HomeMy WebLinkAbout20210915 Ver 1_Compliance Evaluation Inspection_20221012Wetland Inspection Report
Project Num: 20210915 Version: 1
Project Name: Reedy Fork Industrial - 5955 Summit Avenue, Browns
County: Guilformmit
Status: Issued
Project Type: Industrial / Commercial /
Business
Region: Winston-Salem
Location: Reedy Fork Industrial - 5955 Summit Avenue, Browns Summit
Latitude: +36° 10' 48"
SW Plan Location:
Site Owner Name: SI Reedy Fork
Inspection Date: 10/12/2022
Reason for Inspection: Follow-up
Inspection Type: Site Inspection (non -DOT)
Inspection Contact Person:
On -Site Representative(s):
Primary Inspector: Sue L Homewood
Secondary Inspector(s):
Title:
Facility Compliance Status: El Compliant Not Compliant
Program Areas: Standards/Sediment
Question Areas:
Unpemittable Activities
Inspection Summary:
Longitude: -79° 42' 00"
Phone:
Phone: 336-776-9694
page 1
Site Number: 20210915 Owner: Lacz, Dan
Inspection Date: 10/12/2022 Inspection Type: Site Inspection (non -DOT) Reason for Visit: Follow-up
Unpermittable Activities Yes No NA NE
# Note: This section should be completed only if the impact is unpermittable (eg. Sediment, draining
wetlands, etc.).
Is stream(s) free of unpermittable impacts? ❑ • ❑ ❑
Is wetland(s) free of unpermittable impacts? • ❑ ❑ ❑
Is open water(s) free of unpermittable impacts? ❑ ❑ • ❑
Are other standards being met (turbidity, pH, etc.) in all surface waters onsite? • ❑ ❑ ❑
Are surface waters on the site free of illegal discharges? • ❑ ❑ ❑
Comment: Inspected 3 sewer line crossings. At 2 of them the crossings are non -compliant and there are significant
sediment deposits within downstream waters. See USACE email/notes for more details
page 2
Wetland Inspection Report
Project Num: 20210915 Version: 1
Project Name: Reedy Fork Industrial - 5955 Summit Avenue, Browns
Summit
County: Guilford
Status: Issued
Project Type: Industrial / Commercial /
Business
Region: Winston-Salem
Location: Reedy Fork Industrial - 5955 Summit Avenue, Browns Summit
Latitude: +36° 10' 48"
SW Plan Location:
Site Owner Name: SI Reedy Fork
Inspection Date: 10/12/2022
Reason for Inspection: Follow-up
Inspection Type: Site Inspection (non -DOT)
Inspection Contact Person:
On -Site Representative(s):
Primary Inspector: Sue L Homewood
Secondary Inspector(s):
Title:
Facility Compliance Status: El Compliant Not Compliant
Program Areas: 401 (includes isolated/non-404)
Question Areas:
Permit (401 WQC)
Inspection Summary:
Longitude: -79° 42' 00"
Phone:
Phone: 336-776-9694
page 1
Site Number: 20210915 Owner: Lacz, Dan
Inspection Date: 10/12/2022 Inspection Type: Site Inspection (non -DOT) Reason for Visit: Follow-up
Permit (401 WQC)
Does the impact(s) match what was approved in the 401 WQC or non 404 permit?
Are the culverts and/or filled areas installed properly?
Is the site compliant with additional conditions of the 401 WQC or non 404 permit?
Yes No NA NE
▪ •
❑ ❑•▪ •
Comment: Inspected stream relocation: some pools insufficient depth, water piping under some riffles, embedded
riprap not embedded and tie in to natural channel is steep slope with rock thrown on top.
Inspected 3 sewer line crossings. 1 is acceptable, 1 appears to have banks that have completely
collapsed into the channel, 1 is full of sediment caught behind 2 check dams. See USACE emails/notes
for more details
page 2