HomeMy WebLinkAboutNO Written Concurrence_20210447_B-5721 - Replacement of Bridge 124 on SR 2177 over Mayo River
Carpenter,Kristi
From:Conchilla, Ryan
Sent:Tuesday, October 18, 2022 12:11 PM
To:Dilday, Jason L
Cc:Turchy, Michael A; Carpenter,Kristi; David.E.Bailey2@usace.army.mil
Subject:20210447_B-5721 - Replacement of Bridge 124 on SR 2177 over Mayo River
Attachments:20210447_ B-5721 _ Rockingham _ Permit Application Distribution.pdf
Jason,
Good afternoon. The USACE has confirmed use of the NWP 14 for the project as requested (email attached).
The proposed project impacts do not exceed thresholds listed in the corresponding WQGC 4246, and therefore written
certification will not be needed. No additional approval is required from our office.
Let me know if you have any questions or if I can provide additional assistance.
Thanks-
Ryan Conchilla, PWS
Environmental Specialist II
401 and Buffer Transportation Permitting Branch (DOT Divisions 7+8)
Division of Water Resources, NC Department of Environmental Quality
919-707-9111 office
Ryan.Conchilla@ncdenr.gov
From: Carpenter,Kristi <kristilynn.carpenter@ncdenr.gov>
Sent: Friday, October 14, 2022 11:27 AM
To: Dilday, Jason L <jldilday1@ncdot.gov>
Cc: Conchilla, Ryan <ryan.conchilla@ncdenr.gov>; Turchy, Michael A <maturchy@ncdot.gov>
Subject: RE: review fee for B-5721 - Replacement of Bridge 124 on SR 2177 over Mayo River DWR 20210447 Version 1
Jason,
I’m going to let Ryan respond to that one as the reviewer, but please keep me in the loop so I will know how to keep the
project updated correctly in our system.
Thanks,
Kristi Lynn
Kristi Lynn Carpenter
Administrative Assistant
1
401 & Buffer Transportation Permitting Branch
Department of Environmental Quality
Division of Water Resources
kristilynn.carpenter@ncdenr.gov
th
512 N Salisbury Street, 12 Floor
1617 Mail Service Center
Raleigh, NC 27699-1617
Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental Quality has
adjusted operations to protect the health and safety of the staff and public. Many employees are working remotely or
are on staggered shifts. To accommodate these staffing changes, all DEQ office locations are limiting public access to
appointments only. Please check with the appropriate staff before visiting our offices, as we may be able to handle your
requests by phone or email. We appreciate your patience as we continue to serve the public during this challenging
time.
From: Dilday, Jason L <jldilday1@ncdot.gov>
Sent: Friday, October 14, 2022 11:06 AM
To: Carpenter,Kristi <kristilynn.carpenter@ncdenr.gov>
Cc: Conchilla, Ryan <ryan.conchilla@ncdenr.gov>; Turchy, Michael A <maturchy@ncdot.gov>
Subject: RE: review fee for B-5721 - Replacement of Bridge 124 on SR 2177 over Mayo River DWR 20210447 Version 1
Kristi,
Can you explain what the trigger is for requiring a written certification for this project? We thought we had interpreted
it correctly.
Thanks,
Jason
From: Carpenter,Kristi <kristilynn.carpenter@ncdenr.gov>
Sent: Thursday, October 13, 2022 10:35 AM
To: Dilday, Jason L <jldilday1@ncdot.gov>
Cc: Conchilla, Ryan <ryan.conchilla@ncdenr.gov>
Subject: review fee for B-5721 - Replacement of Bridge 124 on SR 2177 over Mayo River DWR 20210447 Version 1
Jason,
After application review, it has been determined that the application submitted for the subject project as a For the
Record Only project needs a written Individual Certification.
I currently have a WBS Element of 45677.1.1 that I can charge the $240.00 review fee against if you could verify that
fund code to still be the correct code.
Please feel free to reach out if you need to discuss the need for written IC.
I have copied Ryan Conchilla on this email as the reviewer.
Thanks,
Kristi Lynn
2
Kristi Lynn Carpenter
Administrative Assistant
401 & Buffer Transportation Permitting Branch
Department of Environmental Quality
Division of Water Resources
kristilynn.carpenter@ncdenr.gov
th
512 N Salisbury Street, 12 Floor
1617 Mail Service Center
Raleigh, NC 27699-1617
Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental Quality has
adjusted operations to protect the health and safety of the staff and public. Many employees are working remotely or
are on staggered shifts. To accommodate these staffing changes, all DEQ office locations are limiting public access to
appointments only. Please check with the appropriate staff before visiting our offices, as we may be able to handle your
requests by phone or email. We appreciate your patience as we continue to serve the public during this challenging
time.
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
3