From: Jennifer Robertson <jrobertson@atlasenvi.com>
Sent: Friday, September 30, 2022 10:10 AM
To: David.E.Bailey2@usace.army.mil
Cc: Homewood, Sue; Jacob Sinclair; Holden Sabato; Shane Metzler
Subject: [External] RE: Reedy Fork Stream Enhancement
Attachments: Reedy As Built.pdf, Post Construction Photo Log Compressed.pdf
Follow Up Flag: Follow up
Flag Status: Flagged
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
David/Sue,
Please see attached the as -built survey and photo log for the Reedy Fork Stream Enhancement project. If all
looks good to you all, we will follow up next year for the first annual monitoring report.
Thank you,
Jennifer L Robertson, President
ATLAS Environmental, Inc.
338 S. Sharon Amity Road #411
Charlotte, NC 28211
(704) 512-1206 office
(828) 712-9205 mobile
www.atiasenvi.com
Offices in Asheville and Charlotte
ONMENTAL
From: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>
Sent: Monday, September 19, 2022 10:13 AM
To: Jennifer Robertson <jobertson@atlasenvi.com>
Cc: sue. homewood@ncdenr.gov; Jacob Sinclair <jsinclair@atlasenvi.com>; Holden Sabato
<holdensabato@silvermangroup.net>; Shane Metzler<ShaneMetzler@silvermangroup.net>
Subject: RE: Reedy Fork Stream Enhancement
Sounds good, Jennifer. Thanks for keeping us up to date.
-Dave Bailey
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Mobile: (919) 817-2436
Email: David. E.Bailey2@usace.army.miI
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is
located at: https://regulatory.ops.usace.army.mil/customer-service-survey/
Thank you for taking the time to visit this site and complete the survey.
From: Jennifer Robertson <iobertson@atlasenvi.com>
Sent: Monday, September 19, 2022 8:40 AM
To: Bailey, David E CIV USARMY CESAW (USA)<David.E.Bailey2@usace.army.mil>
Cc: sue. homewood@ncdenr.gov; Jacob Sinclair <isinclair@atlasenvi.com>; Holden Sabato
<holdensabato@silvermangroup.net>; Shane Metzler<ShaneMetzler@silvermangroup.net>
Subject: [URL Verdict: Unknown] [Non-DoD Source] RE: Reedy Fork Stream Enhancement
David/Sue,
Good morning! Construction of the stream enhancement project is complete. As far as I know Wildlands will
be planting the live stakes in January 2023. Morgan Corp is completing the as -built survey. Atlas will be back
onsite this Wednesday to collect field data and photographs for the initial report per your email below.
Thank you,
Jennifer L Robertson, President
ATLAS Environmental, Inc.
338 S. Sharon Amity Road #411
Charlotte, NC 28211
(704) 512-1206 office
(828) 712-9205 mobile
www.atiasenvi.com
Offices in Asheville and Charlotte
RONMENTAL
From: Bailey, David E CIV USARMY CESAW (USA)<David.E.Bailey2@usace.army.mil>
Sent: Thursday, August 18, 2022 11:58 AM
To: Jennifer Robertson <iobertson@atlasenvi.com>
Cc: sue. homewood@ncdenr.gov; Jacob Sinclair <isinclair@atlasenvi.com>; Holden Sabato
<holdensabato@silvermangroup.net>; Doug Keesee <dougkeesee@silvermangroup.net>
Subject: RE: Reedy Fork Stream Enhancement
Hi Jennifer, and thank you for the detailed description of events. Based on this information and our discussion on
Tuesday, the Corps is amenable to extending the deadline for completion of all aspects of the Stream CH 100 relocation.
As such, Special Condition 2 of the attached Nationwide Permit (NWP) 39 verification, dated 1/21/2022, has been
revised to state the following:
2. Stream CH 100 must be relocated using natural channel design techniques. The approved stream relocation is shown
on Permit Figures 7 and 8 of the enclosed plans. This stream must be relocated according to the plans and descriptions
shown on Permit Figures 8 through 20 of the enclosed plans. These activities shall be completed no later than September
16, 202Z with the exception of live stake planting wherever referenced, which shall be completed no later than March
31, 2023. Once the stream relocation work is complete, you must submit an initial report within 30 days detailing the
work completed, including a photograph record sufficient to document the entirety of the stream relocation reach.
All other Special Conditions and terms and conditions of the above referenced NWP 39 verification remain valid and
unchanged.
Please let me know if you have any questions.
-Dave Bailey
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Mobile: (919) 817-2436
Email: David. E.Bailey2@usace.army.miI
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is
located at: https://regulatory.ops.usace.army.mil/customer-service-survey/
Thank you for taking the time to visit this site and complete the survey.
From: Jennifer Robertson <iobertson@atlasenvi.com>
Sent: Thursday, August 18, 2022 11:26 AM
To: Bailey, David E CIV USARMY CESAW (USA)<David.E.Bailey2@usace.army.mil>
Cc: sue. homewood@ncdenr.gov; Jacob Sinclair <isinclair@atlasenvi.com>
Subject: [URL Verdict: Neutral][Non-DoD Source] RE: Reedy Fork Stream Enhancement
David,
Jacob met with folks from Morgan Corp and folks from Wildlands Construction to what we thought was going to
be to kick off the stream relocation construction work yesterday. Morgan Corp is the general contractor for the
developer. We had been frantically trying to get our information to Wildlands the day before as Morgan Corp
had not given them our plan documents. It became apparent quickly that we were not going to be able to start
construction this week. Based on current site conditions and the elevation of the SCM outlet at the bottom of
our relocation reach we need to steepen our slopes a little.
Here is a summary of Jacob's notes back to Morgan Corp and Wildlands last night.
As requested during the conclusion of today's site meeting this email includes a summary of discussions
related to the stream relocation to continue moving the project forward in a timely manner.
- Atlas will coordinate with regulators as necessary regarding any additional grade control structures and
time limitations due to unforeseen site constraints and requirements.
- Wildlands has expressed concerns about completing the project by the USACE deadline.
o As we discussed today, 1 do not anticipate David Bailey (USACE) having issues approving a 2
week extension so long as efforts to progress the project are occurring.
- Wildlands has expressed concerns about the stability of the upper 157 feet of the restoration reach.
o Atlas will add 5 additional grade control structures to the design between station 0+00 to
approximately station 1 +78.
- Atlas observed and approved of the stockpiled substrate material.
- Due to the relocation being positioned within a DOT right-of-way an As -Built will be required to be
submitted to DOT.
o Due to this, and other limitations, it was determined there was not enough information to begin
the construction today.
- Atlas was tasked to provide the following additional information:
o Station and elevation data
o Head and tail of riffles
o Radius points along bends
o XML/DXF files to stake alignment in the field
- Wildlands has requested the alignment be staked out in the field based on the above additional
information.
We need an extension until September 161" to get this work completed but for the live stake
installation. Please let us know if this extension is granted. If you have any questions or need to discuss the
specifics give me a call. Thanks!
Thank you,
Jennifer L Robertson, President
ATLAS Environmental, Inc.
338 S. Sharon Amity Road #411
Charlotte, NC 28211
(704) 512-1206 office
(828) 712-9205 mobile
www.atiasenvi.com
Offices in Asheville and Charlotte
ONMENTAL
From: Bailey, David E CIV USARMY CESAW (USA)<David.E.Bailey2@usace.army.mil>
Sent: Wednesday, August 17, 2022 8:46 AM
To: Jennifer Robertson <Robertson@atlasenvi.com>
Cc: sue.homewood@ncdenr.gov
Subject: RE: Reedy Fork Stream Enhancement
Thanks for the update, Jennifer. Glad to hear it's getting underway. Will the work (with the exception of the live stake
planting) be completed no later than August 31, 2022, per the permit Special Condition?
-Dave Bailey
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Mobile: (919) 817-2436
Office: (919) 554-4884, Ext. 30.
Fax: (919) 562-0421
Email: David. E.Bailey2@usace.army.miI
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is
located at: https://regulatory.ops.usace.army.mil/customer-service-survey/
Thank you for taking the time to visit this site and complete the survey.
From: Jennifer Robertson <iobertson@atlasenvi.com>
Sent: Tuesday, August 16, 2022 8:19 PM
To: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>; sue.homewood@ncdenr.gov
Subject: [URL Verdict: Neutral][Non-DoD Source] Reedy Fork Stream Enhancement
David/Sue,
Just wanted to give you all a heads up that the stream enhancement construction work will begin
tomorrow. We will be working with Riley and his folks from Wildlands as the contractor.
Thank you,
Jennifer L Robertson, President
ATLA,, Environmental, Inc.
338 S. Sharon Amity Road #411
Charlotte, INC 28211
(704) 512-1206 office
(828) 712-9205 mobile
www.atiasenvi.com
Offices in Asheville and Charlotte
ONMENTAL
11282 'dN a}}01.4ny3 b960f6L- '8998I'9£ :sa�nwi10.4000 o4-ngnS uaploH uW :u}}d
llb# 'pd A}Iwy uo.AnyS 'S 8££
1V1NIMO t712L2 SN 'q-IwwnS SUMOJ9 dnouq unwuanIIS aqi :uoJ
arnuand OiwwnS 9969
SVIII&6L;)
d/N :pa4-npdg �
>� .,I O j ! p a a N 2202 '92 .4agwa}daS :a}nQ .I
oc
L�J
LJ z
LLJ J s e
z
LL I > a a
LJ W
l� J J II � Y o
LLJ o LD Oo� L) z
o o Q o 0
/ a
J
7 11
1 ,1
C
6
6£
e
Stream Relocation Photos: March 12, 2021 During Delineation
A
a
f-
i� ,
01.12.2021 OT 47
r
�.
:.y�--_��- - •+,way a � -- -. -
Stream Relocation Photos: August 24
fir. �. .• �k�'w .. `� i
PV
.ice ,_ ��;.� � •r... ��.Y.
i
Stream Relocation Photos: August 24-29, 2022 During Construction
Simi=
OPF7
ANA
..... . . . . . . . . . . . . . . . . .
fit
_A
Stream Relocation Photos: August 24-29, 2022 During Construction
Stream Relocation Photos: September 21, 2022 After Construction
.:�... _.� _ � i -�- •--'. �! •, •� Tit:.. '�?tiA
or
;�?'_ �.: - .JYT L.'•
Overview of of relocation
Cross vane at downstream extent of relocation near
station 4+20
Log step above cross vane near station 3+94
Herbaceous vegetation starting to grow
,1Criit►��
r-i
�
-
F
Looking upstream
Log Step
Stream Relocation Photos: September 21, 2022 After Construction J
Boulder toe at log step near station 2+38
%-4
I
Log step near station 1+77
Boulder toe at log step near station 1+57
..
'r
Upper extent of relocation.
Ditch above relocation reach