HomeMy WebLinkAboutWQ0043822_Application (FTSE)_20221011DWR
Division of Water Resources
State of North Carolina
Department of Environmental Quality
Division of Water Resources
Flow Tracking for Sewer Extension Applications
(FTSE 10-18)
Entity Requesting Allocation: Town of Aberdeen
Project Name for which flow is being requested: Duck's Landing
More than one FTSE may be required for a single project if the owner of the WWTP is not responsible for all pump
stations along the route of the proposed wastewater flow.
I.
Complete this section only if you are the owner of the wastewater treatment plant.
a. WWTP Facility Name: Moore County Water Pollution Control Plant
b. WWTP Facility Permit #: NC 0037508
All flows are in MGD
c. WWTP facility's permitted flow 10.0000
d. Estimated obligated flow not yet tributary to the WWTP 0.94137
e. WWTP facility's actual avg. flow 5.17000
f. Total flow for this specific request 0.01440
g. Total actual and obligated flows to the facility 6.12577
h. Percent of permitted flow used 61.2577
II. Complete this section for each pump station you are responsible for along the route of this proposed
wastewater flow.
List pump stations located between the project connection point and the WWTP:
Pump Pump
Station Station
(Name or Permit
Number) No.
Firm
Capacity, *
MGD
(A)
Design
Average
Daily Flow**
(Firm / pf),
MGD
(B) (C) (D)=(B+C) (E)=(A-D)
Obligated,
Approx. Not Yet Total Current
Current Tributary Flow Plus
Avg. Daily Daily Flow, Obligated Available
Flow, MGD MGD Flow Capacity***
* The Firm Capacity (design flow) of any pump station is defined as the maximum pumped flow
that can be achieved with the largest pump taken out of service.
** Design Average Daily Flow is the firm capacity of the pump station divided by a peaking factor
(pf) not less than 2.5, per Section 2.02(A)(4)(c) of the Minimum Design Criteria.
*** A Planning Assessment Addendum shall be attached for each pump station located
between the project connection point and the WWTP where the Available Capacity is < 0.
Downstream Facility Name (Sewer): Moore County Public Utilities
Downstream Permit Number: WQCS00034
Page 1 of 6
FTSE 10-18
III. Certification Statement:
I Randy G. Gould, PE certify to the best of my knowledge that the addition of
the volume of wastewater to be permitted in this project has been evaluated along the route to the receiving
wastewater treatment facility and that the flow from this project is not anticipated to cause any capacity
related sanitary sewer overflows or overburden any downstream pump station en route to the receiving
treatment plant under normal circumstances, given the implementation of the planned improvements
identified in the planning assessment where applicable. This analysis has been performed in accordance
with local established policies and procedures using the best available data. This certification applies to
those items listed above in Sections I and II plus all attached planning assessment addendums for which I
am the responsible party. Signature of this form certifies that the receiving collection system or treatment
works has adequate capacity to transport and treat the proposed new wastewater.
_e,,
Signing Official 1gnafure
CGbr
Title of Signing Official
9
22
Date
Page 2 of 6
FTSE 10-18