Physical Plant Maintenance
October 21, 2022
Vanessa E. Manuel, Assistant Regional Supervisor
Water Quality Regional Operations Section
Raleigh Regional Office, NC DEQ
Subject: Compliance Evaluation Inspection
Central Carolina Community College Collection System
Permit No. WQCSD0144 Lee County
Dear Ms. Manuel:
This letter is in response to required action items identified by Mitch Hayes
during his on- site inspection performed on September 27, 2022 at our Lee
Main Campus. Action items are as follows (College responses are in red):
1. Currently there is no Grease Control Program. This program is required per
15 A NCAC 02T 00403 (a) (8). Please ensure the College adopts a Grease
Control Program. The College is currently developing a Grease Control
Program and it will be implemented by 11/30/2022.
2. There are 7 pump stations in the collection system. All pump stations were
inspected. The following are a summary of the inspections:
a) Large Animal PS — There is no identification signage. Temporary signage
will be in place by 11/15/2022. Quotes are being obtained for permanent
signage and will be installed when delivered from vendor.
b) Keller Health Building PS — There is no identification signage. Temporary
signage will be in place by 11/15/2022. Quotes are being obtained for
permanent signage and will be installed when delivered from vendor.
The visual alarm is behind a wall and is not visible to the public.
. Please raise this alarm so that is visible to the public. Visual alarm Tight will he
elevated above the wall by 11/15/2022.
The on -site generator was not tested because power to the pump station could
not be disconnected. A power down test was performed on 10/ 19/2022 and
the backup generator started and ran as required.
c) Lift # I Science Building — There is no identification signage. .
Temporary signage will be in place by 11/15/2022. Quotes are being
obtained for permanent signage and will be installed when delivered from
vendor.
CENTRAL
CAROLINA
COMMUNITY
COLLEGE
Chatham Main Campus
764 west Street
Pittsboro, NC 27312-8822
(919) 542-6495
Harnett Main Campus
1075 E. Cornelius Harnett Blvd.
Lillington, NC 27546-7672
(910)893-9101
Lee Male Campus
1105 Kelly Dr.
Sanford. NC 27330-9840
(919) 775-5401
Physical Plant Maintenance
e) Lift # 4 — The identification sticker was faded and needs to be replaced.
Temporary signage will be in place by 11/15/2022. Quotes are being obtained
for permanent signage and will be installed when delivered from vendor.
f) Maintenance Building — There is no identification signage. Temporary
signage will be in place by 11/15/2022. Quotes are being obtained for
permanent signage and will be installed when delivered from vendor.
Please call if you have questions or concerns.
Sincerely,
Ronnie Measamer
Physical Plant Manager
1105 Kelly Drive
Sanford, NC 27330
919.718.7409 (office)
919.770.9335 (cell)
rmeas073@cccc.edu
cc: Dr. Phillip Price
Ben Rankin
Mitch Hayes