HomeMy WebLinkAbout20211588 Ver 1_More Information Received_20211230CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to Report Spam. <mailto:report.spam@nc.gov>
Hi Colleen,
1. It is my understanding that the project engineers are still addressing the request for additional information submitted by the US Army Corps of Engineers via email on November 29th,
2021. Is this correct? If so, please provide a copy of the final response to the Division. [15A NCAC 02H .0502(c)] - Yes, they had to resubmit to City of Raleigh and get back to me
when they have the revised maps.
2. Please provide additional information on how the two drainage conveyances listed as “Impact Area 2- Drainage - Deemed Allowable” fit under Item 9 of the buffer rules. [15A NCAC 02B
.0714(9)] - I'll work on this.
3. The proposed road crossing in Impact Area 1 does not appear to be a perpendicular crossing of a stream or other surface water. Road impacts other than perpendicular crossings of streams
and other surface waters require mitigation. Please provide additional information to demonstrate that this crossing is a perpendicular crossing or provide a statement of availability
from a mitigation bank. [15A NCAC 02H .0714(11)] - Get back to you on this.
4. Has a stream/buffer determination been performed for this site by DWR? If so, please provide a copy of the Buffer Determination Letter. [15A NCAC 02H .0502(c)] - I am not finding
that one was conducted, but I will circle back with the others and let you know.
Thanks, Ian
Ian McMillan, PWS, GISP, CPM
Sage Ecological Services, Inc.
919-608-3156
IMcMillan@SageEcological.com
________________________________
From: Cohn, Colleen M <colleen.cohn@ncdenr.gov>
Sent: Thursday, December 30, 2021 10:19 AM
To: Ian McMillan <imcmillan@SAGEECOLOGICAL.COM>; Sean Clark <SClark@SAGEECOLOGICAL.COM>
Cc: George.L.Phillips@usace.army.mil <George.L.Phillips@usace.army.mil>
Subject: 500 Rawls Drive DWR#20211588
Good morning!
I am reviewing the above referenced project, and in order to complete the review, some additional information is required:
1. It is my understanding that the project engineers are still addressing the request for additional information submitted by the US Army Corps of Engineers via email on November 29th,
2021. Is this correct? If so, please provide a copy of the final response to the Division. [15A NCAC 02H .0502(c)]
2. Please provide additional information on how the two drainage conveyances listed as “Impact Area 2- Drainage - Deemed Allowable” fit under Item 9 of the buffer rules. [15A NCAC 02B
.0714(9)]
3. The proposed road crossing in Impact Area 1 does not appear to be a perpendicular crossing of a stream or other surface water. Road impacts other than perpendicular crossings of streams
and other surface waters require mitigation. Please provide additional information to demonstrate that this crossing is a perpendicular crossing or provide a statement of availability
from a mitigation bank. [15A NCAC 02H .0714(11)]
4. Has a stream/buffer determination been performed for this site by DWR? If so, please provide a copy of the Buffer Determination Letter. [15A NCAC 02H .0502(c)]
Thank you,
Colleen Cohn
Environmental Specialist II
North Carolina Department of Environmental Quality
Division of Water Resources
Raleigh Regional Office
3800 Barrett Drive
Raleigh, NC 27609
Office: 919-791-4258
E-mail correspondence to and from this address may be subject to the
North Carolina Public Records Law and may be disclosed to third parties.