp 10 ea " 1 $26,000 $260,000 WWTTP Improvements Subtotal $3,400,000 $530,000 Construction Contingency _ 30 % $1,000,000 $160,000 Total Construction $4,400,000 $690,000 Engineering, Legal & Administration - 15 % ,. $660,000 $100,000 Total Capital Cost $5,060,000 $790,000 City of Laurinburg, NC Project: Campbell Soup Company Pump Station/Force Main Evaluation Date: June 2010 Subject: Planning Level Capital Cost Opinion Item Quantity • .Unit Rate Total Cost Pump Station Pump station (4,000 gpm peak capacity at 225 ft TDH; 2 duty 250 HP pumps and 1 standby) 5.8 mgd $0.45 / gal $2,587,500 Pump Station Construction Contingency 25 % . $650,000 Pump Station Subtotal $3,240,000 Force Main - - - 18-in PVC force main (open cut) 31,500 If. $120 / If $3,780,000 18-in force main under roadways (trenchless) 150 If . . $1,000 / If $150,000 18-in force main under river (trenchless) 200 If $1,500 / If $300,000 Rock excavation allowance (See Note 2) 1 Is `. $2'00,000 Is $200,000 Air/vacuum valves in manholes 15 ea_ $10,000 ea $150,000 Force Main Construction Contingency 10 % $500,000 Force Main Infrastructure Subtotal $5,080,000 Pump Station/Force Main Construction Total $8,320,000 Engineering, Legal & Administration 15 % . , $1,250,000 Land Acquisition Contingency 1 Is .. $1'00,000 $100,000 Total Capital Cost $9,670,000 Notes: 1. Force main material assumed to be C905 PVC. 2. Assumes no significant rock or problematic subsurface material encountered. 3. Assumes 3 road crossings and 1 river crossing. 4. Easement acquisition cost assumed, actual cost may vary depending on final pipeline alignment. 5. All costs are in 2010 dollars. Barblir, Jim From: Robert Ellis [raellis@laurinburg.org] Sent: Tuesday, April 19, 2011 3:03 PM To: Barber, Jim Subject: FW: Laurinburg-CDM Call Attachments: Laurinburg_04_18_11.docx From: Mills, Dianne jmailto:MillsDB@cdm.coml Sent: Monday, April 18, 2011 3:05 PM To: Ed Burchins; Jenny Tippett; raellis@laurinburg.ora; smcquage@laurinburg.org Cc: Zimmer, David Subject: FW: Laurinburg-CDM Call This is a copy of the report in tracking mode. I have changed the numbers throughout the tables to reflect the changes we agreed to: Added $30K for Adm Used the Wooten report book value for plant Increased the debt service interest rate to 5.5% which increased the rate of return. After our phone call today I will send another draft version with the tracking gone. I have another conference call at 4 which I cannot change so I will only have 30 minutes. Thanks Dianne B. Mills 1 Management Consultant CDM 301 South McDowell Street, Suite 512 I Charlotte, North Carolina 28204 t/f: 704-342-4546 X205 1 704-342-2296 www.cdm.com 1 City of Laurinburg: Campbell Soup Analysis 1.0 Background & Purpose The City of Laurinburg (the "City" or "Laurinburg") is currently assessing the feasibility of treating wastewater flows from the Campbell Soup Company ("Campbell Soup"). One option the City is evaluating is the purchase of the WestPoint Pepperell Wastewater Treatment Plant (WWTP) to handle the flows from Campbell Soup. CDM was retained previously by the City to evaluate the capital and construction costs associated with adequately treating the estimated flow from Campbell Soup. In the previous study, dated June r ', it was estimated that the cost of the pump station and force main to convey to the WestPoint plant would be an estimated $9,67o,000. This estimate included engineering, legal, administration and land acquisition. For the purposes of this analysis it was assumed that Campbell Soup would fund these improvements directly and that cost is not included in this analysis. The purpose of this memorandum is to determine the hypothetical rate the City would charge Campbell Soup for the use of the WestPoint plant, assuming the purchase of the plant by the City. For this analysis, it is assumed that there will only be two customers contributing flow to the plant - Campbell Soup and Gulistan Carpeting ("Gulistan"). If additional customers are expected to . contribute flow to the plant, it would be necessary to amend the analysis to include the impact of those customers. City of Laurinburg Campbell Soup Analysis Key Team Members Dianne Mills, CDM _Brian orXer, CDM Date April 12, 2011 Formatted: Superscript The analysis follows the utility method of cost recovery, which focuses on both an operating cost component and a capital cost component. The plant operating costs and the capital improvements that would be required to treat the flow from Campbell Soup is based on CDM's previous cost estimates. For the purposes of this exercise, the purchase price of the plant is assumed to be the net book value (original cost of the plant assets depreciated to current year) as defined in the Wooten report on the WWTP. This is an important assumption to note as the actual purchase price of the plant may differ substantially from the net book value depending on the results of negotiations. Any variations in the purchase price will result in a calculated rate different from what is presented herein. The net book value calculated in the Wooten report was used as a purchase pricempslat °n-g those estimates of depreciation up to this year. An overview of the utility method is outlined in the • following section. 2.0 Overview of the Utility Method The utility method of cost recovery is based on allocating to customers the system costs for operations and maintenance separately from capital costs. The operating cost element is allocated among customers based on individual flow characteristics. The general idea is that the cost to operate and maintain the system is dependent upon the amount of flow through the system, so eaeh customer should pay its proportionate share of those costs based on flow. The process to calculate a • general O&M rate is to divide the total allocable O&M cost by total flow to get a flow per 1,00o gallon, • that applies to all customers. •1 In this analysis, the operating cost element also factors in BOD loadings from Campbell Soup. As extra strength waste, treatment of BOD loadings theoretically requires greater expenses than norr 'al. wastewater flow. Since Gulistan is not anticipated to have any BOD loadings, the estimated portion of the operating costs that deal with treating BOD are separated and allocated directly to Campbell '. Soup as a separate charge per ioo pounds. The capital cost element under the utility method contains a charge for depreciation and a return.oh rate base of the assets. This provides proper compensation for the costs of creating and replacing • assets to ensure system integrity and to cover interest costs on the debt financed portion of capital • and a return on the equity portion of assets. The approach requires a valuation of the current system, in this case the current net book value of the plant and the cost of any anticipated improvements that would be required as a result of the additional flow. These values are multiplied by a rate of return factor to calculate the annual return on rate base. The return on the rate base is added to the annual depreciation, and this total is divided by the total annual flow to determine a rate per r,000 gallons . applied to both customers. 3.0 Rate Analysis The following section details the approach to estimate the rate to adequately recover the costs of the , WWTP. For the purposes of this analysis, the following assumptions have been used: ▪ Campbell Soup is expected to pay for the entirety of the pump station and force main required to convey flow to the plant • The estimated average daily flow for Campbell Soup is 2.69 MGD, and o.7 MGD for Gulistan • Average daily BOD loadings from Campbell Soup is estimated to be 15,933 lb/day, or 58,155 roo lb annually • BOD treatment expense is assumed to be 75% of the chemicals and power costs at the plant • The rate of return is assumed to be 5.5e% which is based on the anticipated interest rate for revenue bonds • The cost of anticipated capital improvements are assumed to be bonded at a rate of 5.5e%: with and amortization of 3o years and a 2% cost of issuance. Capital is inflated at 3.o% • It is assumed the City will recover 5o% of the capital rate through a monthly fixed charge The next section describes the cost categories and how the expenses are allocated into the appropriate categories. 3.1 O&M and Capital Cost Recovery The O&M costs in this case are recovered by three separate but related rates — a general O&M charge based on total flow, a charge to recover the costs of conveyance from Campbell Soup, and an extra strength BOD treatment charge based on Campbell Soup loadings. The first step is to separate the,, expenses into the appropriate expense category. As mentioned, it is assumed that 75% of the power and chemical costs at the plant are BOD related expenses. The operating expenses related to conveyance are to be incurred entirely by Campbell Soup. All other O&M expenses are allocable to the general O&M category. COM Table i shows the breakdown of operating costs by allocable category. Table City of Laurinburg Schedule of Operating Expenses Campbell Soup Analysis Allocable Category FY 2012 General Operating Personnel $443,500 Electricity/Chemicals 383,000 Maintenance/Repairs 706,500 Professional/Contract Services/Lab 42,000 Capital Outlay 36,000 Administration 30,000 Other/Contingencv 164.500 Total Revenues $1,805,500 Operating Expenditures Campbell BOD Electricity/Chemicals $1,149,000 Operating Expenditures Campbell PS/Pipeline Electricity/Maintenance $290,000 Total Operating Cost $3,244,500 Annual capital costs are determined by calculating the annual depreciation and annual rate of return.. on plant assets. The depreciation on the plant assets were calculated using straight line depreciation.: This included both the depreciation on existing plant assets and the annual depreciation on the $3.9M in anticipated capital improvements. The rate of return is calculated using the rate of return factor multiplied by the net book value of the existing plant (estimated to be $2.7M) and the $3.9M of improvements (OCLD-Original Cost Less Depreciation). Table z shows the results of the capital cost recovery calculation. • Table 2 City of Laurinburg Schedule of Capital Recovery Campbell Soup Analysis Allocable Category . OCLD Return on Rate Capital Recovery West Point WWTP $2,681,000 $147,455 Phase 1 and 2 Improvements $3.900,000 $214,500 Total 0 $6,581,000 $361955 I Annual Depreciation on Assets West Point WWTP $144,537 Phase 1 and 2 Improvements $130,000 Total $274,537 Total Capital Cost to be Recovered $636,492 The following section outlines the calculations for the rates that would be assessed to both Campliell Soup and Gulistan. 3.2 Rate Calculations The general O&M rate is calculated by dividing the total allocated O&M cost by the total system flOw. The resulting cost per i,000 gallons applies to all flow from both Campbell Soup and Gulistan. As previously mentioned, Campbell Soup intends to incur all costs related to conveying its flow to the plant. Therefore it necessary to calculate a separate rate per i,000 gallons for the costs related to the pump station and pipeline, allocable solely to Campbell Soup. . The remaining piece to the O&M rate is the rate per BOD loading. Since Gulistan is not expected to have any BOD loadings, the BOD related expenses divided by Campbell Soup's estimated loading per year yields a rate per loading that would be assessed to Campbell Soup. Table 3 summarizes the results of the O&M rate calculation. Table 3 City of Laurinburg O&M Rates Calculation Campbell Soup Analysis O&M Annual Flow Cost per 1,000 gal General Operating Charges $1,775,500 . 1,237,350 $1.43 Campbell PS/Pipeline $290,000 981,850 $0.30 O&M .'' Campbell Loadin g '.„ (100 lb/year) Charge per 100 lb BOD Charge Calculation $1,149,000 58,155 $19.76 ccM •.. • ' . The capital recovery rate has been separated into a fixed monthly capital charge and a volumetric charge. For this analysis, the assumption is that the City will recover half of the capital cost through the fixed charge, and half through the volumetric charge. The monthly fixed charge is calculated using the pro rata share of the fixed cost to be recovered (i.e. 50% of total capital cost) based on flow. The volumetric charge calculation involves dividing half of the total capital cost by total annual flow. Table 4 outlines the capital recovery rates. Table 4 City of Laurinburg Capital Rates Calculation Campbell Soup Analysis Costs Annual Flow Monthly Fixed Charge Total Capital Cost to be Recovered: $636,492 1,237, 350 Monthly Fixed Fee $318,246 1,237,350 Campbell $21,044 Gulistan $5,476 Costs Annual Flow Cost per 1,000 gal Volumetric Rate $318,246 1,237,350 $0.26. 3.3 Estimated Impact of Rates This section describes the estimate impact the calculated rates would have on a typical bill for each customer as well as the impact on,revenue and expenses for the City. Table 5 estimates the typical monthly bills for Campbell Soup and Gulistan under the calculated rates. Table 5 City of Laurinburg Estimated Monthly Billings Campbell Soup Analysis Campbell Soup Gulistan Total Monthly Revenue General Operating Charges $117,406 $30,552 $147,958. Campbell PS/Pipeline $24,167 $24,167 BOD Charge Calculation $95,750 $95,750. Capital Charge Fixed $21,044 $5,476 $26,520.: Capital Charge Per 1,000 Gal $21,044 $5,476 $26,520'. Total Monthly Billings $279,412 $41,504 $320,916.•. Table 6 outlines the schedule of revenues and expenditures by category as it pertains to this exercise. The debt service is calculated using the inflated estimated annual improvements needed at the plant and on the estimated purchase price of the plant. As mentioned, the purchase price of the plant is assumed to be the net book value of the plant as determined in the Wooten report, -and -updated. The results of the analysis project net revenues to the City of approximately $195,000. • Table 6 City of Laurinburg Schedule of Revenue and Expenditures Campbell Soup Analysis Cost Revenues O&M Charges $2,065,500 BOD Charges $1,149,000 Capital Charges $636,492 Total Revenues $3,880,992 Operating Expenditures General Operating $1,805,500 Campbell PS/Pipeline $290,000 Extra Strength Operating $1,149,000 Total Operating $3, 244, 500 Debt Service $441,275 Net Revenue $195,217 A number of assumptions were made in this analysis order to get a starting point for the rate analysis. These assumptions if changed could have a significant impact on the suggested rates. It is very important-that---94,e-r-eleasing-te-Cacuphell-as-a-r-ate-Fee.ammendation: Buffer Selections Buffer Distance (feet) 1 Source Layer Parcels Target Layer Parcels Measure Results Segment: 0 feet feet Area: 7.95 acres rsiacK I tans a 1 ... , . .. . — - - • ' — ..:10 a ..1Z• • 40 W • • Sign In 1 Register • Contact Us • Subscribe ik LOT .o... +arm • Vacation Starts/Stops Search Pinehurst's Wagram Water Deal Not Likely Wagram water tower By John Krahnert III Tuesday, March 16, 2010 Favorite -story - Your favorites Discuss__ __.._. Share -this - Comment, Bloq about Email, Facebook, TwitterAdvertisement Specialty , Y 9 Pharmacy Now OPEN Medicine Food Fitness Knowledge Compounding ending Pinehurst's bid to buy water and -wastewater treatment plants in Scotland County for $5.5 million appears to be over. Village Manager Andy Wilkison said today that the Scotland County Board of Commissioners has still not approved the deal, and it doesn't appear that will change. The owner of the plants — WP Properties Wagram — is now shopping them to private entities, he said. "As far as the village of Pinehurst being the lead agency in trying to make something happen that would involve the Wagram plants and their use for the public in the Lumber River basin, I think that initiative has stalled out, probably permanently," Wilkison said, adding, however, there is still the possibility that another public entity could take up the cause. The two plants served a former Westpoint-Pepperell textile plant. The village announced its intention to purchase the plants last July. The deal included the plants, an intake line and 198 acres of land. It had hoped to close on the deal in November, but the deal became hampered by delays in Scotland County. According to state law, the Scotland County Board of Commissioners has the right to approve or deny the sale of utilities to an entity that is from outside of the county. The village and Scotland County reached an impasse over when feasibility and due diligence studies on the deal should be conducted. Village officials wanted approval before they committed a significant sum of money to conduct any studies. Scotland County wanted the studies completed before voting on the proposal. The deal has been hanging in limbo for a few months. Wilkison said Pinehurst has not withdrawn its proposal -and the owner of the plants hasn't rejected it, but completing the deal now seems unlikely. "It would appear that the owner sees our bid as unworkable, at least of right now," he said. He said theoretically, Scotland County could change its mind, bait said every indication leads him to believe that won't happen. He said there hasn't been anf communication with Scotland County officials recently. Village officials who supported the deal not only said the plants Would help alleviate Pinehurst's water issues, but would be a resource for the entire: region. The village had hoped to form a consortium of partners — neighboring counties and municipalities — to utilize the facilities. Mayor Ginsey Fallon said today that if anything, Pinehurst's bid to acquire the facilities has raised public consciousness and the visibility of the resource. She said the village would continue to study the possibility of additional wells to supplement its water supply. She stressed the importance of conservation and planning for the future. She hoped that the plants are still pursued. • "The end of the desire was to secure water not only for Pinehurst,.but for the entire region," she said. "That was what we were so excited about. Maybe it'll all happen anyway, but it won't be purchased by Pinehurst." Just recently, the Moore County Board of Commissioners expressed its preliminary interest in the facilities and agreed to join other communities in seeking a.grant to study the plants' potential. "If it still happens somehow, that's a good thing," Wilkison said. "That's what we wanted. To that extent, we didn't feel like Pinehurst had to be the lead on it. We were just the only ones at that time willing to take a step out there and acquire them. "If the facilities slip away and are lost for the public's possible benefit in the future, that would be disappointing." Contact John Krahnert III at (910) 693-2473 or by e-mail at jkrahnert©thepilot.com. More like this story . Village's Wagram Water Deal Falls Through • Village Still Has Interest in Wagram Plants • Village Water Deal Reaches Impasse • Water Deal Reaches Impasse . Village's Deal in Wagram Faces Delay Like Be the first of your friends to like this. Advertisement