Loading...
HomeMy WebLinkAbout20221010 Ver 1_More Info Requested_20220829Moore, Andrew W From: Moore, Andrew W Sent: Monday, August 29, 2022 3:11 PM To: Jeff Golladay Cc: Brown, David W SAW; Leslie, Andrea J Subject: RE: [External] RE: Request for Additional Information, Blue Ridge Metals Industrial Park, Henderson County (DWR Project #20221010) Jeff, On July 26, 2022, the Division of Water Resources (Division) received your application requesting a 401 Water Quality Certification from the Division for the subject project. Additional information in support of the project was received August 25, 2022. The Division has determined that your application is incomplete and cannot be processed. The application is on -hold until all of the following information is received: 1. The response to request 3 does not adequately demonstrate how hydrology will be maintained in the wetlands not proposed for impact. It's not clear how the project will be able to allocate run off to the wetlands while meeting post -construction stormwater requirements. Please provide additional clarification. If it is not adequately demonstrated that hydrology will be maintained in the wetlands not proposed for impact, the Division will consider that a secondary impact that will be counted toward impact totals. [15A NCAC 02H .0506(b)(3)] Pursuant to Title 15A NCAC 02H .0502(e), the applicant shall furnish all of the above requested information for the proper consideration of the application. Please provide your response by September 29, 2022. If all of the requested information is not received, the Division will be unable to approve the application and it will be denied as incomplete. The denial of this project will necessitate reapplication to the Division for approval, including a complete application package and appropriate fee. Andrew W. Moore, PG Environmental Specialist II — Asheville Regional Office Water Quality Regional Operations Section NCDEQ — Division of Water Resources 828 296 4684 office email: Andrew.W.Moore@ncdenr.gov 2090 U.S. Hwy. 70 Swannanoa, N.C. 28778 Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. From: Jeff Golladay <jgolladay@enviroscienceinc.com> Sent: Thursday, August 25, 2022 10:03 AM To: Moore, Andrew W <andrew.w.moore@ncdenr.gov> Cc: Brown, David W SAW <David.W.Brown@usace.army.mil>; Leslie, Andrea J <andrea.leslie@ncwildlife.org> Subject: [External] RE: Request for Additional Information, Blue Ridge Metals Industrial Park, Henderson County (DWR Project #20221010) 1 CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to Report Spam. Andrew, Thank you for the comments. Please see below for our response to each comment in order below: 1. The Pre -Construction Notification (PCN) is un-signed. Please provide a signed PCN. [15A NCAC 02H .0502(a)(11)] Response: Signed PCN form is attached. 2. Please provide addition information regarding how many vehicles are anticipated to be stored on the property and how it was determined that 34.2 acres of parking surface area is required. [15A NCAC 02H .0506(b)(1)] Response: The storage capacity projections could vary from 3,500 on average to 5,100 vehicles at peak times. 34.2 acres allows the capacity of 5,100 vehicles with the current layout of storage rows and drive isles. 3. Please describe how wetland hydrology will be maintained in the wetlands and streams downgradient of the proposed wetland fill areas as well as in the wetland upgradient of proposed impact W4, particularly considering stormwater will be routed away from the streams and wetlands not proposed for impact. [15A NCAC 02H .0506(b)(3)] Response: The wetland hydrology (for wetlands not proposed for impact) will be maintained by allocating runoff from the proposed site to the wetland that would be equal to the pre -development flow. The remainder of the runoff from the site would flow into the drainage basins on site to be treated to ensure the wetlands not proposed for impact would remain as they were pre -development. More detailed clarification (i.e. stormwater plan and grading plan) will be provided during the design process. 4. Please provide a figure depicting the location of the stormwater basin outlets. [15A NCAC 02H .0502(a)(9)] Response: Please see attached stormwater exhibit. We believe these responses adequately address DWR concerns. Please do not hesitate to call if you have any additional questions. Thank you, Jeff Golladay Biologist CLearWaer An EnviroScience Company a 145 7th Avenue West, Suite B Hendersonville, NC 28792 Office: 828-698-9800 ext. 304 Mobile: 815-451-8139 jeffcwenv.com WWW.CWENV.COM WWW.EnviroSciencelnc.COM OH ITNIVAIWVINC E 0 ITO From: Moore, Andrew W <andrew.w.moore@ncdenr.gov> Sent: Wednesday, August 10, 2022 12:56 PM To: Jeff Golladay <jgolladay@enviroscienceinc.com> 2 Cc: Brown, David W SAW <David.W.Brown@usace.army.mil>; Leslie, Andrea J <andrea.leslie@ncwildlife.org> Subject: Request for Additional Information, Blue Ridge Metals Industrial Park, Henderson County (DWR Project #20221010) Jeff, On July 26, 2022, the Division of Water Resources (Division) received your application requesting a 401 Water Quality Certification from the Division for the subject project. The Division has determined that your application is incomplete and cannot be processed. The application is on -hold until all of the following information is received: 1. The Pre -Construction Notification (PCN) is un-signed. Please provide a signed PCN. [15A NCAC 02H .0502(a)(11)] 2. Please provide addition information regarding how many vehicles are anticipated to be stored on the property and how it was determined that 34.2 acres of parking surface area is required. [15A NCAC 02H .0506(b)(1)] 3. Please describe how wetland hydrology will be maintained in the wetlands and streams downgradient of the proposed wetland fill areas as well as in the wetland upgradient of proposed impact W4, particularly considering stormwater will be routed away from the streams and wetlands not proposed for impact. [15A NCAC 02H .0506(b)(3)] 4. Please provide a figure depicting the location of the stormwater basin outlets. [15A NCAC 02H .0502(a)(9)] Pursuant to Title 15A NCAC 02H .0502(e), the applicant shall furnish all of the above requested information for the proper consideration of the application. Please provide your response by September 9, 2022. If all of the requested information is not received, the Division will be unable to approve the application and it will be denied as incomplete. The denial of this project will necessitate reapplication to the Division for approval, including a complete application package and appropriate fee. Feel free to contact me if you have any questions. Andrew W. Moore, PG Environmental Specialist II — Asheville Regional Office Water Quality Regional Operations Section NCDEQ — Division of Water Resources 828 296 4684 office email: Andrew.W.Moore@ncdenr.gov 2090 U.S. Hwy. 70 Swannanoa, N.C. 28778 Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties. 3